Title: Caltex Refinery Commitment to Operational Excellence
1- Caltex Refinery Commitment to Operational
Excellence - A Presentation to the
- Environmental Affairs and Tourism
- Parliamentary Portfolio Committee
- By
- Steve Woodruff
- Caltex Refinery General Manager
- 23 August 2005
2Safety Moment
3Focus on injury prevention
Historical Learning Look-back
Forward-Looking Predictive Preventative
To prevent injuries, we must focus below the line
4- An overview of the Caltex Refinery
5Caltex refinery then and now
1966 Refinery started up (30 000
bpsd). 1970 More units added (50 000
bpsd). 1975 Capacity increase (58 000
bpsd). 1977 Debottleneck (62 000
bpsd). 1978 North refinery built (110 000
bpsd).
1990 Instrument modernisation project. 1992 Octa
ne enhancement project. 1995 Unleaded petrol
project. 1996 Jet fuel project. 1998 New steam
boiler. 2000 Tailgas treating unit. 2002 Sulphur
pastillation project. 2005 Clean fuels
project. PMG note Graphics not included
6Chevron corporate vision
- Vision for Operational Excellence
- To be recognised and admired by industry and the
communities in which we operate as world-class in
safety, health, environment, reliability and
efficiency.
Dave OReillyChairman and CEOChevron Corporation
7Caltex refinery mission2005 2007
0 0 84.5 100 PMG note Graphics not
included
8 Refinery mission
0 Injuries 0 Incidents 84.5 Plant
utilisation 100 Engagement with employees
and external stakeholders
9- Our journey to world class environmental
performance started 10 years ago
10More than R450 million invested in environmental
improvements
11- Progressive reduction in air emissions
12A 79 reduction in sulphur dioxide emissions
13Refinery Burner Fuel Reduction of Sulphur
Dioxide Emissions
- R 30 million
- Control sulphur in burner fuel below 2 wt
sulphur - Minimise Fuel Oil firing
- Maximum Gas firing
- Gas is low in sulphur content
- Sulphur in burner fuel part of crude selection
- Future Plans
- Work towards 100 gas firing
14Sulphur Recovery Units Reduction of Sulphur
Dioxide Emissions
- R 71 Million
- Tailgas Treating Unit installed in 2000
- Future Plans
- Continuous improvement in reliability and
efficiency of unit
152005 - Our Journey continues
Sources of sulphur dioxide
- Measurement
- Modeling
- Control
- Work with DEAT, City of Cape Town to meet
requirements of new AQA
16An 80 reduction in particulate matter (dust)
emissions
- R 40 Million
- Installation of Electrostatic Precipitators in
1996/1997
- Future Plans
- Continuous improvement in reliability and
efficiency of units
17Reduction in volatile organic compound emissions
- R8 million
- Installed tank seals on all floating roof tanks
at the refinery
- Future Plans
- Fenceline monitoring to collect baseline
information on VOC emissions from the refinery
2005 2006 - Complete a R70 million upgrade of effluent plant
2005 2007
18Effluent plant upgrade (R70 million)
- Implementing new effluent project to improve
quality of used water going out to sea. Project
will reduce VOCs from effluent plant. - Have had a number of meetings with kitesurfers to
resolve issues, develop plans and build trust. - Project work in progress to bring effluent
treatment facilities in line with world class
equalisation secondary treatment (Phase 3 4
of project) - New effluent license issued Oct 2004. CalRef
currently within permit specs although upgrade to
be carried out to meet 2007 requirementsPMG
note Graphics not included
19Guiding Principles of Refinery Air Emission
Reduction Plan
- Focus on SO2, VOCs, NOx, H2S, particulates, black
smoke (opacity), flare - Alignment with Chevron vision for operational
excellence - Alignment with new Air Quality Act
- Evaluate options for improved measurement and
reduction of air emission - Focus on technology investment and improving
reliability - Continue to involve stakeholders
20- Community Air Quality Monitoring
21Daily Average, Ground level SO2 as monitored in
Bothasig, Goodwood, Table View and Killarney
22(No Transcript)
23- We are focusing on plant reliability to eliminate
incidents
24Incidents
Date Incident Description
26 February 2003 Black smoke from refinery stacks
04 July 2004 Pressure safety valve lifted causing crude oil spray
10 January 2005 25 minute black smoke flare
13 January 2005 Pressure safety valve lifted causing some diesel spray
04 February 2005 Fire
14 March 2005 Three minute black smoke flare
25Strong reliability focus is our key strategy for
eliminating incidents
- Reliability focus will improve environmental
performance - Visible leadership and accountability
- Preventative maintenance
- Training and development
- Reinforce procedure compliance and pre-task
planning - Shutdown effectivenessPMG note Graphics not
included
26 27Water Recycling Project(R30 million)
- Joint venture between Caltex Improchem to
purify sewerage water for Potsdam refinery
boilers using reverse osmosis - Conservation Incentive Saving drinking water
for 6000 households - PMG note Graphics not included
28Clean Fuels Project(R200 million)
- Project to produce lower sulphur diesel (0.05
wt) by end 2005 according to new government
specifications - PMG note Graphics not included
29Community Involvement
Partnering with environmental groups and air
quality authorities to implement fenceline air
(VOC) monitoring.
- Introducing neighbours to the refinery.
- PMG note Graphics not included
30