Title: Payback
1CHAPTER 6 Capital Budgeting Decision Methods
- Payback
- Net present value (NPV)
- Internal rate of return (IRR)
- Modified internal rate of return (MIRR)
2Steps
- 1. Generate ideas.
- 2. Estimate the CFs (inflows and outflows).
- 3. Assess the riskiness of the CFs.
- 4. Determine the project cost of capital.
- 5. Find NPV, IRR, and/or MIRR.
- 6. Accept if NPV gt 0 and/or IRR gt cost of
capital.
37-
What is the difference between independent and
mutually exclusive projects?
- Projects are independent if the cashflows of one
are not affected by the acceptance of the other - Projects are mutually exclusive if acceptance of
one impacts adversely on the cashflows of the
other
4Example of mutually exclusive projects
Bridge vs. boat to get products across a river.
57-
What is the difference between normal and
non-normal projects?
- Projects are normal if they have outflows or
costs in the first year(s) followed by a series
of inflows - Projects are non-normal if one or more outflows
occur after the inflows have begun
6Inflow () or Outflow (-) in year 0 1 2 3 4 5 N
NN - N - - NN - - - N
- - - NN - - - NN
7Cashflow data we will use for examples
Year 0 1 2 3
L -150 15 90 120
S -150 105 75 30
? L-S 0 -90 15 90
8What is the payback period?
- The expected number of years required to recover
a projects cost, i.e. how long will it take to
get our money back?
9Payback for Project L (Long Most CFs in later
years)
CFt Cumulative CF
PaybackL 2 45/120 2.375 years
10Payback for Project S (Short Most CFs in early
years)
CFt Cumulative CF
PaybackS 1 45/75 1.6 years
11What is the rationale for the payback period?
- Its a type of breakeven analysis. It tells
us when the project will break even in a cash
flow sense.
12Strengths of Payback
1. Indication of a projects risk and
liquidity. 2. Easy to calculate and understand.
Weaknesses
- 1. Ignores time value of money.
- 2. Ignores CFs occurring after payback.
13If maximum acceptable payback is two years, what
is the best decision if L and S are
independent? Mutually exclusive?
- If required payback is 2 years, Project S would
be accepted and L would not. - In this situation, it makes no difference whether
the projects are independent of mutually
exclusive.
14Should capital budgeters even look at payback?
- Some firms do calculate payback and give it some
weight in capital budgeing decisions. - Its not the primary criterion rather it is used
as one meausre of a projects liquidity and
riskiness.
15NPV is the sum of the PVs of a projects inflows
and outflows.
n
CFt
?
NPV
(1 k)t
t 0
If all costs at t 0, then
CFt
n
- CF0
NPV
?
(1 k)t
t 1
16What is project Ls NPV?
NPVS 29.98
17Calculator Solution
Enter in cash flows for L
CF0
-150 15 90 120 10
CF1
CF2
CF3
28.18 NPVL
NPV
I
18Rationale for NPV method?
- NPV PV inflows - PV costs Net gain in
wealth - Accept project if NPV gt 0
- Choose between mutually exclusive projects on the
basis of higher positive NPV. Adds most to value.
19Using the NPV method, which project(s) should be
accepted?
- If Projects S and L are independent, accept
both NPV gt 0. - If Projects S and L are mutually exclusive,
accept S because NPVS gt NPVL.
20Would the NPVs change if the cost of capital
changed?
CFt
n
NPV
?
(1k)t
t 0
YES NPV is dependent on k
If k , NPV If k , NPV
217-
Internal Rate of Return (IRR)
- IRR is the discount rate which forces the NPV to
equal zero - (PV of inflows PV of outflows)
227-
NPV Enter k, solve for NPV
IRR Enter NPV 0, solve for IRR
CFt
n
?
0
(1IRR)t
t 0
23What is Project Ls IRR?
Enter in cash flows for L
CF0
-150 15 90 120
CF1
CF2
23.56
IRR
CF3
24How is a projects IRR related to a bonds YTM?
- They both measure percentage
- rate of return. IRR is to a capital
- project what the YTM is to a bond.
- A bond YTM is its IRR.
25Internal rate of return rationale
If IRR k, then project cashflows are just
sufficient to provide investors their required
rates of return
IRR gt k implies some return is left over to boost
shareholder returns. Example k WACC 10 IRR
15. Profitable.
26IRR acceptance criteria
- If projects are independent,
- accept all projects with IRR gtk
- reject all projects with IRR lt k
- If projects are mutually exclusive,
- accept project with the highest IRR gt k
27Are S and/or L acceptable by IRR?
- If S and L are independent, accept both. IRR gt k
10. - If S and L are mutually exclusive, accept S
because IRRS gt IRRL.
28Are IRRs affected by changes in the cost of
capital?
- NO. IRRs are independent of the cost of capital.
- However, the acceptability of projects could
change.
29Construct the Projects NPV Profiles
Enter CFs in CFLO and find NPVL and NPVS at
several discount rates k NPVL NPVS 0 75 60
5 50 44 10 28 30 15 10 18 20
- 6 7
30k NPVL NPVS 0 75 60 5 50 44 10 28
30 15 10 18 20 - 6 7
NPV 80 60 40 20
Crossover point 8.7
IRRL 18.1
IRRS 23.6
0 5 10 15 20 25 k
31NPV and IRR always lead to the same accept/reject
decision for any independent project.
IRR lt k and NPV lt 0
IRR gt k and NPV gt 0
NPV
ACCEPT
REJECT
IRR
32Mutually Exclusive Projects
NPV 80 60 40 20
L
k lt 8.7 NPVL gt NPVS IRRSgt IRRL CONFLICT k gt
8.7 NPVSgt NPVL IRRS gt IRRL NO CONFLICT
IRRL
S
IRRS
0 8.7 15 20 25 k
33How do you find the crossover rate?
- Find the CF differences between the projects.
- Enter the differences in CFLO, then press IRR.
Crossover rate 8.68. - Can subtract S from L or vice versa, but better
to have first CF negative. - If profiles do not cross, one project dominates
the other.
34Why do NPV profiles cross?
- Timing differences A project with faster
payback provides more CF in early years for
reinvestment. If k is high, early CF is
especially good and NPVS gt NPVL. - Size (scale) differences Smaller project frees
up funds at t 0 for investment. The higher the
opportunity cost, the more valuable these funds
are. High k favors small projects.
35Reinvestment rate assumptions
- NPV assumes reinvestment at k (opportunity cost
of capital). - IRR assumes reinvestment at IRR.
- Reinvestment at opportunity cost, k, is more
realistic, so NPV method is best. NPV should be
used to choose between mutually excusive projects.
36Managers like rates- they can visualize IRR
better than NPV. Can we give them a better IRR?
- YES. MIRR is the discount rate which causes the
PV of a projects terminal value (TV) to equal
the PV of its costs. Since TV is found by
compounding inflows at the opportunity cost of
capital, - MIRR assumes cash inflows are reinvested at k
37MIRR for Project L (k 10)
0
1
2
3
10
-150
15
90
120
10
237.15
TV of inflows
PV of outflows
237.15 (1MIRR)3
MIRRL 16.5 MIRRS 16.9
150
38Calculator Solution
- First enter CFs for t 1-3 and solve for PV of
inflows 178.17 - Calculate FV of inflowsPV -178.17 n 3, I
10 FV 237.15 - Calculate MIRRFV 237.15 PV -150 N 3
I 16.5 MIRRL
39Why use MIRR vs. IRR?
- MIRR correctly assumes reinvestment at the
opportunity cost of capital. - MIRR also avoids problems with nonnormal
projects. - Managers like rate of return comparisons and MIRR
is better for this than IRR.
40Is MIRR better than NPV?
- NO. MIRR does not always lead to the same
decision as NPV for mutually exclusive projects.
In particular, small projects often have a higher
MIRR, but a lower NPV than larger projects. - NPV remains the conceptually best decision rule.
41The Pavilion Project Find NPV and IRR
Year 0 1 2
CF -400,000 2,500,000 -2,500,000
k 10
Enter CFs in CFLO, enter I 10 NPV
-193.39 IRR ERROR. WHY?
42We got IRR ERROR because there are 2 IRRs.
Nonnormal CFs- two sign changes.
NPV Profile
225
100 400
-400
IRR1 25
IRR2 400
43Logic of Multiple IRRs
- At very low discount rates, the PV of CF2 is
large negative, so NPV lt 0. - At very high discount rates, the PV of CF1 and
CF2 are both low, so CF0 dominates and again NPV
lt 0. - In between, the discount rate hits CF2 harder
than CF1, so NPV gt 0, resulting in 2 IRRs.
44Could find IRR with HP-10B calculator as follows
- Enter CFs as before.
- Enter a guess as to IRR by storing the guess.
Try 1010 STOIRR 25 lower IRR. - Now guess large IRR, say 200200 STOIRR
400 upper IRR.
45When there are nonnormal CFs and more than one
IRR, use MIRR.
0 1 2
-400,000 2,500,000 -2,500,000
PV outflows _at_ 10 -2,466,115.70 PV inflows _at_
10 2,750,000.00 MIRR 5.6
46Accept Project P?
- NO. Reject it because
- MIRR 5.6 lt k 10
- Also, if MIRR lt k, NPV will be
- negative NPV -193,388.43