Title: Waste Paper
1Waste Paper
Ethanol
- Converting Waste Paper into Ethanol
- March 28, 2008
-
2Outline
- U.T.C. Engineering
- Agricultural Comparison
- Papernol Process Overview
- Material Balances
- Energy Balances
- Equipment Sizing and Cost
- Full Scale Outlook
- Current Development
3Distillation
Intro Chemical Process
Thermodynamics
Engineering Economics
Senior Papernol Project
Freshman Design
Process design
Heat Mass Transfer
Reactor Design
Unit Operations
4UTC Papernol Team - 2008
5How is Papernol Different?
6Papernol Advantages
- Value added to waste stream
- Resource from Local Community
- Improves Local Economy
- Minimal Transportation/Fuel Inputs
- No Cropland Requirement
7Acid Hydrolysis Dilute acid to generate glucose
from cellulose
Fermentation Convert Glucose into Ethanol
Purification Separate Ethanol from water
Papernol Process
C6H10O5 H2O H? C6H12O6
C6H12O6 Yeast ? 2 CO2 2 C2H6O
Preparation and Hydrolysis
Fermentation
Purification
8Material Balances
EtOH 500 gal/day
PAPER 10,000 lb/day
9Preparation (Basis 10,000 lb paper/Day)
150,000 lb H2O
10,000 lb paper
160,000 lb slurry 8,000 lb cellulose
Research 7 paper water mixture
80 paper is cellulose
10Hydrolysis (Basis 10,000 lb paper/Day)
1600 lb H2SO4acid
10 lb steam/hr
2600 lb steam/hr
1300 lb NaOH
150,000 lb H2O 5600 lb glucose
70 conversion
160,000 lb slurry
7300 lb solid waste
11Evaporation - Fermentation (Basis 10,000 lb
paper/Day)
860 lb yeast
2750 lb CO2
3,000 lb steam/hr
1600 gal CW/hr
62,000 lb H2O 2850 lb EtOH
150,000 lb H2O 5600 lb glucose
62,000 lb H2O 5600 lb glucose
12Purification (Basis 10,000 lb paper/Day)
2,800 lb EtOH
Azeotrope at 88
500 gal EtOH
65,000 lb EtOHH2O 1.8 EtOH
62,200 lb H2O
13Energy Balances
QLOST
QIN 49 million BTU/day
QPRODUCT 38 million BTU/day
QADDED
14Preparation
55 kW
18 kW
15Hydrolysis
QIN7700 BTU/hr
QIN2.1 MM BTU/hr
16Evaporation - Fermentation
QOUT 333,000 BTU/hr
QIN 4 MM BTU/hr
17Purification
QOUT 1.7 MM BTU/hr
QIN 2750 BTU/hr
QOUT9300 BTU/hr
QIN 2.5 MM BTU/hr
18Equipment Size and Cost
Equipment Size(ft3) Quantity Total Cost (1000)
Storage Hopper 98 3 2
Shredder 1700 1 32
Mixer 1700 1 42
Hydrolysis Tank 2700 1 26
Evaporator 1
Fermentation Vessel 800 4 61
Mixer fermentation 20 1 1
Distillation Column 360 1 600
Molecular Sieve 2 20
19Equipment Size and Cost
Equipment Size(ft3) Quantity Total Cost (1000)
Slurry Pump 1 22
Slurry Heat Exchanger 2500 ft2 1 102
Acid Heat Exchanger 11 ft2 1 3
Conveyor N/A 2 22
20Current Development
- Economics
- Environmental Aspects
- (CO2 foot print)
- Utility Costs
21Stages of Project Development
Lab Proof of Concept
- Lab Scale Proof of Concept
- Currently in Progress at UTC
- Available Budget 500
- Restricted Testing
Pilot Scale 2009-2010 Integrated
Processing Utilize TVA/UTC Chickamauga
Site Estimated Budget 1,000,000
Medium Scale 2008-2009 Small Demonstration
Budget 150,000 Tested Using UTC ENGR Labs
Medium Small Demonstration
Pilot Integrated Processing
Orange Grove 2010-2011 Full Unit Skid-Mounted
Modular Estimated budget 3,000,000
Full Scale Unit Orange Grove Center
22Potential Orange Grove Site
Process 10,000 lb Paper 500 gal of Ethanol per
day gt Three Tractor Trailers
23Papernol Outlook
- Orange Grove 500 gal/day max.
- Adds value to Orange Grove
- Competitive with Corn Switchgrass
- A Renewable Ethanol Source