Title: CERTIFIED CLEAN ROOM
1CERTIFIED CLEANROOM
2Clean Room Certified by
NEBB (National Environmental Balancing Bureau)
3Standard Clean Room
- Federal Standard 209E ( FS 209E )
- ISO Standard ( ISO 14644 1 )
- Good Manufacturing Practice (GMP)
4Federal Standard 209E (FS-209E)
5ISO Standard ( ISO 14644 1 )
6Good Manufacturing Practice (GMP)
7Test Description
- Airborne Particle Count Test
- Airflow Velocity Test Under
- Temperature Test
- Relative Humidity Test
- Room Pressurization Test
- Scan Leak Test Hepa
- Scan Leak Test PAO
- Light Intensity Level Test
- Sound Pressure Level Test
8Type of Condition
- AS BUILT
- The condition where the installation is complete
with all services connected and functioning but
with no production equipment, materials, or
personnel present - AT REST
- The condition where the installation is complete
with equipment installed and operating in a
manner agreed between the customer and supplier,
but with no personnel present - OPERATIONAL
- The condition where the installation is
functioning in the specified manner, with the
specified number of personnel present and working
in the manner agreed upon
9Certify Clean room Testing
10Airborne Particle Test
11Airflow Velocity Test
12Temperature Relative Humidity Test
13Room Pressurization Test
14Scan Leak Test
15Instrument
16Test Procedures
17Procedure ForAirborne Particle Count
- Purpose
- To measure the airborne particulate level in the
Cleanroom and to determine the room Cleanliness - Classification as per Federal Standard 209E.
- Instrumentation and Equipment
- PMS Lasair II / 310A counter
- Specification
- Test Condition At Rest / As Built / Operational
- Allowable Count Limit for each particle size
- Class 1,000 lt 1,000 count/ft3 _at_ 0.5 µm
greater - lt 7 count/ft3 _at_ 5.0
µm greater - Class 100 lt 300 count/ft3 _at_
0.3 µm greater - lt 100 count/ft3 _at_ 0.5 µm
greater - Procedure
- Reference Federal Standard 209E
- NEBB Procedural Standard for Certified Testing
Of Cleanroom - This test was conducted after all the other tests
had been completed. - The Cleanrooms were purged for at least 12 hours
before testing commences. - The Cleanrooms were divided into test grids
according to their Cleanliness Class as per
Federal Standard 209E as follow - - Class 1,000 Grid size not exceeding
31.6 sq ft3.
18Procedure For Temperature Relative Humidity
Test
- Purpose
- To determine the capability of the Cleanroom air
handling system to maintain the air temperature
and relative humidity - within specified limits.
- Instrumentation and Equipment
- TSI Thermal Hygrometer 8722-M-GB
- Specification
- Average Temperature 20 24 oC
- Average Relative Humidity 40 70
-
- Procedure
-
- All airflow balancing was completed prior to
this test. - The air conditioning system was operated
continuously for at least 24 hours prior to the
commencement of the test. - The Cleanrooms were divided into test grids of
no larger than 100 ft2 - The temperature RH meter was held at the
center of the test grid at 1 meter above the
floor. - When an obstruction was encountered, the
measurement was taken at 6 above the
obstruction.
19Procedure ForAirflow Velocity Test
- Purpose
- To determine the airflow velocity of the filters
installed in the Cleanrooms. - Instrumentation And Equipment
- Airdata Electronics Micromanometer, ADM-870
- Specification
- Test Condition At Rest / As Built / Operational
- Two (2) velocity values are to be taken for each
2x4 HEPA filter at 75 mm. from the filter
surface - Average 0.41 - 0.61 m/s
- Two (2) velocity values are to be taken for each
2x4 HEPA filter at 150 mm. from the filter
surface. (Under Laminar Flow Hood) - Average 0.36-0.56 m/s
-
- Procedure
- Reference IES Recommended Practice,
IES-RP-CC006.2 Testing Cleanrooms - NEBB Procedural Standard for Certified Testing
of Cleanroom -
- Every filter was divided into 2 test grids each.
- The electronics micromanometer was setup with the
Velgrid attachment and the temperature probe for
automatic compensation of air density variation.
20Procedure ForRoom Pressurization Test
- Purpose
-
- To determine the capability of the Cleanroom
system to maintain the specified pressure
differential. -
- Instrumentation and Equipment
- Electronic Micromanometer ADM-870
- Specification
- Test Condition At Rest / As Built / Operational
- Differential Pressure 0.05WG wrt adjacent /
less stringent room - Procedure
-
- All airflow balancing were completed prior to
this test. - All doors into the Cleanroom and the reference
areas were closed throughout the duration of the
test. - The differential pressure between the Cleanroom
and the adjacent room was measured and recorded
with Electronic Micromanometer.
21Procedure ForHEPA Filter Installation Leak Test
- Purpose To verify the absence of bypass leakage
(between filter frame and ceiling grid system) in
the installation of the filters and confirm - that the installed filters are
free of defects and small leaks. - Instrumentation and Equipment
- PMS Lasair II / 310A counter
- Airdata Electronics Micromanometer, AMD-870
- Specification
- Test Condition At Rest / As Built / Operational
- Note
- No additional aerosol challenge will be
introduced to the upstream of the filters being
tested. - Not More than 1 particle at size 0.3 micron and
greater must be detected in the downstream of the
filter systems - For each filter, any repair surface must not
constitute more than 0.5 sq.inch. - Procedure
- Reference IEST Recommended Practice,
IEST-RP-CC001.3 HEPA and ULPA Filters - IEST Recommended Practice, IEST-RP-CC006.3
Testing Cleanrooms - NEBB Procedural Standard for Certified Testing
Of Cleanroom - The filters face velocities were determined to
ensure that they were within the general design
range. - The upstream concentration was taken at 0.3
micron and greater. This was taken for
information only. - Laser Particle Counter with a resolution of 0.3
micron was use for the leak test. The sampling
flow rate of the counter was 1 ft3/min.
- Rectangular particle counter probe was use to
scan the filters. The probe dimension was
selected to achieve iso-kinetic sampling. The
scanning rate used was in accordance to the above
reference.
22Procedure ForHEPA Filter Installation Leak
Test(Photo meter Method)
- Purpose
-
- To insure and confirm that the HEPA filter system
is properly installed by verifying the absence of
bypass leakage - in the installation and the installed filters are
free of defects and pinhole leaks. - Instrumentation and Equipment
- ATI Aerosol Photometer ,Model 2H
- Specification
- Test Condition At Rest / As Built / Operational
- 1 Upstream Concentration
- Minimum value 20 µm/litre
- Preferred Range 10 - 100 µm/litre
- 2 Maximum allowable penetration lt 0.01 of
upstream
23Procedure ForHEPA Filter Installation Leak
Test(Photo meter Method)
Procedure Reference NEBB Procedural Standard
for Certified Testing Of Cleanroom ,2nd Ed
IEST Recommended Practice, IEST-RP-CC006.3
Testing Cleanrooms. 1. The filters face
velocities are first determined to ensure that
they are within the general design range. 2. The
photometer and the aerosol generator are then
set-up according to the manufacturers
instruction. 3. Emery 3004 aerosol is then
generated with the generator and introduce at the
upstream of the filter (s). 4. Upstream
concentration ,in µm / liter, is then measured.
The sampling point should immediately (subject to
physical site constraint) ahead of the
filter under tests. Appropriate adjustment, if
necessary , is made to ensure that the
concentration is within the preferred range. 5.
Once upstream concentration is satisfied and set,
the photometer will be setup for downstream
penetration measurement. 6. Rectangular
sampling probe will be used to scan the filters.
The probe will be held at approximately 1from
the frame and filter surface during
scanning. The maximum concentration level will be
recorded. 7. Upon completion of the tests, the
upstream challenge concentration is sampled again
to ensure consistency of the challenge
throughout the test. 8. Certificate Of Compliance
will be issued for each HEPA filter / filter bank
that meet the required specification . A
sample of the certificate is attached.
24Procedure For Light Intensity Level Test
- Purpose
-
- To determine the light intensity level at working
height level within the Cleanrooms. -
- Instrumentation and Equipment
- Digital Lux Meter LX-50
- Specification
- Test Condition At Rest / As Built / Operational
- Average Light Intensity Level 700 Lux
880 Lux -
- Procedure
- All fluorescent lighting were operated for at
least 100 hours to ensure proper seasoning. - The lighting ware operated continuously for least
2 hours to allow for temperature stabilization
prior to the actual commencement of the test. - The Cleanrooms were divided into test grids of no
larger than 100 ft2. - One reading was taken at the centre of each grid
and at a height of 1 meter above the floor. - When an obstruction was encountered, the
measurement was taken at 6 above the
obstruction. - The readings for all the other grids were taken
and recorded. - The average light intensity level of the
Cleanroom were computed from these data.
25Procedure For Sound Pressure Level Test
- Purpose
- To measure the airborne sound pressure level
within the Cleanroom produced by the basic
Cleanroom - mechanical and electrical systems.
- Instrumentation and Equipment
- Sound Level Meter , Cesva SC-2c
- Specification
- Test Condition At Rest / As Built / Operational
- Average Sound Pressure Level 70 dBA.
-
- Procedure
- All airflow balancing was successfully
completed prior to this test. - All fan filter modules and air conditioning
equipment were switched on before any readings
were taken. - The Cleanrooms were divided into test grids of
no larger than 10x10 - The sound pressure level meter was placed 1
metre above the floor and with the sensor
pointing in the - direction of the operating module.
- The sound pressure level , in dBA, was taken
for each location. - When an obstruction was encountered, the
measurement was taken at 6 above the
obstruction, provided it
26Reference Customer
- Olic
- Kawasumi
- Urgo
- Better Pharma
- Bangkok Hospital
- Siriraj Hospital
- Childen Hospital
- NSTDA
- GHP
- Chulabhorn Research Institute
- Leader Industrial
- NMB
- Compart
- ISCM
- Belton
- Nidec
- Casio
- Johnson Johnson
- WD
- Epson Toyocom
- Seksun Technology
27Reference Customer
- NOK
- JCY
- NHK
- Metal Form
- AGC
- E Tech
- PSC
- Solar Lens
- Hoya
- Transition
- MTEC
- Chulalongkorn University
- Seagate
- Bumrungrad Hospital
- CP Meji
- MEGA Life
- Central Lab
- Sema Technology
- M H
- Min Aik
- Seiko
- Khonkaen Hospital
28THANK YOU
Contact Us At Tel 02-536-5316-8,
02-536-5376-8 Fax 02-536-5354
sales_at_pmt.co.th www.pmt.co.th