Title: More%20design%20Works
1- More design Works
- More simulation to study the physics reaches
with BESIII. magnet? solid angle coverage ?
Identify several important physics topics, and
study - the physics performances.
- D physics, leptonic, semileptonic, D-Dbar
mixing - What is the luminosity needed after
CLEOc, - 1 10 to 33 or gt 3 10 to 33
- Some physics topics demand high mom.
Resolution and very good PID
2- More study about IR, the backgrounds and mask
design. - More detector simulation to arrive design
optimization - - TOF time resolution, the z position error
from track extrapolation? - - the low limit of photon detection?
- Each system (detector components, DAQ and
electronics) needs RD, prototypes - Commissioning machine with detector outside beam
line, radiation issue.
3- Major issues related with BESIII design
- The radius of crystal calorimeter, affecting
performances and cost. Possibility of using CsI
crystals as EMC. - Personally, CsI is fine, except radius
problem, if we use existing magnet (CLEO I) - Backgrounds associated with machine operation,
the design of interaction regions, vacuum, masks,
etc.
Experienced man power big issue
4(No Transcript)
5Competition from CLEOC Serious challenge from
CLEOC project Design machine and detector to be
as advanced as possible, Complete the
BEPCII/BESIII project ASAP Collaboration between
BES and CLEO
- Fit with BEPCII lattice, space? 1.8 m from IP to
SCQ - Schedule, commitment of detector moving?
- - Physics collaboration?
6BESIII Collaboration Welcome international
collaboration, and domestic collaboration,
groups to participate in BESIII project Design,
MC simulation, decision making process for
making Final decision, Sub-detectors RD
and construction Electronics RD and
manufacture Online/Offline software, more
flexible arrangement Software
package Reconstructions and
Calibration code Physics study
In charge of some sub-system or send people to
IHEP
7- about Cost and schedule
- Cost for EMC, SC magnet and electronics is most
crucial - MDC, EMC and SC magnet (including iron
structure) on critical path. - Man power issues
- Serious man power shortage exists, especially
the experienced people. -
8- Cost estimation of Detector subsystem
(Preliminary) - In M RMB (1 USD 8.3 RMB)
- Beam pipe vertex chamber
3.0 - MDC
11.0 - TOF
6.0 - Barrel EMC
54.0 - Endcap EMC
20.0 - Barrel Muon detector
4.5 - Endcap Muon detector
2.5 - Super conducting magnet
45.0? - Luminosity
2.0 - Electronics
63.0? - Trigger and DAQ
13.0 - Total
224.0 - about 1/4 to 1/3 of the detector budget
either be contributed other sources - or be staged.
9Schedule
- Feasibility Study Report of BEPC II has been
submitted to the funding agency . - Technical Design Report of BEPC II to be
submitted by first half of 2002. - Construction started from Summer of 2002
- BESII detector moved away Summer of 2004, and the
BESIII iron yoke started to be assembled, mapping
magnet early 2005 - Preliminary date of the machine long shutdown
for installation Spring of 2005 - Tuning of Machine Beginning of 2006
- BESIII detector moved to beam line, May 2006
- Machine-detector tuning, test run at end of 2006
10Schematic of BESIII detector
11 Major Upgrades in BESIII
- Superconducting magnet
- Calorimeter BGO with ?E/E 2.5 _at_ 1GeV
- MDC IV with small cell, Al wires and He gas
- Vertex detector Scintillation fibers for
trigger - Time-of-flight ?T 65 ps
- Muon detector
- New trigger and DAQ system
- New readout electronics
12(No Transcript)
13Scintillating fiber for Trigger
- 1.27 mm or thinner Be beam pipe may be used
- R 3.5 cm
- 2 double-layers one axis layer and one stereo
layer - Scintillating fiber 0.30.3 mm2, L60 cm
- Clear fibers 0.30.3 mm2, L1.4 m
- two side readout by APD (F3) (below 300)
- Signal/noise lt6 p.e.gt / lt1p.e.gt
- ?? 50 ?m ?z 1mm
- Total of channels 27 x 8 216
14(No Transcript)
15Main Draft Chamber
- End-plates with stepped shape to provide space
for SC quards and reduce background - Inner part stepped conical shape, cos ? 0.93
- Outer part L 190 cm, cos? 0.83 with full
tracking volume - cell size 1.4 cm x 1.4 cm
- Number of layers (cell in R) 36
- Gas HeC2H6 , or HeC3H8
- Sense wire 30 ?m gold-plated W ,
- Field wire 110 ?m gold-plated Al
- Single wire resolution 130 ?m
- Mom. resolution 0.8 _at_ 1GeV 1T, 0.67
_at_1GeV1.2T - DE/dx resolution 7
16Trackerr simulation of MDC, ?pt as a function of
pt in for pion, wire resolution 130 ? m
17Trackerr simulation of MDC, ?pt as a function of
pt in for pion, wire resolution 100 ? m
18PID Time of Flight Counters
- Double layers TOF ( or TOF CCT)
- plastic scintillator (BC-404)
- 80 pieces per layer in ?
- R 66 75 cm,
- Thickness 4 cm, length 190 cm
- Readout both sides by F-PMT
- Time Resolution 65 ps
- 2son k/? separation
- 1.11.5GeV/c (for polar angle 00 450)
- For CCT option, need RD
19 TOFTOF
TOFCCT
20BGO Barrel Calorimeter
- To provide minimum space for main draft chamber
and TOF and to obtain the necessary solid angle,
one must modify L3 BGO crystals, and add new
crystals - 13 X0 ?E/E 2.5 _at_ 1GeV
- Rin 75cm , Lin 200cm cos ? 0.83
- Cut L3 BGO crystals (10752) 22 X0 (24cm)
into 13X0 (14cm) 8.5 X0(9.5cm) - Making new bars of 14 cm
- by gluing 9.5cm new crystal of 4.5cm
- new BGO crystals needed.
21(No Transcript)
22(No Transcript)
23- Endcap Detector
- Two possible technologies can be used,
- CsI crystals as in the detector figure, similar
technology as in the barrel, need endcap TOF. - 2. Similar technique as KLOE using lead-fiber
- technique, may not need TOF counters.
- The first choice is preferred.
24Superconducting Magnet for BESIII
- B 1 1.2 T,
- L 3.2 m
- Rin 105 cm, Rout 145 cm
-
- Technically quite demanding for IHEP,no
- experience before, need collaboration from
- abroad and other institutes in China, both for
- coil and cryogenic system.
25Muon Counter
- Barrel (L 3.6m ) Endcap cos? 0.9
- Consist of 12 layers stream tube or RPC
- Rin 145cm (yoke thickness 40cm)
- Iron plate thickness 2-6 cm
- ? counter thickness 1.5 cm
- Readout hits on strips 3cm
- total weight of iron 400 tons
26Muon acceptance
Pion contamination
27- Interaction Region
- It is very compact at IR, very close cooperation
is needed in the designs of detector and machine
components at IR - Understand the space sharing, the support,
vacuum tight - Understand the backgrounds from machine and how
to reduce them, - - Beam loss calculation (masks)
- - Synchrotron radiation (masks)
- - Heating effect (cooling if necessary)
- Understand the effects of the fringe field from
SCQ to the detector performances
28(No Transcript)
29- Luminosity Monitor
- Because the situation at the IR, the luminosity
has to either - be located quite far away from the IR (3-5m), or
in front of - Machine Q magnet, to be designed carefully.
- Accurate position determination
- Multiple detection elements at each side to
reduce the - variation of luminosity when the beam position
shifted - BGO crystals ?
30- Trigger
- Trigger rate estimation
(using the same
trigger conditions as now) - Background rate, with 40 times beam current and
half of the beam lifetime, the rough estimation
for the background is 80 times the current rate
(10-15), or 800-1200 Hz, taking 1500 as a design
number - Good event rate
When leave room for maximum luminosity to be as
calculated, 1?1033, 200 times as current event
rate, to be 1500 Hz
- Cosmic ray background can almost be negligible
Total peak trigger rate can be more than 3000 Hz,
additional trigger (software) is needed to reduce
the event rate to 2000Hz.
31Level 0 and 1 are hardware triggers, latency
2.4?s, Level2 is software filtering using
online computing farm Because fastest detector
element TOF need a time window of about 30 ns,
the trigger can identify bunch train only, not
individual bunch
- Level 0 with TOF signals
- Level 1 with hardware track finding, EMC
clustering, total EMC energy, VC tracking or
hits, ? counter hits
32- Front-end Electronics
- Pipeline scheme is required
- Requirements
- For the timing measurement
- 25 ps for TOF, 0.5 ns for MDC
- For charge measurement
- 1 accuracy for EMC, 2 for MDC and TOF
- Total number of electronic channels 76800 (too
many muon channels?)
33Data Acquisition System Event builder 3000 Hz ? 6
K bytes 20 Mb/s Event filtering Data
storage Run control Online event monitor Slow
control
Switch network
34- Offline Computing and Analyses Software
- Computing, network, data storage, data base,
processing management - Supporting software package, data offline
calibration, event reconstruction, event
generators, detector simulation
Total CPU 36000 MIPS Data storage 500 Tbytes/y
on tapes, 24 Tbytes/y on disks Bandwidth for data
transfer 100 Mbps
Substantial manpower needed for software
35Major New Subsystems of BESIII
- Vertex chamber ZHANG
Qinjian - Main drift chamber CHEN
Yuanbo - Time of flight counter HENG
Yuekun - EMC shower counter LU
Jungguang - Luminosity monitor WU Jian
(USTC) - Trigger system LIU
Zhenan - Front-end electronics SHENG Huiyi, ZHAO,
Jingwei - Data Acquisition HE
Kanglin - Computing and software MAO Zepu
36- Detector RD
- A lot of new detector technology
- RD for most sub-systems started
- Detector optimization is needed
- Modify the detector design when international
collaboration is formed, new ideas are mostly
welcome
37Cost Estimation
- Detector 220M Chinese Yuan ( 30 M US )
- 2/3 to 3/4 are from Chinese Government
- International collaboration and contribution
are needed
38Intl. Cooperation on BEPC II / BES III
- Intl. cooperation played key role in design,
construction and running of BEPC/BES. - Intl. cooperation will play key role again in
BEPC II / BES III design, review, key
technology, installation, tuning - Participation of foreign groups is mostly
welcomed. - BESIII should be an international
collaboration, - Establish organization accordingly.
39If not enough fund is expected, 2nd option
40- Summary
- BEPC energy region is rich of physics, a lot of
important physics results are expected to be
produced from BESIII at BEPCII - Detector design is started, need a lot of
detailed work to finish detector design - Very interesting and very challenging project
Thanks