Failures of Earth Retaining Structures and Lessons Learned - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

Failures of Earth Retaining Structures and Lessons Learned

Description:

Damage occurred in the form of cracking and tilting ... co-ordination between the structural engineer and the contractor is the primary ... – PowerPoint PPT presentation

Number of Views:348
Avg rating:3.0/5.0
Slides: 19
Provided by: ash787
Category:

less

Transcript and Presenter's Notes

Title: Failures of Earth Retaining Structures and Lessons Learned


1
Failures of Earth Retaining Structures and
Lessons Learned
  • Presented By
  • Ashish Wadkar

5th November, 2009
2
Importance of Retaining Stuctures
  • Varying topography of earth makes retaining
    structures vital
  • Resist the thrust of earth bank
  • Provide soil stability

3
Failures
  • Failures of earth retaining structures can be
    quite catastrophic
  • It is important to understand the assumptions
    made in the design philosophy
  • Design of walls backfilled with clay is based on
    the analysis that applies to granular soils only
  • Only savior margin would be overgenerous factor
    of safety assumed in the design

4
Failure Modes
5
Common reasons for failures
  • Often times, granular material is specified for
    the backfill by the designer which is not always
    available at site
  • To avoid additional cost, the material available
    at site is used for backfilling
  • Lack of awareness for internal and external
    stability

6
Importance of engineering design
7
Lack of External Stability
  • A cantilever retaining wall collapsed due to
    lack of external stability

8
Poor Design and Workmanship
  • A cantilever retaining wall collapsed due to poor
    design and workmanship
  • The active pressure was calculated considering a
    flat backfill while at site a sloping backfill
    was constructed
  • Design engineers assume a drained backfill with
    granular material for full height
  • Clayey soils available at site was used for
    backfilling
  • Damage occurred in the form of cracking and
    tilting

9
Imbibing waters
  • Rainfall is the triggering factor for many cases
    of retaining wall failures
  • Geogrid reinforced retaining wall collapsed in
    Kentucky shortly after construction

10
SRW failure
  • Investigation revealed that backfill was not
    adequately compacted
  • Triaxial tests suggested that loss of strength
    occurred as the moisture content became dry of
    optimum
  • Steeper backslope was constructed due to space
    limitations
  • Length of geogrid reinforcement was not adequate

11
Segmental retaining wall
12
SRW failure
  • A hybrid SRW failed in New England due to
    improper design
  • Field reports indicated no deviations from
    construction drawings and proper compaction was
    achieved
  • Backfill became saturated with water due to
    rainfall

13
Construction sequence
14
Additional failure reasons
  • Wall was designed for dry backfill however the
    as-built stability FOS were found to be safe
  • However FOS for connection of geogrid with wall
    units was under the required limit
  • Wet backfill was not only the reason of failure

15
Backfill Material
  • The most important single consideration in wall
    design is insuring good drainage. There are two
    approaches
  • - Remove water from backfill
  • - Keep water out of backfill
  • The best backfill is rigid, free draining and
    with a high angle of internal friction
  • Lightweight artificial material such as expanded
    shale and crushed slag often make good backfill.

16
Summary of Lessons Learned
  • Conservatism may lead to the original designer
    ignoring the design of the connections
  • Failure of retaining walls takes place when
    as-built conditions varied considerably from the
    design conditions
  • Lack of co-ordination between the structural
    engineer and the contractor is the primary reason
    for such deviations

17
Summary of Lessons Learned
  • The properties of soil available at site should
    be identified at the beginning in order to
    incorporate necessary changes in the design of
    walls
  • Walls shall be laterally supported by provision
    of shear key and earthquake loads shall be
    considered in design of walls for a seismic zone
  • Backfill material should be compacted adequately
    without development of excessive compaction
    pressures

18
THANK YOU !
William John Macquorn Rankine (1820-1872)
Write a Comment
User Comments (0)
About PowerShow.com