Critical Equipment Inspections
  • Xstrata Coal South Africa

2
Contents
  • Historical situation
  • ATCOM Fatal accident 23/02/2004
  • Identification of critical equipment and
    installations
  • Inspection criteria used
  • Out sourcing contract work
  • Tagging of equipment

3
Historical review
  • Pre use inspection lists for equipment
  • Log book system
  • No physical proof of inspections conducted
  • Contractors pack requirements

4
Critical equipment
  • List compiled of critical equipment and
    installations
  • Inspection criteria developed

5
ATCOM 23 February 2004
  • Incident -Electrocution
  • Work planned to replace water column
    contractors pack completed
  • Task delayed Making up of pipes work extended
    into evening
  • Changing conditions rain, darkness and using
    different type of tools as planned
  • Sub contractor bring additional undisclosed
    equipment onto mine
  • Faulty extension lead and inadequate earth
    leakage protection
  • Incident
  • Medical condition of now deceased
  • Certificate of compliance for electrical
    installations


6
Short Comings identified
  • Appointment of responsible persons to do various
    inspections ( plant / opencast working)
  • Listing of critical equipment and installations
  • Proof that inspections were carried out not a
    paper exercise
  • Inspection of contractors/ sub contractors
    equipment

7
Tagging of equipment and out sourcing of
inspection authority
  • Appointment of Gear Industry legal appointment
  • Critical inspection lists developed and signed
    off mine engineers (include vehicle checks)
  • Quality inspections carried out of facility by
    mine engineers
  • Requirement in contractors pack that inspections
    were conducted and equipment tagged
  • Three month inspection cycle observed
  • Pre-use inspection system still in place for
    daily checks

8
Inspection Tagg

9
Results of inspections
  • Past four months
  • 28 rejection on vehicles breaks and lights
  • 23 rejection on vehicles fire extinguishers
  • 26 rejection on electrical equipment
  • 25 on hydraulic/ lifting and other equipment
  • Improvement on the quality of equipment from
    contractors that have been through the process