Payback - PowerPoint PPT Presentation

1 / 46
About This Presentation
Title:

Payback

Description:

The Pavilion Project: Find NPV and IRR. k = 10% Enter CFs in CFLO, enter I = 10; NPV ... Could find IRR with HP-10B. calculator as follows: Enter CFs as before. ... – PowerPoint PPT presentation

Number of Views:170
Avg rating:3.0/5.0
Slides: 47
Provided by: vick116
Category:
Tags: hp | pavilion | payback

less

Transcript and Presenter's Notes

Title: Payback


1
CHAPTER 6 Capital Budgeting Decision Methods
  • Payback
  • Net present value (NPV)
  • Internal rate of return (IRR)
  • Modified internal rate of return (MIRR)

2
Steps
  • 1. Generate ideas.
  • 2. Estimate the CFs (inflows and outflows).
  • 3. Assess the riskiness of the CFs.
  • 4. Determine the project cost of capital.
  • 5. Find NPV, IRR, and/or MIRR.
  • 6. Accept if NPV gt 0 and/or IRR gt cost of
    capital.

3
7-
What is the difference between independent and
mutually exclusive projects?
  • Projects are independent if the cashflows of one
    are not affected by the acceptance of the other
  • Projects are mutually exclusive if acceptance of
    one impacts adversely on the cashflows of the
    other

4
Example of mutually exclusive projects
Bridge vs. boat to get products across a river.
5
7-
What is the difference between normal and
non-normal projects?
  • Projects are normal if they have outflows or
    costs in the first year(s) followed by a series
    of inflows
  • Projects are non-normal if one or more outflows
    occur after the inflows have begun

6
Inflow () or Outflow (-) in year 0 1 2 3 4 5 N
NN - N - - NN - - - N
- - - NN - - - NN
7
Cashflow data we will use for examples
Year 0 1 2 3
L -150 15 90 120
S -150 105 75 30
? L-S 0 -90 15 90
8
What is the payback period?
  • The expected number of years required to recover
    a projects cost, i.e. how long will it take to
    get our money back?

9
Payback for Project L (Long Most CFs in later
years)
CFt Cumulative CF
PaybackL 2 45/120 2.375 years
10
Payback for Project S (Short Most CFs in early
years)
CFt Cumulative CF
PaybackS 1 45/75 1.6 years
11
What is the rationale for the payback period?
  • Its a type of breakeven analysis. It tells
    us when the project will break even in a cash
    flow sense.

12
Strengths of Payback
1. Indication of a projects risk and
liquidity. 2. Easy to calculate and understand.
Weaknesses
  • 1. Ignores time value of money.
  • 2. Ignores CFs occurring after payback.

13
If maximum acceptable payback is two years, what
is the best decision if L and S are
independent? Mutually exclusive?
  • If required payback is 2 years, Project S would
    be accepted and L would not.
  • In this situation, it makes no difference whether
    the projects are independent of mutually
    exclusive.

14
Should capital budgeters even look at payback?
  • Some firms do calculate payback and give it some
    weight in capital budgeing decisions.
  • Its not the primary criterion rather it is used
    as one meausre of a projects liquidity and
    riskiness.

15
NPV is the sum of the PVs of a projects inflows
and outflows.
n

CFt
?
NPV
(1 k)t
t 0
If all costs at t 0, then
CFt
n
- CF0
NPV
?
(1 k)t
t 1
16
What is project Ls NPV?
NPVS 29.98
17
Calculator Solution
Enter in cash flows for L
CF0
-150 15 90 120 10
CF1
CF2
CF3
28.18 NPVL
NPV
I
18
Rationale for NPV method?
  • NPV PV inflows - PV costs Net gain in
    wealth
  • Accept project if NPV gt 0
  • Choose between mutually exclusive projects on the
    basis of higher positive NPV. Adds most to value.

19
Using the NPV method, which project(s) should be
accepted?
  • If Projects S and L are independent, accept
    both NPV gt 0.
  • If Projects S and L are mutually exclusive,
    accept S because NPVS gt NPVL.

20
Would the NPVs change if the cost of capital
changed?
CFt
n
NPV
?
(1k)t
t 0
YES NPV is dependent on k
If k , NPV If k , NPV
21
7-
Internal Rate of Return (IRR)
  • IRR is the discount rate which forces the NPV to
    equal zero
  • (PV of inflows PV of outflows)


22
7-
NPV Enter k, solve for NPV
IRR Enter NPV 0, solve for IRR
CFt
n

?
0
(1IRR)t
t 0
23
What is Project Ls IRR?
Enter in cash flows for L
CF0
-150 15 90 120
CF1
CF2
23.56
IRR
CF3
24
How is a projects IRR related to a bonds YTM?
  • They both measure percentage
  • rate of return. IRR is to a capital
  • project what the YTM is to a bond.
  • A bond YTM is its IRR.

25
Internal rate of return rationale
If IRR k, then project cashflows are just
sufficient to provide investors their required
rates of return
IRR gt k implies some return is left over to boost
shareholder returns. Example k WACC 10 IRR
15. Profitable.
26
IRR acceptance criteria
  • If projects are independent,
  • accept all projects with IRR gtk
  • reject all projects with IRR lt k
  • If projects are mutually exclusive,
  • accept project with the highest IRR gt k

27
Are S and/or L acceptable by IRR?
  • If S and L are independent, accept both. IRR gt k
    10.
  • If S and L are mutually exclusive, accept S
    because IRRS gt IRRL.

28
Are IRRs affected by changes in the cost of
capital?
  • NO. IRRs are independent of the cost of capital.
  • However, the acceptability of projects could
    change.

29
Construct the Projects NPV Profiles
Enter CFs in CFLO and find NPVL and NPVS at
several discount rates k NPVL NPVS 0 75 60
5 50 44 10 28 30 15 10 18 20
- 6 7
30
k NPVL NPVS 0 75 60 5 50 44 10 28
30 15 10 18 20 - 6 7
NPV 80 60 40 20
Crossover point 8.7
IRRL 18.1
IRRS 23.6
0 5 10 15 20 25 k
31
NPV and IRR always lead to the same accept/reject
decision for any independent project.
IRR lt k and NPV lt 0
IRR gt k and NPV gt 0
NPV
ACCEPT
REJECT

IRR
32
Mutually Exclusive Projects
NPV 80 60 40 20
L
k lt 8.7 NPVL gt NPVS IRRSgt IRRL CONFLICT k gt
8.7 NPVSgt NPVL IRRS gt IRRL NO CONFLICT
IRRL
S
IRRS
0 8.7 15 20 25 k
33
How do you find the crossover rate?
  • Find the CF differences between the projects.
  • Enter the differences in CFLO, then press IRR.
    Crossover rate 8.68.
  • Can subtract S from L or vice versa, but better
    to have first CF negative.
  • If profiles do not cross, one project dominates
    the other.

34
Why do NPV profiles cross?
  • Timing differences A project with faster
    payback provides more CF in early years for
    reinvestment. If k is high, early CF is
    especially good and NPVS gt NPVL.
  • Size (scale) differences Smaller project frees
    up funds at t 0 for investment. The higher the
    opportunity cost, the more valuable these funds
    are. High k favors small projects.

35
Reinvestment rate assumptions
  • NPV assumes reinvestment at k (opportunity cost
    of capital).
  • IRR assumes reinvestment at IRR.
  • Reinvestment at opportunity cost, k, is more
    realistic, so NPV method is best. NPV should be
    used to choose between mutually excusive projects.

36
Managers like rates- they can visualize IRR
better than NPV. Can we give them a better IRR?
  • YES. MIRR is the discount rate which causes the
    PV of a projects terminal value (TV) to equal
    the PV of its costs. Since TV is found by
    compounding inflows at the opportunity cost of
    capital,
  • MIRR assumes cash inflows are reinvested at k

37
MIRR for Project L (k 10)
0
1
2
3
10
-150
15
90
120
10
237.15
TV of inflows
PV of outflows
237.15 (1MIRR)3
MIRRL 16.5 MIRRS 16.9
150
38
Calculator Solution
  • First enter CFs for t 1-3 and solve for PV of
    inflows 178.17
  • Calculate FV of inflowsPV -178.17 n 3, I
    10 FV 237.15
  • Calculate MIRRFV 237.15 PV -150 N 3
    I 16.5 MIRRL

39
Why use MIRR vs. IRR?
  • MIRR correctly assumes reinvestment at the
    opportunity cost of capital.
  • MIRR also avoids problems with nonnormal
    projects.
  • Managers like rate of return comparisons and MIRR
    is better for this than IRR.

40
Is MIRR better than NPV?
  • NO. MIRR does not always lead to the same
    decision as NPV for mutually exclusive projects.
    In particular, small projects often have a higher
    MIRR, but a lower NPV than larger projects.
  • NPV remains the conceptually best decision rule.

41
The Pavilion Project Find NPV and IRR
Year 0 1 2
CF -400,000 2,500,000 -2,500,000
k 10
Enter CFs in CFLO, enter I 10 NPV
-193.39 IRR ERROR. WHY?
42
We got IRR ERROR because there are 2 IRRs.
Nonnormal CFs- two sign changes.
NPV Profile
225
100 400
-400
IRR1 25
IRR2 400
43
Logic of Multiple IRRs
  • At very low discount rates, the PV of CF2 is
    large negative, so NPV lt 0.
  • At very high discount rates, the PV of CF1 and
    CF2 are both low, so CF0 dominates and again NPV
    lt 0.
  • In between, the discount rate hits CF2 harder
    than CF1, so NPV gt 0, resulting in 2 IRRs.

44
Could find IRR with HP-10B calculator as follows
  • Enter CFs as before.
  • Enter a guess as to IRR by storing the guess.
    Try 1010 STOIRR 25 lower IRR.
  • Now guess large IRR, say 200200 STOIRR
    400 upper IRR.

45
When there are nonnormal CFs and more than one
IRR, use MIRR.
0 1 2
-400,000 2,500,000 -2,500,000
PV outflows _at_ 10 -2,466,115.70 PV inflows _at_
10 2,750,000.00 MIRR 5.6
46
Accept Project P?
  • NO. Reject it because
  • MIRR 5.6 lt k 10
  • Also, if MIRR lt k, NPV will be
  • negative NPV -193,388.43
Write a Comment
User Comments (0)
About PowerShow.com