CITY & COUNTY OF SAN FRANCISCO CAPITAL PLANNING PROGRAM FY 2011-2020 DRAFT CAPITAL PLAN REVIEW Wholesale Produce Market Expansion February 22, 2010 – PowerPoint PPT presentation

Number of Views:58
Avg rating:3.0/5.0
Slides: 9
Provided by: bst99
Category:
Tags: city | plan | project

less

Transcript and Presenter's Notes

Title: City


1
City County of San FranciscoCapital Planning
Programfy 2011-2020 DRAFT Capital Plan
REVIEWWholesale Produce Market Expansion
  • February 22, 2010

2
SF Wholesale Produce Market - Overview
  • 8 acres along Jerrold Avenue, between Toland and
    Rankin 336,000 sf under roof today.

3
SF Wholesale Produce Market - Overview
  • Non-profit Corporation formed in 1960 to secure
    this former military property, gift it to the
    City with 50 year lease-back, for sole purpose of
    creating new market.
  • Opened in 1963 following relocation of market
    from Embarcadero to present site.
  • Corporation is master tenant, sole shareholder is
    CCSF.
  • Ground Lease expires 1/31/2013.
  • Most recent expansion ten years ago at 2101
    Jerrold 55,000 square feet, fully pre-leased,
    debt retired early, and 100 occupied today.

4
SF Wholesale Produce Market - Overview
  • Project Drivers
  • Lease Expiration
  • Facility Condition and Food Safety/Security
  • Operational Safety
  • Demand for Space
  • Project Options Elements
  • 901 Rankin Street re-purposing AND
  • Renovations of 4 buildings 369,195 sf upon
    completion OR
  • New construction of 4 bldgs 476,427 sf upon
    completion AND
  • Vacation of a number of street segments,
    including Jerrold

5
SF Wholesale Produce Market - Overview
  • Project Accomplishments
  • Several design options reviewed
  • Economic modeling completed, testing fiscal
    feasibility
  • Preferred design options priced by Swinerton
  • Board approval to submit Environmental Evaluation
    Application
  • EE submitted
  • Project Cost
  • Roughly 70,000,000
  • Five phases allows progression as market demand
    and economics warrant
  • First phase roughly 20,000,000

6
SF Wholesale Produce Market - Budget
  • Secured revenues
  • Lease revenues since debt retirement have
    generated 5,600,000 in reserve funds for project
  • Exploring supplemental debt and equity options
  • COPs
  • New Market Tax Credits
  • SFRA
  • Institutional financing
  • Expenditures Encumbrances
  • 1,100,000 in consultancies to date
  • 375,201 in permit application fees to City
  • 1,400,000 expected in 2010

7
SF Wholesale Produce Market Milestones
  • CEQA Findings Fall 2010
  • Governance Model for 2013 forward Fall 2010
  • Board Action Winter 2010
  • Relocation from 901 Rankin Summer/Fall 2011
  • Construction start Early 2012

8
SF Wholesale Produce Market
  • Questions?