Title: From Logical Framework Approach to Results Based Management
1From Logical Framework Approach to Results
Based Management
- A Flexible Tool for Participatory Development
(Danida, 1996)(??) - Henrik Secher Marcussen, IDS/ISG
2To-days Menu
- The Background. A tool for guided change under
uncertain conditions and subjective perceptions
of problems, objectives, conditions and
directions - Or Aid under the influence of management and
rational planning theories - 2) The logic behind, the method
- The options, the necessities, the criticism
- Results Based Management, RBM Human
Accountability Project, HAP) - The meta-scientific discussion Rationality,
predictability and control under complex
conditions Is it at all possible?
31) The Background
- Development is a process of change with some
basic common features - A broader context in which we act
- A problem area or present situation we want to
change - An objective, or a vision of the future, that we
want to achieve - Choices about where and how we intend to move,
through time and - Actions we want to be implemented
41) The Background, contd
- In moving from the present to the future, we
want - To create a shared perception of the changing
context we work in - To create a shared perception of the problems or
barriers we wish to overcome - To create commitment to clear objectives
- To choose transparency between alternative
options and - To design courses of action
5The Background, contd
- Explicit and implicit goals of LFA
- To better master the Project cycle
(identification, inception, drafting the Project
Document, appraisal, approval, implementation,
monitoring, completion and evaluation) - But in particular improve on likelihoods of
meeting objectives (from inputs via activities to
outcome and impact) - To foster commonality of understandings among
stakeholders about project objectives and means
of achievement
61) The Background, contd
- To engage the local population in all phases of
the process (participation, as means or end?) to
counter top down through bottom up-processes - To avoid blueprint approaches by adapting to
the local and specific context - To foster direct involvement (incentives,
investments, commitments, users pay-schemes,
maintenance and sustenance, etc.), believed to
create the ownership locally to the entire
process - Logically, to create improved conditions for
sustainability
7The Background, contd
- But also to direct and control
- To improve on likelihood that objectives are well
defined, realistic and attainable - To create a better background for monitoring and
evaluation - To ensure that money well spent value for
money - To be able to document and justify the
intervention towards donors and their
constituencies, whether bilateral-state to
state (taxpayers money), NGOs (their members)
or the multilaterals (their members/governing
council/board of directors) -
8The Background, contd
- To create improved conditions for maintaining the
financing wanted in the long term (Framework
agreements) NGOs - To create legitimacy and public/political backing
and direct support - To maintain organisational growth (diversify
funding sources) - To prove that the organisation is a professional,
qualified and trustworthy partner, able to run a
project/programme with the needed tools and
deserves to be mandated with new additional
tasks
92) Logikken, metoden
- The LFA is, then, a framework for designing
change processes, monitoring progress and
evaluating impact - This is achieved by ordering the elements of the
change process in a logical structure - Inputs or resources are identified as necessary
means for performing activities - Specific actvities are identified
102) Logikken, metoden, contd
- Activities are leading to outputs, again
necessary to achieve objectives - Objectives are, hopefully, met in particular
Immediate Objectives - That are contributing to meeting the Overall
Development Objective - If Objectives are met, Outcome and Impact are
likely to be demonstrated (in theory, at least)
by means of Reviews and Evaluations - To facilitate measuring, Achievement Indicators
are identified and listed
11(No Transcript)
12(No Transcript)
132) The Logic, the Method contd
- To establish the Framework, work in five Focus
Areas - Context
- Problems
- Objectives
- Choice and
- Action
142) Method (the instruments). Focus Area 1 Context
- Who are the stakeholders
- Policy concerns
- Values and principles within the group, community
or society - Uncertainties and risks
- (Existing structures, formal and informal
institutions arenas of power and positioning
socio-economic inequality gender (im)balances,
etc.)
152) Method. Focus Area 2 Problems
- Identify problems and problem owners
- Structure problems and relations between them
- Develop a shared perception of problems
- Develop options for which problems to concentrate
on - (Who will gain, who will loose who will seek
ownership, who will be excluded power games
conflicts manipulative behaviour claims and
rights) - (Identify the problems that suit the solutions
technological fixes blueprint approaches)
162) Method. Focus Area 3 Objectives
- Identify objectives and objective owners
- Structure objectives and relations between them
- Develop options for what objectives to pursue
- (Include in objectives (problems and risks)
considerations as to reducing existing
inequalities foster democracy and real
empowerment and participation, etc.)
172) Method. Focus Area 4 Choice
- Estimate the resources that are available
- Create an overview of options
- Assess options (weigh costs and benefits)
- (Immediate and long term options include EIAs
and SIAs identify, if at all possible, options
that build on already existing knowledge,
structures and institutions) - Make a choice
182) Method. Focus Area 5 Action
- Specify objectives chosen, results, activities
and resources needed - Identify critical assumptions about the context
- Check that the project is logically consistent
- Establish indicators that allows monitoring of
project progress and impact - --The whole being an iterative process,
cumbersome and time consuming, going back and
forth and trying to identify the dialectics,
the contradictions, paradoxes and dilemmas
193) The Options, the Necessities, the Criticism
- Can be a heuristic, idea generating tool
- Towards Learning Development iterative,
feedback mechanisms, monitoring, synthesising,
evaluating - Create an overview, clarity, precision and,
ideally, well argued and well justified choices - Create (perhaps) better projects/programmes
avoid (perhaps) the worst white elephants
203) The Possibilities
- May create a consensus among stakeholders but
is unable to force on a consensus not existing in
the real world - May establish longer lasting partnerships
- May create greater awareness about both
justifications, risks and killer assumptions
213) The Possibilities
- May help thinking logically, but cannot
substitute for it! - If to be a workable tool, real consultations and
negotiations are needed - May visualise project elements, and foster
clarity but may also limit, frame or block for
identifying needs or shaping visions - Holds promise of emancipation, but often fails
- And it is crucial to determine Whom, for what
and with which intention an LFA exercise is
carried out. - Qualifications, experience and background matter
tremendously, and requirements as to independence
and integrity are crucial elements
223) The Possibilities
- To master the techniques, including LFA, show
quality and professionalism and may attract
funding in cases, LFA is a funding condition - LFA reflects business and logistics planning of
the 1960s, with assumptions of relatively
well-understood and controllable change,
engineered via a project within or largely
controlled by a single organisation. It centres
attention on outputs and service delivery and on
achievement of intended effects by intended
routes (Gasper, 2000)
233) The Criticism
- LFA is also an instrument of control, both for
donors and stakeholders in project locations - LFA is a rigid tool that is narrowing the
planning process - Too often it is short-sighted in perspective
- May contribute to strategic thinking and capacity
development, but also the opposite - Risk maintaining status quo may cement and
reify the development process - LFA may be able to balance costs and benefits,
particularly in relation to stakeholders, but
does not necessarily do that
243) The Criticism
- Time is needed, and time is always and
increasingly a scarce ressource within
development business - It requires involvement, enthusiasm and
contextual insight - Result Routinely conducted, in a stereotyped
fashion and, in cases, with overtones of
paternalism and top down - Do we talk about Logic-Less Frames,
Lack-Frames, or Lock-Frames?
254) Results Based Management
- Same logic, same steering, control and
measurement mechanism More of the same, but now
all over the place - Life cycle management Input (Budget, etc.),
Output target, Output indicators, Achievements, -
and Outcome and Impact - Monitoring tool Process and corrective measures
Proposed action (Danidas Guidelines for
Programme Management)
264) RBM
- Monitoring of bilateral and NGO projects in
relation to effectiveness, efficiency and
quality - Also monitoring multilateral organisations their
performance and quality control mechanisms - Programming, Annual Work Plans, organisational
strategies - RBM provides legitimicy and alludes to quality
and professionalism
274) RBM
- UNDP Means of linking discrete projects and
placing under national priorities and goals - May illustrate a collective achievement of
UNDPs own overall success indicators - May contribute to showing how MDGs and other
strategic objectives are met - May provide the successful picture UNDP at a
glance
28- May also show insight and experience, prove
accountability and transparency - Using more specific indicators also assist in
measuring output and impact - May easily depict performance and justify
efforts, showing value for money - May cement language commonality and
understandings the language of development
common reporting standards
29Human Accountability Project (HAP)
- Newest trend, humanitarian assistance
- Intended to address past experience
Overcrowding, unplanned and uncoordinated, and
ineffective - Licensing of quality, modalities of operation,
ethical standards, etc ISO 2008 equivalent - Legitimacy, accountability, transparency
- Justified in relation to recipients, but mainly
addressing own funding sources
305) Meta-scientific Perspectives
- LFA etc. have their background in western
rationality concepts/theories within planning - Combined with recent management theory, drawn
from the private sector - The trust With the tool box intact, incentives
and/or sanctions in place, a development process
can (in principle) be fostered that can be
directed, controlled and predicted
315) Meta-scientific
- ...the concept of planning embodies the belief
that social change can be engineered and
directed, produced at will - Once normalized, regulated and ordered,
individuals, societies and economies can be
subjected to the scientific gaze and social
engineering scalpel of the planner, who like a
surgeon operating on the human body, can then
attempt to produce the desired type of social
change (Escobar)
325) Meta-scientific
- In theory, traditional economic development
planning is based on the assumption that the
development process can be steered, overcoming or
eradicating underdevelopment, poverty,
traditions, irrationalities, and other obstacles,
a.s.o. - But disillusionment was the result effects of
extensive planning exercises limited the
development challenge much more complex,
contextually specific and fluid
335) Meta-scientific
- Development problems/dev. countries constitute
complexity complex systems - Constitute generally unknown or not fully
understood contextuality - Represent different rationalities
- And stakeholders are bringing their different
ideological/cultural frameworks to the analysis - Result Consult complexity theory!
345) Meta-scientific
- ..complex systems cannot be fully explained by
the methods we traditionally associate with
techne. It is impossible to gather and properly
process all the information pertinent to the
working of such systems, or to predict the ways
inwhich they will change. Clearly such systems
will be resistant to the machinations of any
architect who wishes to reduce it to a blueprint
and thereby manipulate it (Parfitt, 2006) - Where does that lead us and LFA?
355) Meta-scientific
- Planned intervention The critical analysis,
Olivier de Sardan Bierschenk Long van der
Ploeg Crehan von Oppen, m.fl. - Forms and functions of aid tabula rasa,
a-historical the by necessity stipulated
discontinuity as justification, the postulate
that the world is (re)born when aid arrives, and
the sins of the past now finally addressed
and, as a result, all good things in life will
materialise
365) Meta-scientific
- Development Interface, Ferguson, Long, Arce,
a.o. - Intervention as meeting place, arena, interface
between cultures and forms of rationality - Interface mediated by institutions, formal and
particularly informal ones, performed in arenas,
with positioning, investments and power play - Where interventions constantly negotiated,
turned, twisted and modified, when adapted to
local agendas - Unintended consequences at least as important as
intended ones - Focusing on contextuality, variability, fluidity
in local political processes
375) Meta-scientific
- The Language of Development, Arce, Long,
Escobar, Sachs, m.fl. - Interventions use phrases, a language, that
supports particular knowledge systems,terms and
concepts which confirm and maintain certain
representations, legitimizing particular
interventions, while also carrying myths and
narratives forward - Knowledge systems paves the way for particular
interpretations of the reality, however often
misrepresentations inclusion/exclusion - Sustained by epistemic communities
- Knowledge systems tend to gain hegemonic status,
dominant and policy setting paradigm