Title: PROJECT REPORT
1PROJECT REPORT
- DESIGN CONCEPTS OF BOW STRING GIRDER (40 M SPAN)
OF ROAD OVERBRIDGE AND DESIGN OF SUB STRUCTURE
FOR THE SAME.
2 PRESENTED BY
- 1. R.M.MEENA
- (XEN/C/JU/NWR)
- 2. SIVA KUMAR (AXEN/Designs/MTP/MS/S.R.)
- 3. L.N.LOKHARE
- (AXEN/C/KTT/WCR)
- 4. L.B.SINGH MAURYA
- (Vice Principal/SRETC/TBM/S.R.)
3INTEGRATED COURSE BATCH NO-514
- PROJECT GUIDE
-
- Sri.G. Bansal
- COURSE DIRECTOR
- Sri A.K.Rai
4INTRODUCTION
- On Indian Railway there are 16471 Nos of manned
level crossings and 19284 Nos of unmanned level
crossings as on date. These Level crossings are
affecting the safe effective functioning of
Railways. The Level crossings are the accident
prone zones and causes delay of trains due to
detention by road traffic at gate.
5INTRODUCTION- cont
- There are loss of valuable human life and
Railways properties due to accidents taking place
on this level crossings. Keeping safety point of
view it become necessary to replace these level
crossings by ROB/RUB..
6INTRODUCTION- cont
- Replacing the level crossings with ROB/RUB are
being done by Railways in a phased manner based
upon its TVU. Where ever possible ROB is
preferable over RUB due to its less maintenance,
effective usefulness, even though the initial
cost of ROB is more.
7SCOPE OF THE PROJECT
- The ROB comprises following different structure-
- 1. Main railway span (40 m)
- 2. Approach spans having 20 m spans
- 3. Abutment
- 4. Reinforced earth retaining wall beyond
abutment on the approaches where height is less
than 4.0 m
8SCOPE OF THE PROJECT - cont
- As far as super structure is concerned only
design concept of Bow string girder is
emphasized. However for substructure complete
design is made and enclosed.
9ELEMENTS OF BOW STRING GIRDER
- MAIN I- GIRDER
- Main I- girder is purely a tension member because
of its geometry. This member is proposed as a
prestressed member .The amount the prestressing
required shall be less since the same required
only nullify the tension.
10ARCH MEMBER
SUSPENDERS
MAIN I GIRDER
11ARCH MEMBER
- Arch member is always in compression and hence
RCC is sufficient to take this load. A member
size of 450x900 at supports and 450x600 at crown
is normally sufficient to carry the compression
for this 40 meter span.
12SUSPENDERS
- Since suspenders are pure tension members and it
does not requires any flexural rigidity , these
members can be provided as HTS strands firmly
anchored between main I beams and arch members
13CROSS GIRDER
- Cross girder can be of RCC, which spans between
main I -girders. The spacing of cross girders is
kept as 4.15 meter the span is 8.0 meter. At
the top of cross girder, a continuous slab of
span of 4.15 meter and thickness of 230 mm is
provided. Over the slab road-wearing surface as
per IRC, specification is provided.
14C LINE OF SPAN
L
C LINE OF BEARING
BOW STRING
L
CROSS GIRDER
4150
8m
41500
PLAN AT DECK LEVEL
15LOADING
- Live load
- Load as per IRC-6
- Combinations are
- 1. Single lane 70R wheeled/track vehicle
- 2. Two lane IRC class A, wheeled
16ADVANTAGES OF BOW STRING OVER DECK TYPE GIRDERS
- There is some considerable savings in depth of
construction in case of bow string girder
compared to typical deck type girder Due to
reduced depth of construction, the over all
length of ROB get reduced and overall economy
achieved
177500
ROAD SURFACE
2500
DEPTH OF CONSTRUCTION2.50m
BOX GIRDER TYPE ROB
187500
BOW STRING GIRDER
ROAD SURFACE
2400
1000
DEPTH OF CONSTRUCTION1.0m
BOW STRING GIRDER TYPE ROB
19DESIGN CONCEPT OF BOW STRING GIRDER
- LIVE LOAD
- Like our railway bridge rules, these IRC codes
does not provide any EUDL,so for the above
rolling loads maximum bending moment and shear
force shall be worked out using STAAD-PRO 2003
software. However a manual calculation is also
shown. Due provision for impact is also
considered as per the code.
20DEAD LOAD
- This comprise of dead load of all element of bow
string span ,the carriage way wearing coat, foot
path and other miscellaneous load such as cables,
parapets, crash barriers have been considered
21 WIND LOAD
- Wind load is arrived at as per IS 875
part-III.the wind intensity multiplied by the
projected area gives the wind load on the
structure.
22SUB STRUCTURE
- The substructure consists of two numbers of
1.80 meter dia column spaced at 8.0 meter apart.
The depth of trestle beam is fixed as 1.25 meter
for stiffness and other practical consideration
such as requirement during construction and
replacement of bearing.
238.0m
1.25m
6.525m
COLUMN 1.80m dia
1.80m
Rail level
PILE CAP
PILE 1.0m dia
ELEVATION OF SUBSTRUCTURE
4
24LOADS AND OMENTS ON COLUMN
- As we know the the column is critical at the
pile cap level . Maximum moments will come at
this level which are all explained through the
following sketches. Algebraically adding all the
moments the column section is designed
25SESMIC LOAD
- Lateral Seismic Coefficient0.04
- Importance Factor 1.5 (for important bridges)
- Foundation system factor 1.0 (for pile
foundation) - Design for seismic force.04x1.5x1.0.06
26SESMIC LOAD
- Code followed IRC 78
- Even though the seismic load does not affect the
super structure, the impact on the substructure
design is considerable. - Seismic Zone III
27Adjoining span -20m
Bow string span- 40m
Lumped mass of super structure
Lever arm
Pile cap
1.DUE TO DEAD LOAD
Pile
28Adjoining span -20m
Bow string span- 40m
Lumped mass of trestle beam
Lever arm
Pile cap
2.DUE TO DL OF SUB STRUCTURE
Pile
29Adjoining span -20m
Bow string span- 40m
y
x
Lower load
Higher load
Un balanced moment higher load y-lower load
x
Pile cap
Pile
30Adjoining span -20m
Bow string span- 40m
1.83 m
Lever arm
Pile cap
4. DUE TO LIVE LOAD
Pile
31Foundation
- The foundation system consists of four no of 1.0m
dia pile spaced at 3.0m apart. The piles are
proposed to be founded on hard strata, which is
available at 25.0m depth. The piles are of bored
cast in situ.
32Foundation
-
- Max. vertical Load in pile workout to be -
- under seismic condition 264 tonnes
- under normal loads 214
tonnes - lateral load per pile 14
tonnes
33Foundation
- Vertical load bearing capacity of pile 320 t
- The above capacity of piles is based on soil
capacity at site. The pile derives its capacity
both from friction as well as end bearing.
34FOUNDATION
- Reinforcement design of pile
- The length of fixity of pile below ground level
Le is found based on lateral modulus of
subgrade reaction of the pile - The moment on pile Horizontal load x Le
- Based on the moment and the vertical load on the
pile,the reinceforcement of the pile is designed
35Pile cap
L12.5m
Le
5.318m
L22.5m
CALCULATION OF LENGTH OF FIXITY OF PILE