Title: Office Ergonomics Today
1(No Transcript)
2Scaffolding Safety
Erecting Dismantling
3Introduction
As a person who erects and dismantles
scaffolding, your safety - and the safety of
those who will work on the scaffold - depends on
your ability to closely follow the minimum safety
requirements for constructing and using
scaffolds.
4Introduction
The scaffold system you erect will support many
workers and allow them to carry out their job
functions. How well you follow proper procedures
and safe work practices while erecting scaffolds
will have a direct affect on their safety. If you
have any questions about erecting or dismantling
scaffolding, ask your supervisor.
5Pre-planning
It is important that thorough pre-planning takes
place before scaffolding is erected. This should
include
- Evaluation and Preparation of the Site
- Identification of Any Potential Hazards
- Determining the Type of Scaffolding to be Used
- Activities to be Performed and their Weight
Requirements - Weight Capacity of the Scaffold
6Pre-planning
Evaluating the Site
While evaluating the site there are many factors
to consider. There may be a number of steps you
will need to take to prepare the site.
Some items to check could include
7Pre-planning
- Is the surface level and sound?
- Can the ground support the scaffold unit?
- Are there any unguarded openings or potential
underground utility work that may affect the
stability of the scaffold?
8Pre-planning
- Are there any nearby electrical power lines?
- If so, can the scaffold be erected while keeping
a minimum safe approach distance from the lines? - Can work be performed on the scaffold while
maintaining a minimum safe approach distance from
the electrical power lines?
9Pre-planning
- What type of pedestrian, vehicular, or equipment
traffic will be in the area? - What type of fall protection will be feasible?
- Will safe access while erecting and dismantling
the scaffold be feasible? - Will conditions such as high winds, storms, or
icy conditions exist?
10Scaffolding Inspection
To make sure scaffold components are in good
working order, carefully inspect all scaffolding
parts before and during its erection. A defective
or damaged part could affect the integrity of the
whole scaffold.
11Scaffolding Inspection
Items to Check
Some areas to inspect include the following
- Are planks and wood components free of splits,
rot, burns, warps, splintering, oil, or paint and
opaque finishes that could cover potential
defects. - Are wood planks scaffold grade?
- Are welds and bolted connections in good
condition.
12Scaffolding Inspection
CAUTION!
- Any defective parts must not be used.
- Any damaged or weakened scaffold part must be
immediately repaired or removed from service
until it is repaired. - Never risk your safety by using damaged parts.
13Load Capacity
The load capacity of a scaffold varies, depending
on its design and application. General capacity
requirements for all scaffolds include
14Load Capacity
- The scaffold and each scaffold component must be
capable of supporting four times the maximum
intended load. This includes all personnel,
equipment, and supplies. - Direct connections and counterweights used to
balance adjustable suspension scaffolds must be
able to resist at least four times the tipping
moment of the scaffold, including stall loads.
15Load Capacity
- All suspension ropes and connecting hardware must
be capable of supporting at least six times the
maximum intended load. - Scaffolds must be designed by a qualified person,
and built and loaded according to that design. - Never overload the scaffold.
16Platform Construction
The platform surface that supports workers and
materials on the scaffold is called planks.
Planks are usually made of steel, aluminum, or
wood. Wood scaffold planks should be 2 by 10
inches, scaffold plank grade, and stamped by an
agency approved by the American Lumber Standards
Committee. Any unsafe planks should be removed
from service and clearly marked or made unusable.
17Platform Construction
- When erecting scaffolding it is most important to
make sure the first unit of any scaffold is
plumb, aligned, and level. - Each platform on all working levels of scaffolds
are required to be fully planked or decked,
except when used only as walkways or for erecting
or dismantling scaffolding.
18Platform Construction
- The platform and walkway must be at least 18
inches wide. - Install each platform unit (plank, fabricated
deck, or fabricated platform) so that the space
between planks, and the space between the
platform and the uprights, is no more than one
inch.
19Platform Construction
- The front edge of the platform must be no more
than 14 inches from the face of the work, unless
guardrails are used along the front edge and/or
personal fall arrest systems are used. - Never cover wood platforms with opaque finishes
(such as paint), except for the edges, which may
be covered or marked for identification. - Never intermix scaffold components by different
manufacturers, unless a competent person
determines they are compatible and the scaffolds
structural integrity is maintained.
20Platform Construction
- Each end of the platform, unless cleated or
restrained by hooks or other means, must extend
over the center line of its support at least six
inches. - If the platform is 10 feet or less in length, the
end cannot extend over its support more than 12
inches. - If the platform is over 10 feet in length, its
end cannot extend over the support more than 18
inches.
21Platform Construction
- When platforms are overlapped to create a long
platform, the overlap must occur only over
supports and must be at least 12 inches, unless
the platforms are restrained to prevent movement. - Each abutted end of a plank must rest on a
separate support surface. - When the platform changes direction, any platform
that rests on a bearer at an angle other than a
right angle must be laid first. Platforms that
rest at right angles over the same bearer must be
laid second, on top of the first platform.
22Supported Scaffolds
Supported scaffolds have one or more platforms
that are supported by outrigger beams, brackets,
poles, legs, uprights, posts, frames, or similar
rigid supports. The following are some general
requirements for supported scaffolds
23Supported Scaffolds
- When using mud sills, the base plates should be
attached to it. For added stability, it is
recommended the mud sill be one continuous sill
under both legs. The sill should extend at least
12 inches beyond the center line of the pole.
24Supported Scaffolds
- All supported scaffold poles, legs, posts,
frames, and uprights must bear on base plates,
mud sills, or other firm foundation. - They must also be plumb and braced to prevent
swaying and displacement. - Footings must be level, sound, rigid, and capable
of supporting the load of the scaffold without
settling or displacing.
25Supported Scaffolds
- Never use cinder blocks, bricks, gravel, loose
fill, or other means for leveling uneven
surfaces, or providing a foundation for the base
plate. - When supported scaffolds have a height-to-base
width ratio of more than 4-to-1 (four feet of
height for every one foot of width), then guys,
ties, or braces must be installed at locations
where horizontal members support both inner and
outer legs.
26Suspension Scaffolds
Suspension scaffolds have one or more platforms
suspended by ropes or other non-rigid means from
an overhead structure. Before the suspension
scaffold is used, a competent person must confirm
that the supporting surfaces are capable of
supporting the loads imposed on them.
27Suspension Scaffolds
The following are some general requirements for
suspension scaffolds
Ropes
- NEVER use repaired wire rope as suspension rope.
- Ropes need to be inspected by a competent person
for defects before each work shift and after any
occurrence that could affect a ropes integrity.
28Suspension Scaffolds
Hoists
- Gasoline-powered equipment and hoists must not be
used on suspension scaffolds. - Gears and brakes of power-operated hoists used on
suspension scaffolds must be enclosed.
29Suspension Scaffolds
Support Devices
- All suspension scaffold support devices (such as
outrigger beams, cornice hooks, and parapet
clamps) must rest on surfaces that are capable of
supporting four times the load imposed on them. - Two-point and multi-point suspension scaffolds
must be tied or otherwise secured to prevent them
from swaying if a competent person determines it
is necessary. Never use window cleaners anchors
for this purpose.
30Suspension Scaffolds
Outrigger Beams
- When suspension scaffold outrigger beams are
used, they must be restrained to prevent
movement. The inboard ends of suspension scaffold
outrigger beams must be stabilized by bolts or
other direct connections to the floor or roof
deck, or by counterweights.
31Suspension Scaffolds
Counterweights
- Never use sand, gravel, or other materials that
can be easily dislocated as counterweights. Only
objects specifically designed as counterweights
must be used. - Counterweights must be secured by mechanical
means to the outrigger beams to prevent
accidental displacement. - Do not remove the counterweights until the
scaffold is disassembled.
32Suspension Scaffolds
Tiebacks
- Outrigger beams that are not stabilized by both
bolts or other direct connections to the floor or
the roof deck must be secured by tiebacks. - Tiebacks must be equal in strength to the
suspension ropes. - Tiebacks must be secured to a structurally sound
anchorage on the building or structure. Do NOT
use standpipes, vents, or electrical conduits as
anchorages.
33Access Requirements
Many scaffold-related injuries occur while
improperly getting on or off platforms. Never
jump onto a scaffold.
34Access Requirements
- When the scaffold platform is more than two feet
above or below a point of access, then a portable
ladder, stairway, ramp, or other means of access
that does not affect the scaffolds stability
must be used. - Never use cross braces to climb onto the scaffold
or another level of the scaffold. - Direct access from one scaffold to another can
only be used when the scaffold surfaces are not
more than 14 inches horizontally and 24 inches
vertically from each other.
35Access Requirements
Portable, Hook-On, and Attachable Ladders
- Place hook-on and attachable ladders so their
bottom rung is not more than 24 inches above the
scaffold support level. - When hook-on and attachable ladders are used on a
supported scaffold that is more than 35 feet
high, rest platforms must be provided at least
every 35 feet. - The minimum rung length for hook-on and
attachable ladders is 11-1/2 inches. Rungs must
be uniformly spaced with a maximum spacing of
16-3/4 inches between rungs.
36Access Requirements
Stairway-Type Ladders
- Place stairway-type ladders so their bottom rung
is not more than 24 inches above the scaffold
supporting level. - Rest platforms are required at least every 12
feet. - The step width should be a minimum of 16 inches.
Mobile scaffold stairway-type ladders must have a
minimum step width of 11-1/2 inches.
37Access Requirements
Integral Prefabricated Scaffold Access Frames
- Rungs on integral prefabricated scaffold access
frames must be at least 8 inches long. - Rest platforms must be provided at least every 35
feet on supported scaffolds more than 35 feet
high. - Rungs must be spaced no more than 16-3/4 inches
apart.
38Access Requirements
Stairtowers (Scaffold Stairway/Towers)
- Stairtowers must be positioned so their bottom
step is not more than 24 inches above the
scaffold supporting level. - Stairways must be installed between 40 degrees
and 60 degrees from the horizontal. Each stairway
must be at least 18 inches between stair rails.
39Access Requirements
Stairtowers (Scaffold Stairway/Towers)
- Each side of the scaffold stairway must have a
stair rail that includes a toprail and a midrail.
Stair rails must be between 28 inches and 37
inches in height, from the top of the stair rail
to the surface of the thread. - The toprail of each stair rail system must also
serve as a handrail, unless a separate handrail
is provided. All handrails must provide a good
handhold for employees.
40Access Requirements
Stairtowers (Scaffold Stairway/Towers)
- A landing platform at least 18 inches wide and at
least 18 inches long must provided at each level.
All treads and landing must have slip-resistant
surfaces. Guardrails must be provided on the open
sides and ends of each landing.
41Access Requirements
Ramps and Walkways
- All ramps and walkways that are six feet or more
above lower levels must have guardrails. - A ramp or walkway that is steeper than one
vertical to eight horizontal, must have cleats
not more than 14 inches apart that are securely
fastened to the flanks to provide footing. Ramps
and walkways may not incline more than a slope of
one vertical to three horizontal.
42Access Requirements
Access for Supported Scaffolds
- When erecting or dismantling a scaffold, a safe
means of access must be provided, if possible. A
competent person will determine this based on
site conditions and the type of scaffold being
erected or dismantled. - Hook-on or attachable ladders must be installed
as soon as safe installation and use are
possible.
43Access Requirements
Access for Supported Scaffolds
- When erecting or dismantling tubular welded frame
scaffolds, end frames with horizontal members
that are parallel, level, and not more than 22
inches apart vertically may be used as climbing
devices for access.
44Fall Protection
A competent person will determine if fall
protection is feasible during erecting and
dismantling procedures. Check with your
supervisor or the competent person if you are not
sure what type of fall protection is required.
45Fall Protection
Guardrail Systems
- Guardrails must be installed along all open sides
and ends of scaffolds that are more than 10 feet
above a lower level. - The top edge height of toprails on supported
scaffolds manufactured or in service after
January 1, 2000 must be installed between 28 and
45 inches above the platform.
46Fall Protection
Guardrail Systems
- The top edge height on supported scaffolds
manufactured or in service before that date, and
on all suspended scaffolds where both a guardrail
and personal fall arrest system are required,
must be installed between 36 and 45 inches. - When midrails, screens, mesh, intermediate
vertical member, solid panels, or similar
structural members are used, they must be
installed between the top edge of the guardrail
system and the scaffold platform.
47Fall Protection
Personal Fall Arrest Systems
- When engineering controls, such as guardrails and
safety nets cannot protect you from fall hazards,
then a personal fall arrest system must be used.
In the construction industry, a personal fall
arrest system is required at heights of 6 feet or
more. - A personal fall arrest system must be attached by
a lanyard to a vertical lifeline, horizontal
lifeline, or scaffold structural member.
48Fall Protection
Personal Fall Arrest Systems
- The personal fall arrest system must limit free
fall to six feet or less. - Do not attach the personal fall arrest system to
the guardrail system.
49Fall Protection
Personal Fall Arrest Systems
- The anchor point must be able to support 5,000
pounds per attached worker. When vertical
lifelines are used, the anchor point must be
independent of the scaffold. Standpipes, vents,
other piping systems, electrical conduits,
outrigger beams, and counterweights are NOT
considered safe points of anchorage. - Inspect the personal fall arrest system before
each use. Look for wear, tears, cuts, and other
signs of damage.
50Falling Object Protection
A hard hat must be worn whenever there is a
possibility of being struck by falling objects,
impact while handling material at head level, or
other situations where the danger of injuries to
the head exists. OSHA (Occupational Safety and
Health Administrator) recommends that if a hard
hat is needed anywhere on the job site, then you
should wear it at all times.
51Falling Object Protection
- If tools, materials, or equipment could fall and
strike employees below, then the area must be
barricaded and unauthorized personnel must not be
allowed to enter. If the platform is more than 10
feet above a lower level, then toeboards must be
used. - Toeboards must be at least 3-1/2 inches high from
the top edge of the toeboard to the level of the
walking surface, have no more than a 1/4 inch
clearance above the walking/working surface, and
solid or have openings no larger than one inch in
size.
52Falling Object Protection
- If tools, materials, or equipment are piled
higher than the top edge of the toeboard, then
mesh, debris nets, canopies, or other means of
protection must be installed.
53Dismantling Scaffolding
All scaffolds must be dismantled only under the
supervision or direction of a competent person
who is qualified.
- Before dismantling scaffolding, check that it was
erected properly and that no structural
alterations were made. - Make sure the correct number of ties and braces
are in place. - Check that all planks are correctly seated and
will not fall as you remove other planks.
54Dismantling Scaffolding
- Lower all components to the ground by rope,
hoist, or man-to-man. Never throw the parts to
the ground. - If possible, avoid leaving the scaffold partially
dismantled, post warning notices at each point of
access. - Whether erecting or dismantling scaffolding, work
should always be suspended during high winds and
storms.
55Summit Training Source, Inc.
Contact us at 1-800-842-0466 or
at info_at_safetyontheweb.com