Title: QUESTnet
1QUESTnet Data Centre Workshop
- Mike Andrea
- Director
- National Data Centre Practice Manager
- May 2007
ICT master planners and strategists
ICT management services Data centre design
and development Telecommunications and
networking Project office services Contact
centre design and development
2Topics
- Strategic Directions Overview
- AFCOM Five Bold Predictions
- Standards and Best Practice
- Design Considerations
- Build versus Lease
- Polaris Data Centre Overview
- QLD Model for discussion
3The Strategic Directions Group
- Five Practice Areas
- ICT management services
- Data centre design and development
- Telecommunications and networking
- Project office services
- Contact centre design and development
- Vendor independent
- Design Authority on the 200m Tier III Polaris
Data Centre at Springfield (14,000m2 N2,
high-availability, high-security co-location
facility) - External CIO for Springfield, including
responsibility for the ICT Master Plan for the
new city of Springfield under development to
provide - 85,000 residents
- Education City (USQ Campus)
- Health City (public and private hospitals)
- 1 million square metres of commercial space
4Strategic Directions Data Centre Practice
- Focus on business ICT service delivery through
effective data centre facilities - We act as the glue
- Between IT and Facilities
- Between specialist engineering disciplines
- Between the business owner and the delivery team
(financials, design, efficiency and value for
money)
5Strategic Directions Data Centre Practice
- Recent international investigations include
- 2006
- China
- APC InRow Cooling Manufacturing Plant (Shanghai)
- 2007
- UK
- Reuters (media) and JP Morgan Chase Data Centres
(London) - Spain
- Santander Bank Data Centre (Madrid)
- Germany
- CommerzBank Data Centre (Frankfurt)
- Fiducia Data Centre (Karlsruhe) under
construction - Osram Plant (Regensburg)
- Piller Power Systems (Osterode)
- MTU Diesel Engines (Friedrichshafen)
6AFCOM - Predictions
Five Bold Predictions for the Data Center that
will Change Your Future AFCOM Data Center
Institute, March 2006
- AFCOM is a leading association supporting the
educational and business development needs of
data center management, executives and vendors
around the globe. - Report
- Five Bold Predictions for the Data Center that
will Change Your Future, March 2006 - Source www.afcom.com
7AFCOM Predictions
Five Bold Predictions for the Data Center that
will Change Your Future AFCOM Data Center
Institute, March 2006
8AFCOM Predictions
Five Bold Predictions for the Data Center that
will Change Your Future AFCOM Data Center
Institute, March 2006
- AFCOM discusses Mainframe skills
- In terms of large-scale design and construction
(not retrofit) of data centres in Queensland, the
market is very small, and the pool of experienced
/ skilled design teams is even smaller - Most businesses are structured with
- IT groups targeted with business based ICT
delivery not design and build of data centres - Facilities teams focused on building maintenance,
contracts and change management not design and
build of data centres - Data centre design and build projects dont occur
that often, therefore in most cases, theres been
no need to invest in in-house skills - Selective out-tasking of skills?
9AFCOM Predictions
Five Bold Predictions for the Data Center that
will Change Your Future AFCOM Data Center
Institute, March 2006
- If this is correct its only 3 years away
- Options include
- Upgrade or extend existing facilities
- Retrofit an existing building with a new data
centre facility - Relocate higher density servers / platforms to a
3rd party facility - Relocate the entire facility to a 3rd party
facility - Others?
- What does the budget (CAPEX OPEX) allow?
- Has anyone forward planned budget increases?
- Power charges are likely to increase
- Power and cooling density is increasing
- Power consumption has increased 7-fold in the
last 7 years
10AFCOM Predictions
Five Bold Predictions for the Data Center that
will Change Your Future AFCOM Data Center
Institute, March 2006
- The water crisis has recently seen power
generation output of some Queensland power
stations curtailed - Queensland is growing not just in the South East
- The investment required in the energy network to
continue to meet residential growth and business
demand is huge - Public holidays are some of the largest peak
demand periods for energy providers - Some commercial building owners are refusing, or
are unable, to upgrade mains power and water
feeders in order to support tenants data centres
11AFCOM Predictions
Five Bold Predictions for the Data Center that
will Change Your Future AFCOM Data Center
Institute, March 2006
- Virtualisation consolidation
- Internet delivery of services and applications
- AFCOM notes IPv6
- Mobility both devices and users
- Increase in broadband and wireless internet use
- Virtual office working
- Working from home, vehicle or remote office
- The data centre is at the heart
12AFCOM Predictions
Five Bold Predictions for the Data Center that
will Change Your Future AFCOM Data Center
Institute, March 2006
- Business disruption could be caused through
- Loss of power, cooling or communications
- Fire or water damage
- Natural disaster
- Bomb threat / terrorism
- Staff error / sabotage
- Data loss
- Security breach
- System availability of some server hardware can
be less than the data centre itself
13Standards and Best Practice
- There are plenty of Standards
- But what is best practice?
14Standards and Best Practice
- There are plenty of Standards
- But what is best practice?
- Is it the best way to meet local standards?
15Standards and Best Practice
- ANSI/TIA-942-2005 (approved 12 April 2005)
- Telecommunications Industry Association
Telecommunications Infrastructure Standard for
Data Centers - Uptime Institute (Tier I to IV)
- Tier I (99.67) to Tier IV (99.99) availability
- Requires consistent application of Tier concepts
to 16 critical subsystems - ASHRAE (American Society of Heating,
Refrigerating and Air-conditioning Engineers) - DSM (Defense Services Manual Australian Federal
Government) - EPA (Environmental Protection Agency) Qld State
Government - BCA (Building Codes Australia) and Local Council
building regulations and approvals - Includes a mix of US, European and Australian
standards - Different voltages, codes, and interpretations
16Standards and Best Practice
- Formal due diligence reviews can get tied up
comparing US standards against Australian
building codes - EPO is a prime example (not desired or required
on data centre floors for fire management) - EPO in plant areas for electrical safety
- Fire separation of infrastructure and fire zones
- Fire ratings of walls and doors (circular
mantraps are a problem) - Size of zones impacts fire suppression system
selection - Security has significant implications in the
design of the physical building - Distance between redundant access points
- Loading bay access control management
- Fire escape doors (e.g. quad locking, steel
encased)
17Standards and Best Practice
- Availability of a facility
- How is it measured?
- Mixed levels of redundancy across a facility
- What if the ICT infrastructure is single corded?
- Does it account for all components of the service
delivery chain? - Electrical, mechanical, security, fire
suppression, hydraulics, telecommunications - People, support and maintenance
- Where are the single points of failure?
- Have you looked at the building riser lately?
- Mains power and water service connections
- Lifts and other access points
18Design Considerations
19Design Considerations
- Most obvious is Power and Cooling
- Mains supply to the building (and/or suburb) for
both power and water - Weight - floor slabs (if not on ground) typically
constructed in the range of 100kg/m2 to 400kg/m2 - Some 19 racks known to weigh over 1000kg (approx
1600kg/m2, with point load of 400kg) - Batteries for UPS systems
- Floor to ceiling height, including height of
raised floor (if you have one) - Fire separation (diesel generator, UPS,
batteries, transformers, switchboards) and
associated fire suppression
20Design Considerations
- Lead times, local support/maintenance and supply
- Not just the obvious, big items gas fire
suppression, switch boards, distribution boards - Skills shortage its real there is a massive
amount of infrastructure being built in
Queensland - It is difficult to secure consultants and trades
with experience in data centres - Ensure your design team understands the concept
of a data centre, high-availability and
high-density computing - Services co-ordination, it can be a stretch to
fit everything in the same riser or wall/floor
penetration - 415v or 400v ?
21Design Considerations
- Location and climate dictates some solutions
- How are Acceptance Tests conducted?
- Initial build, and then during normal maintenance
routines? - Pay as you grow
- UPS, diesel generators, chillers, cooling towers,
transformers, switchboards, racks - Cabling (power and comms), cable trays
- Some keys to success
- Ensure the building itself doesnt cause future
fit-out problems risers, diesel tank sizes and
location - Mains services (water and power) should be sized
for ultimate load (cost of change later is too
high and may not be possible) - Design with concurrent maintainability and live
upgrades in mind - Have the phase 1 project team document the
process for future fit-out
22Build vs Lease
23Build vs Lease Business Metrics
- Does an investment deliver and/or reinforce core
business what is the return on the investment? - Efficiency
- Floor Space Ratio ratio of plant room floor
area vs raised floor area a direct result of
density and appropriate infrastructure sizing - Selection of redundancy level, UPS, cooling
systems, fire suppression solution, and diesel
generators all impact efficiency - Ride-through capacity to limit false diesel
starts and loss of cooling capacity through
brown-outs
24Build vs Lease Business Metrics
- Financials CAPEX and OPEX
- Lifecycle replacement costs and timeframes
- Rent of the area (raised floor and plant) and/or
return (income) on the construction cost - Sustainability Availability
- Ability to keep operating during mains power
and/or water loss - Total site availability across all components
- Risk
- Who bears the risk of repairs, replacements,
capacity upgrades and/or non-performance
25Build vs Lease build (or retrofit)
- Considerations regarding the investment
- Is it, or will it reinforce, core business?
- Could capital (short term investment) provide a
higher return spent elsewhere? - Are the ongoing operational expenses budgeted and
committed for the next 15 years? - Getting the right team together is key
- Electrical, mechanical, hydraulics,
architectural, civil, construction, security,
ICT/BMS, other - Complying with formal/traditional procurement
processes can create issues - Cost of an experienced design team can be high
- Long lead times (from order to delivery)
- Fixed priced contracts may have exclusions
relating to fluctuating copper, stainless steel,
concrete and water prices - Is the project big enough to ensure the right
companies respond? - Can the building cope?
- Full operational costs are yours and cant be
shared
26Build vs Lease lease
- Considerations regarding the investment
- All costs are OPEX, capital free for use
elsewhere - Are the ongoing operational expenses budgeted and
committed for the next 15 years? - Possible additional carriage costs
- Reliant on a 3rd party to ensure operational
performance, management and maintenance of the
facility - The 3rd party isnt subject to formal procurement
processes - Service levels available, allowing IT group to
focus on IT service delivery - In a co-location facility, the operational costs
are spread across the total leased raised floor
area - Support staff, maintenance, security and
operations - Consumables including diesel, water and gas
suppression storage - Upgrades, repairs and replacements are the 3rd
partys responsibility - Benefits may result through larger scale
- Mains services redundancy
- Carrier diversity
- Higher redundancy and/or longer sustainability
- Concurrent maintainability
- Pay for what you use
27Polaris Data Centre
28Polaris Data Centre
A 200m private investment in Queenslands ICT
industry Lead by Queensland companies
- Springfield Land Corporation
- Strategic Directions
- Suncorp
- Thiess
- Deicke Richards
- Multitech Solutions
- BRW Enterprises
29Polaris Data Centre
7000m2 of raised floor in a 14000m2 purpose
designed and built facility
- Tier III (N2)
- 800W/m2 to 1500W/m2
- 3 data centre levels
- 2 plant levels
- Design nominal 99.999 availability
- NN power distribution to the rack
- N1 Inert gas fire suppression store
- 48 hours sustainability
30Polaris Data Centre
- Concurrent maintainability
- High security (24x7 security, DSM compliant
intruder resistant perimeter, full CCTV coverage,
mantraps and biometric access) - Scalable, flexible, pay-as-you-grow modular
system from 800W/m2 to 1500W/m2 - Slab loading to 1600kg/m2, with raised-floor to
1500kg/m2 - Piller Rotary UPS solution (UBDT) with coupled
MTU diesel engine, and additional Rotary UPS
powerbridge (UBT) for chillers
31Polaris Data Centre
32Polaris Data Centre Key Learnings
- Everyone you talk to is a data centre design
expert - The IT and construction industries are poles
apart - A data centre is designed to fit within the
physical boundaries presented hence no data
centre is the same - Diesel engines require a lot of air for cooling
and combustion - External smoke entry via fresh-air intake
33Polaris Data Centre Key Learnings
- Investigate the power grid with Energex
- What appears simple can turn out very complex and
take a long time - Network upgrades and investment requires long
term planning (transformers, feeders etc) - The supply of water is critical (potable
recycled) - Some equipment lead times can be up to 2 years
- Meeting EPA requirements can be expensive
- Acoustics, emissions, diesel storage, waste
disposal - Size does create efficiency up to a point
- 3000W/m2 maybe in Polaris 2
34Polaris Data Centre Core Design Team
COMPANY ROLE FIRST INVOLVED
Springfield Land Corporation Project Owner 2003
The Strategic Directions Group Design Authority ( ICT Systems) 2004
Deicke Richards Architects 2004
Thiess Design Construction Management 2006
Webb Australia Electrical, Communications and Security ( ICT Systems) 2006
MultiTech Solutions Mechanical, Dry Fire BMS 2006
Robert Bird Group Civil 2005
BRW Enterprises Hydraulics Wet Fire 2006
Clifton Coney Group Project Management 2005
APC Strategic Alliance Partner, Industry and RD 2005
- Queensland Headquartered Companies
35QLD model for consideration
- Universities are
- undertaking reviews
- planning and/or performing upgrades
- Considering the build of new facilities
(retrofit) - Why not pool the resources to build something
specific to University needs? - Dedicated, purpose-built data centre facility as
DR, secondary or primary site - Collaborative model
36QLD Model issues discussion
- Who
- Pays what?
- Owns the facility?
- Controls and manages the facility?
- How
- Are telecommunications charges considered?
- Are consumption charges considered?
- Are different Uni requirements met?
- Big should it be what Tier?
37QLD Model issues discussion
- Does the university funding / budget model
support and/or allow for leasing data centre
space? - Private investment in developing such a facility
is based on financial models outside the
traditional ICT business case - Springfield as a location
- Energex Strategic Alliance with dual zonal
substations (one online, second planned) - Water connections potable and recycled
- Telecommunications multi-carrier, with
dark-fibre to Brisbane - Access to developed land with public transport,
shopping centres and easy access to Brisbane
airport - Natural events are low risk
- Close to experienced consulting, design and
construction team
38European Data Centres
39Summary
- Strategic Directions Overview
- AFCOM Five Bold Predictions
- Standards and Best Practice
- Design Considerations
- Build versus Lease
- Polaris Data Centre Overview
- QLD Model
40Data Centres at the very heart of IT
- Thank You
- Mike Andrea
- Email mandrea_at_strategicdirections.com.au
- Phone 1300 786 566
- Mobile 0410 551 080
- Web www.strategicdirections.com.au
- Polaris Data Centre www.strategicdirections.com.a
u/polaris