Alternative Project Delivery Mechanisms - PowerPoint PPT Presentation

1 / 13
About This Presentation
Title:

Alternative Project Delivery Mechanisms

Description:

Alternative Project Delivery Mechanisms The J. K. Spruce Experience – PowerPoint PPT presentation

Number of Views:66
Avg rating:3.0/5.0
Slides: 14
Provided by: Deskt97
Category:

less

Transcript and Presenter's Notes

Title: Alternative Project Delivery Mechanisms


1
Alternative Project Delivery Mechanisms
  • The J. K. Spruce Experience

2
Overview
  • J.K. Spruce 2 planned as early as 1986.
  • Authorized to proceed without permit in 2004.
  • Chose Design-build methodology.
  • Issued Two Phase RFP.
  • Two Offerors Responded/Awarded July 2005.
  • Issued LNTPs in August 2005 and full NTP in
    April 2006.
  • Provisional acceptance expected no later than
    March 2010.

3
Traditional Process
  • Chapter 252 of Local Gov. Code governed
    procurement activities.
  • Design-Bid-Build was only available method.
  • Bids advertised, opened and awarded publicly.
  • Award based on Lowest responsible bidder.

4
New Processes
  • Chapter 271, Subchapter H added in 2001.
  • Authorized best value determination.
  • Five new methods for project delivery
  • Competitive sealed proposals
  • Design-build
  • Construction manager-agency
  • Construction manager-at-risk
  • Job-order contracting

5
Design-Build process
  • Single entity provides design and construction.
  • Two phase procurement process
  • Phase One RFQ based on qualifications,
    references, past experience.
  • Phase Two RFP based on schedule, implementation
    plan, technical approach, cost.
  • Award to best value offeror.

6
Design-Build Advantages
  • Fast-track schedule and construction
  • Single point of contact.
  • Cost savings due to value engineering.
  • Less owner administrative burden during
    construction phase.
  • Potential for minimization of change orders.

7
Initiation of CPS Energy Process
  • Board Resolution selecting best value process.
  • Engage Owner-Engineer to develop Design Criteria
    Package.
  • Functional specification and conceptual layout.
  • Desired equipment margins.
  • Quality and performance guarantees.
  • Transmission access.
  • Geotechnical and environmental information.
  • Engaged the services of a surety consultant
  • Joint development of RFPP/RFP and evaluation
    matrices.
  • Pre pre-bid meeting held with interested parties.

8
Phase One-RFPP
  • RFPP advertised and sent to attendees.
  • Pre-bid meeting held with Site visit.
  • Evaluation criteria
  • Ability to bond penal value of 250 million.
  • Financial status.
  • Reputation in industry.
  • Past experience.
  • Resumes of proposed project team.
  • References.
  • Two offerors qualified to proceed to Phase Two.

9
Phase Two
  • Offerors given the RFP.
  • Agreement to reimburse losing entity of up to 1
    million for preparation costs.
  • Evaluation criteria
  • costs
  • Implementation plan
  • Project schedule
  • Safety record
  • Workforce and training plans
  • Costing methodology
  • Initial Design drawing and schematics

10
(cont.) Phase Two
  • Interviews conducted to clarify exceptions and
    technical response.
  • Offerors asked to resubmit responses based on
    discussion and to provide pricing to remove
    exceptions.
  • Signed agreement fixing responses for
    evaluation.
  • Evaluation and recommendation of selected
    offeror.
  • Negotiations with selected offeror and award
    based on reaching satisfactory contract.

11
Post Award
  • Limited Notices to Proceed
  • LNTP 1- Early planning and engineering for
    procurement of long lead time items.
  • LNTP 2- Vendor engineering.
  • LNTP 3- Preparatory site construction work
  • LNTP 4- Material and Equipment purchase release
  • LNTP 5- Controls upgrade
  • Full Notice to Proceed upon issuance of permit.

12
Keys to Success
  • Clear and comprehensive Design Criteria package.
  • Effective integration of proposed Design-Build
    Team.
  • Full and consistent communication.
  • Owner involvement.

13
Commercial Considerations
  • Testing and commissioning done by third party.
  • Contract price.
  • Payment and performance bonds.
  • Construction risks.
  • Bidding stipend.
  • Bonus for early completion.
  • Payment of prevailing wage.
  • Use of a Local Government Corp.
Write a Comment
User Comments (0)
About PowerShow.com