Construction Materials and Workmanship - PowerPoint PPT Presentation

About This Presentation
Title:

Construction Materials and Workmanship

Description:

Construction Materials and Workmanship – PowerPoint PPT presentation

Number of Views:86
Avg rating:3.0/5.0
Slides: 21
Provided by: Andrew1784
Category:

less

Transcript and Presenter's Notes

Title: Construction Materials and Workmanship


1
Construction Materials and Workmanship
2
  • All workmanship, materials, equipment, and
    articles incorporated into the work are to be of
    the best available grade in the local trade area
  • Materials must be free of defects or
    imperfections
  • Workmanship is hard to quantify but should be
    best available.

3
  • Request for substitution of materials
  • Contractor must give adequate notice of
    substitution intention
  • A/E needs time to look at substituted material to
    see if it is ok
  • Only allow requests during design phase and
    construction phase, not during bid phase
  • RPR must reject any material that isnt in the
    specifications or has not been approved by A/E

4
  • Inspection of Materials delivered to site
  • RPR must inspect all materials before they are
    used
  • For some items RPR may do inspection at
    fabrication plant precast concrete, steel eams
  • Precast concrete may sit for months in yard
    before delivery to site
  • Not inspecting could hold up job for months

5
  • Rejection of faulty material
  • RPR must reject faulty materials
  • Mark materials with an indelible marker and tag
    them for removal
  • Want to make sure marks are visible to inspector
    if used in work and thatthey cannot be rubbed off
  • All faulty material should be placed in a
    separate area and removed the same day
  • Written notice to contractor of rejection

6
  • Equipment
  • Contractor responsible to have right equipment on
    site.
  • RPR can request changes IF it can be established
    that item can not do job
  • Tells contractor that equipment is unsatisfactory
  • RPR can also halt work for safety issues
    (overloaded crane)

7
  • Quality Assurance
  • Testing
  • Installation according to Manufacturers
    instructions Gillette House used roofing
    instructions on shingles
  • Experience Qualification
  • Prevents fly by night firms to get bid
  • Used for work that requires specialization

8
  • Factory Inspection
  • Matching Samples on Display during Bidding
  • Sample shows bidders what is expected
  • Used for concrete finishes, stone, cabinetry
  • Samples go with RPR to job site for comparison
    during inspections

9
  • Proven Successful Use
  • Contractor must prove that items have been in use
    in a similar project for a specified time period.
  • Elevators, pumps, electrical equip things that
    need to have a long reliable life
  • Qualified Products List
  • Procurement of certain items must be from a list
    of pre-approved items
  • Possibility of less competition
  • Need up to date list
  • Contractor may try to issue a disclaimer for
    those products

10
  • Certified Lab Reports
  • Contractor pays for tests and gets a certified
    report. Report gives method of testing, min level
    of performance, id of product
  • Concrete reinforced steel
  • Steel
  • Fire spread ratings on material
  • Masonry units
  • Certificate of Compliance or Conformance
  • Product complies with a specified reference
    standard
  • Glass, Paint, Wood

11
  • Ownership of Materials
  • Contractor owns all materials until final
    acceptance of the work
  • Delivery and Storage of materials
  • Contractor needs to find space
  • Owner may or may not have space
  • If contractor rents space RPR must see agreement

12
  • Handling materials
  • RPR must oversee delivery, storage, and
    installation of materials
  • How is material off loaded
  • How is it stored
  • How does it get to its final placement

13
Changes and Extra Work
  • Change order is a written agreement to modify,
    add to, or otherwise alter the work from the
    project in the contract
  • Alterations must be within scope of contract
  • Standard practice for owners to make changes in
    project after contract signed
  • May have a change order to correct error in the
    plans

14
  • Changes in the Work
  • Impact Costs
  • Indirect costs, increased costs after order
    signed
  • Owner should add an addenda to change order
    saying that price includes all charges for direct
    and indirect costs arising from the work

15
  • Oral Change orders
  • Risky
  • Are legally binding
  • No written backup to fight claims
  • Should be followed by a letter which formalizes
    the change order

16
  • Bilateral Change Orders
  • Contract addendum
  • Contractor and owner agree to work
  • Unilateral Change Order
  • Intended to expedite issuance of change order to
    perform emergency or protested work
  • Must be followed by a written bilateral change
    order before payment

17
Basic Principles
  • 1. No work beyond scope of base contracts
    especially on public works
  • 2. Who is authorized to request and approve
    change orders
  • 3. Meet during preconstruction to discuss how to
    handle change orders
  • 4. All changes must be authorized in writing
    before execution of a change

18
  • 5. Scope of change order must be clear request
    must be clear enough for contractor to give a
    good estimate
  • 6. Contractors proposal for change order must be
    ASAP as should owners approval or rejection
  • 7. Proposal should be fair to both parties
  • Contractor should include overhead and profit

19
  • Creates extra work for everybody
  • Emergency work
  • RPR can do an Initiator Change Order Request if
    authorized by owner
  • Must follow up with a written change order
  • Protects owner and contractor

20
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com