Title: Product Mix
1Product Mix Master Production Scheduling
2Product Mix Problem
- Quantity of Each of Multiple Products to Produce
- - Example How Much of Various Flavors of Ice
Cream to Produce? - Solution Methods
- - Hueristics
- - Linear Programming
3Linear Programming (L.P.)
- Continuous Decision Variables
- Decision Variable Subject to Constraints
- Objective Function that is Maximized or Minimized
- Equations or Inequalities are Linear
4Consider the Following
- The businessperson, Cindy Light, publishes two
magazines, Paygirl (for men) and Payboy (for
women). Monthly sales average about 6,000 and
4,500 issues respectively for the publications.
Paygirls contribute .60 per issue to net
profits Payboys add about .50 per issue. No
left over magazines are desirable. - Each Paygirl requires two minutes of actual
machine and labor time to produce. Payboys only
require one minute. There are 10,000 total
minutes per month of time available. Inventory
storage space imposes another limitation. 48,000
cubic inches are available and each magazine uses
up about 8. -
- Determine monthly production for each magazine.
5E.g. L.P. Formulation
- X1 Issues of Paygirl
X2 Issues of Payboy - Objective Function Max. Z .6 X1 .5 X2
- Subject to (s.t.) 2 X1 X2 ? 10,000
(Labor) - 8 X1 8X2 ? 48,000 (Inventory)
- X1 ? 6,000 (Demand)
- X2 ? 4,500 (Demand)
- X1, X2, ? 0
6Linear Programming (L.P.)
- We Can Use the Computer (Simplex Method Using POM
for Windows) to Find the Answer. - The Answer Would Be Incorporated in the Master
Production Schedule
7Master Production Scheduling (MPS)
- Link between Production Planning and What is
Built or What Service is Performed - Used for Calculating Resource and Capacity Needs
- Drives Material Requirements Plan (MRP)
- Keeps Priorities Valid Is Negotiated Agreement
8MPS Differs from Production Plan
- Shorter Time Buckets
- Used for Each End Item Not Families of Items as
in Production Plan - Generally More Detailed
9Items in MPS Must Add Upto Whats in Production
Plan
WEEK 1 2 3 4 5 6
UNICYCLES Â 100 50 Â 50 40
BICYCLES 100 Â Â 100 Â 40
TRICYCLES Â Â 50 Â 50 20
TOTAL - Production Plan 100 100 100 100 100 100
10What End Items Go into MPS
11MPS Can Show Running Inventory
WEEK 0 1 2 3 4 TOTAL
FORECAST Â 200 300 100 100 700
AVAILABLE 200 250 200 100 100 Â
MPS Â 250 250 Â 100 Â
12Optimizing MPS
- Develop Preliminary Plan
- Maintain Desired Customer Service by Optimizing
Available Goods - Make Best Use of Resources (Materials, Labor,
Equipment) - Check Preliminary Plan Against Capacity
- Resolve Differences Between MPS and Capacity
13MPS with Minimum Available of 100
WEEK 0 1 2 3 4 TOTAL
FORECAST Â 200 300 100 100 700
AVAILABLE 200 250 200 100 100 Â
MPS Â 250 250 Â 100 Â
14MPS and Capacity
- Made to Stock
- (Two Hours per Bike Three Hours per Trike)
WEEK 1 2 3 4 5 6
BIKES 10 20 30 20 40 0
TRIKES 20 10 20 10 0 30
TOTAL HOURS 80 70 120 70 80 90
CAPACITY 100 100 100 100 100 100
15ATP (Available to Promise)
- Portion of Inventory Not Committed Available to
Customer - ATP Scheduled Receipts Beginning
Inventory - Actual Orders Scheduled
16ATP Calculation
- On Hand100
- ATP (1) 100 80 20
- ATP (2) 100 (1010) 80
- ATP (4) 100 30 70
WEEK 1 2 3 4 5 6
CUSTOMER ORDERS 80 10 10 Â 30 Â
MPS Â 100 Â 100 Â Â
ATP 20 80 Â 70 Â Â
17(No Transcript)