The SFCA and the NRM - PowerPoint PPT Presentation

1 / 41
About This Presentation
Title:

The SFCA and the NRM

Description:

Precast/composite decking systems. Concrete floors. Upper floor ... Space decks. Steel frame. Frame. Superstructure. Level 3. Level 2. Level 1. External works ... – PowerPoint PPT presentation

Number of Views:294
Avg rating:3.0/5.0
Slides: 42
Provided by: indigo7
Category:
Tags: nrm | sfca | contractors | decks

less

Transcript and Presenter's Notes

Title: The SFCA and the NRM


1
The SFCA and the NRM
  • Joe Martin, Executive Director
  • BCIS

2
(No Transcript)
3
(No Transcript)
4
SFCA
  • Standard Form of Cost Analysis
  • Principles Instructions and Definitions

5
NRM
  • New Rules of Measurement
  • Order of cost estimating and elemental cost
    planning

6
SFCA and NRM
  • The titles of these documents indicate their
    purpose
  • The SFCA sets out how to analyse the cost of a
    project into elements.
  • The NRM sets out how to present and develop a
    cost plan as the design develops.

7
SFCA and NRM
  • These two processes are the beginning and the end
    of the cycle of cost information that flows
    through a procurement process.
  • The starting point for an elemental order of cost
    estimate is cost analyses of previous projects.
  • The starting point for a cost analysis is the
    costing documents from a procurement process.
  • There is clearly a chicken and egg relationship.

8
When Adam delved and Eve span
9
Flow of cost information
10
SFCA and BCIS
  • The SFCA, and indeed BCIS, were developed to
    facilitate the move from costing a design, to
    designing to a cost
  • For that you need elemental costs
  • An element is A major physical part of a
    building that fulfils a specific function, or
    functions, irrespective of its design
    specification or construction.

11
SFCA
  • The SFCA defines the Elements and provides
    instructions for analysing the costs of a project
    into Elements and defines the ancillary project
    information needed to interpret it.
  • It defines the purpose of a cost analysis as to
    provide data that allows comparisons to be made
    between the costs of achieving various building
    functions in a project with those of achieving
    equivalent functions in other projects. It is the
    analysis of a building in terms of its elements.

12
SFCA
  • The key point is that the content of the
    functional Elements as defined in the SFCA should
    not change with the design or specification.

13
Elemental cost analyses
  • Why are elemental costs useful?
  • Because they can provide a basis for providing a
    client a robust estimate based on very little
    information at a level that helps define the
    assumption that you have made
  • And can be based on

14
Elemental cost analyses
  • Schedule of accommodation
  • 2000m2 offices
  • Canteen for 200 people
  • 300m2 gallery space
  • Auditorium for 300 people
  • Two shops

15
Elemental cost analyses
  • A sketch designs

16
NRM
  • The NRM
  • provides a structured basis for preparing order
    of cost estimates and elemental cost plans
    including all the costs and allowances forming
    part of the cost of the building to the client
    but which are not reflected in the measurable
    building work.

17
NRM
  • Order of cost estimate
  • The determination of possible cost of a building
    early in design stage in relation to the
    employers fundamental requirements. This takes
    place prior to preparation of full set of working
    drawings or bill of quantities and forms the
    initial build up to the cost planning process

18
NRM
  • Elemental Cost Plan
  • The critical breakdown of the cost limit for the
    building into cost targets for each element of
    the building. It provides a statement of how the
    design team proposes to distribute the available
    budget among the elements of the building, and a
    frame of reference from which to develop the
    design and maintain cost control.

19
SFCA and NRM
  • So far so good.
  • The starting point for the NRM was the SFCA
    elemental definitions, which define the physical
    building.
  • The practical issues involved in pricing a design
    as it develops and in presenting the rules the
    NRM means that the presentation of the two
    documents are different. However some effort was
    made to ensure that the two structures are
    compatible

20
So what are the differences
  • The differences are
  • NRM covers the non-physical aspects of a project
    that the client may require as part of his
    overall budget for the project, while the SFCA
    relates to the physical construction and
    contractors charges.
  • Pragmatic changes to presentation and allocation
  • Different coding system.

21
NRM
  • Guidance on pricing the non-physical aspects of a
    project that the client may require as part of
    his overall budget for the project eg
  • Main contractors preliminaries
  • Contractors overheads and profit
  • Project/design team fees
  • Other development/project costs, eg insurance,
    planning fees, decanting and Section 106
    agreement contributions
  • Risk allowances
  • Inflation
  • Value Added Tax
  • Other considerations eg Capital Allowances, Land
    remediation allowances and Grants

22
Presentation and allocation
  • NRM also introduction some pragmatic changes to
    the familiar SFCA list of elements
  • The purely presentational issues
  • Introduction of designed elements and
    sub-elements
  • Splitting Facilitating works and External works
  • Introducing non-element cost category for
    off-site constructed buildings
  • Practical pricing issue relating to procurement
    that moves the structure away from elements
    towards packages.
  • Editorial changes

23
presentational issue
  • NRM presents the rules in a table with three
    levels
  • To reducing the white space in the tables some
    SFCA sub-elements are presented at level 2 rather
    than level 3
  • For example in the SFCA Substructure is an
    element but is also a group element. In NRM the
    sub-elements are presented at level 2 and further
    broken down at level 3.

24
Designed elements
  • At level 3 the structure is expanded to
    incorporate design and specification eg

25
External works
  • External works split into
  • Work to existing buildings
  • External works
  • Facilitating works

26
Off-site construction
  • Complete buildings and building units
  • Prefabricated buildings complete buildings
  • Prefabricated buildings building units

27
Pricing and packages
  • Practical pricing issue relating to procurement
    that moves the structure away from elements
    towards packages eg
  • Façade retention is included with demolitions
    as it will be procured as part of the demolition
    package.
  • Work to existing buildings covers work all work
    to existing not just work to adjacent buildings.
  • Podium slabs forming roofs to basements are
    included in upper floors
  • Drainage under the building in substructure
  • Testing and commissioning of individual service
    installations separated from installations

28
Coding
  • The SFCA has a numeric/alpha/numeric coding eg
    2F1 External windows
  • The NRM structure uses a numeric/numeric/numeric
    coding eg
  • 2.6.1 External windows
  • This will help to differentiate between the two.

29
The circle of cost information
  • Project costs reported in the format of the NRM
    measurement rules can easily form the basis of
    the and SFCA elemental cost analysis.
  • Elemental cost analyses provides the initial
    costs to inform an elemental order of cost
    estimate before the design exists. This can be
    developed following the NRM guidance as the
    design develops and, where the resultant cost
    plan forms the basis of the contract sum
    analysis, it can be re-analysed into functional
    Elements.

30
NRM Contents
  • Order of cost estimating and elemental cost
    planning in context of
  • RIBA Plan of Work
  • OGC Gateway review process

31
Estimate and cost plan stages
32
NRM order of cost estimate
  • Rules for order of cost estimating
  • Information required
  • Constituents
  • Measurement rules
  • Floor area
  • Functional units
  • Elements floor area, Element unit quantities
  • Updating historic costs
  • Preliminaries
  • Contractors overheads and profit

33
NRM order of cost estimate
  • Rules for order of cost estimating
  • Fees
  • Other development costs
  • Risk allowances
  • Inflation
  • VAT
  • Other considerations
  • Reporting

34
NRM cost planning
  • Rules for elemental cost planning
  • Purpose
  • Constituents
  • Formal cost planning stages
  • Reviewing and approving cost plans
  • Cost control
  • Multiple buildings
  • Information requirements
  • Updating historic costs

35
NRM cost planning
  • Rules for elemental cost planning
  • Preliminaries
  • Contractors overheads and profit
  • Fees
  • Other development costs
  • Risk allowances
  • Inflation
  • VAT
  • Other considerations
  • Reporting

36
Measurement rules
  • Structure of rules
  • Sub element
  • Component
  • Unit
  • Measurement rules for components
  • Included
  • Excluded

37
Measurement rules
  • Component strip foundation details, including
    depth of foundation, to be stated
  • Unit m
  • Measurement rule linear length of component is
    measure on centre line of the component

38
NRM - Appendices
  • Appendices include
  • Information requirements for formal cost plans
  • Templates for cost plans

39
NRM
  • For RICS members it can be downloaded from RICS
    website

40
  • As the meerkat says
  • Is simples!

41
The SFCA and the NRM
  • Joe Martin, Executive Director
  • BCIS
Write a Comment
User Comments (0)
About PowerShow.com