Office of Environmental Management Best Practices - PowerPoint PPT Presentation

1 / 8
About This Presentation
Title:

Office of Environmental Management Best Practices

Description:

Deputy Assistant Secretary. Acquisition and Project Management ... in the last five years in applying a more rigorous project management structure ... – PowerPoint PPT presentation

Number of Views:110
Avg rating:3.0/5.0
Slides: 9
Provided by: s730
Category:

less

Transcript and Presenter's Notes

Title: Office of Environmental Management Best Practices


1
Office of Environmental ManagementBest Practices
  • J. E. Surash, P.E.
  • Deputy Assistant Secretary
  • Acquisition and Project Management
  • Office of Environmental Management
  • November 15, 2006

2006 Project Management Workshop
2
The EM Program is a Large, Complex Cleanup
Effort.
Sites States Acres Budget (FY-07) Workforce
(federal and contractor)
114 31 2,000,000 5.9 B 34,000
3
Project Management Within DOE
  • Late 1990s, National Research Council (NRC)
    study
  • Construction and environmental projects take too
    long and cost too much . . .
  • Improvements made by implementation of DOE Order
    413.3A, Program and Project Management for the
    Acquisition of Capital Assets

4
Project Management Within EM
  • EM has applied project management to the entire
    environmental cleanup effort, not just capital
    asset projects
  • EM Project Portfolios total project cost is
    160 billion
  • 87 Projects
  • 7 EM Line Item Construction Projects (14.5B)
  • 80 EM Cleanup Projects (145.7B)

5
EM Project Management Systems Accomplishments
  • EM has made significant improvement in project
    performance in FY06
  • January 2006 - 15 red/yellow projects
  • October 2006 - 3 red/yellow projects
  • 68 of the 87 Projects have been Reviewed for
    Life-Cycle Reasonableness and/or Near-Term
    Validation
  • 58 Certified Federal Project Directors
  • Currently 39 are Managing the on-going projects

6
EM Project Management Systems Accomplishments
(Contd)
  • EVMS Certification Status for Projects gt 20M at
    CD-2 (55)
  • 36.4 of Projects (20) have Certified EVMS
  • 16.4 of Projects (9) in Review
  • To improve credibility of data and systems we use
    to manage
  • Federal Oversight Reporting, Monitoring, Control
  • Performance Reporting
  • Contractors Monthly Status Report
  • Quarterly Performance Reviews
  • Office of Project Management Oversight Monthly
    Project Assessment
  • OECM Monthly Project Status Report for the Deputy
    Secretary

7
Program Accomplishments Fernald ---- Before and
After
Fernald Closure Project
8
Summary
  • DOE has had a significant culture change in the
    last five years in applying a more rigorous
    project management structure
  • EM has applied DOE Order 413.3A to its entire
    cleanup program
  • EM is integrating comprehensive safety processes
    to our projects
  • EM continues to complete cleanup in a safe,
    compliant manner with Senior management focus on
    controlling cost and schedule