Title: Power Quality Impacts of Distributed Generation
1Power Quality Impacts of Distributed Generation
- Roger C. DuganSr. Consultant
- Electrotek Concepts, Inc.
- Tennessee Tech.
- February 9, 2004
2Introduction
- Renewed interest in Grid-connected DG
- Utility Perspective
- T D Capacity Relief
- Hedge against high market prices
- End User Perspective
- CHP and Improved Reliability
- Incentives from Utility
- Commercial Power Producer
- Sell kWh or ancillary services
3Emphasis of This Presentation
- Units connected to distribution (MV)
- Typically lt 10 MW
- Commonly 1-2 MW
- Frequently owned by end user
- Impact of these units on Power Quality
- Operating conflicts
- We will look at a few of the many
4OverCurrent Protection Conflicts
5Typical Overcurrent Protection
6Only One Device Has to Operate
OperatingDevice
Fault Current
7Transmission Fault Protection
Multiple Sources
Two Devices Must Operate to Clear Fault
8LV Network Systems
9Utility Fault Clearing
- Due to cost, distribution systems are designed
expecting only one source of fault current - Only one device has to operate
- DG must disconnect to allow utility fault
clearing process to continue - This is the source of most operating conflicts
10Reduction of Reach
Utility relays and DG relays may not know
anything is wrong.
11Reduction of Reach
- More of a problem at peak load
- When peaking units are likely to be connected !!
- More of a problem for high resistance faults
- Longer fault detection times
12Instantaneous Reclosing
13Reclosing
- Most faults are temporary
- Reclosing is prevalent in North America
- Reclosing Interval 0.2 5 sec
- Instantaneous lt 30 cycles
14Reclosing, contd
- If DG does not get off, two bad things could
happen - DG is damaged by the reclose
- Shafts
- Winding damage
- Fault is not cleared
- Reduced reliability
- Damage to utility system
15Reclosing
DG Must Disconnect Here
16Instantaneous Reclosing
- Utilities use this for PQ concerns
- Increases the probability that DG will not
disconnect in time - Makes it almost a certainty that some wont
- If 1-2 sec, most operations will be easily
detected by DG protection - Some utilities use 5 sec reclose on feeders with
DG
17Unintended Consequences ...
18Voltage Drop After Fault
OOPS!
19Low Voltage After Interruption
- A problem when there is a fault at peak loading
- When peaking DG is likely to be on !!
- This is often the most limiting condition for how
much DG can be accommodated without change - Particularly on rural feeders
- 500 1000 kW
20Ferroresonance
- Sometimes Conflicting Interconnect Requirements
Collide
21Ferroresonance
DG Required to have separate Transformer and
disconnect at first sign of trouble
G
2) DG breaker detects negative sequence and trips
leaving transformer isolated on cable capacitance
with no load/generation
1) Fuse blows or switch opens
3) Ferroresonance develops
22Ferroresonance
23Ferroresonance Waveform
24Reduced Insulation
25Arrester Duty for SLG
26Varying Generation
27Varying Generation Example
10 000 ft
10 000 ft
20 000 ft
Regulator
115 kV
12.47 kV
500 kW
1000 kW
600 kvar
Wind Gen
336 MCM ACSR
8 MW
(Untransposed)
Unbalanced impedances
Rapidly-varying load
28Varying Generation
1-Phase Regulators
Regulator Operations
29Transformer Connection and Ground Faults
30Grd Wye-Delta Connection
- Some claim this is the best way to interconnect
DG - Same way as nearly all central station generation
is connected - However, most utilities dont allow this
connection on their system.
31Wye-Delta Connection
32Problems with Wye-Delta
- Increases ground fault current
- Interferes with coordination
- Faulted Circuit Indicators get fooled
- Transformer subject to failure
- Special design and/or neutral reactor
- Utilities often discourage Specials
33On Wye-Wye
- Most common U.S. connection
- Generally well behaved
- Does not block Triplen Harmonics
- Leads to Harmonic Surprise when many machines
paralleled with utility system - Also occurs with Delta-Wye
- 2/3 pitch machines lessens the impact
34Conclusions
- Interconnected DG likely to increase
- DG must adapt to Distribution protection system
- Too much infrastructure already in place to
overhaul the system to better accommodate DG - Who would pay for it? Non-participating
ratepayers?
35Conclusions
- DG impact on Power Quality
- Often good for individual end users
- Largest gainers Those with high-value product
that suffer sustained interruptions - But, should not expect power quality improvement
in all areas - Maybe slightly negative for utility
- Contributes to operating conflicts
- Can we see it in the Average indices?
36Conclusions, contd
- Revisit Overcurrent Protection
- Utilities may have to change some practices
- Instantaneous reclosing ?
- Use of line fuses
- Tradeoffs for Transformer Connections
- WYE-Delta good for DG but not for ground fault
coordination - Special engineering reqd for some DG application.
37Despite These Conflicts
- DG can almost always be successfully engineered
- Larger conflict may be over who pays
- Some long-standing utility practices may have to
be changed
38How Much DG ?
- What is the No Changes Penetration Limit ?
- Typical 15 of feeder capacity
- 5 - 10 if Rural