Title: Johnson Creek Covered Bridge
1Johnson Creek Covered Bridge
2Construction Statistics Review Update
- In service since May 1, 2005
- 2386 projects active in system
- 640 finals paid in 2007 for 4,137,168
- 935 Change Orders approved in 2007
- Progress Estimates for payments in 2007 of
1,054,764,758 - 1614 subcontract approved in 2007
3SiteManager DWR
- Summary of DWR Quantities on website updated
bi-weekly with pay estimates. This can also be
created within SiteManager and send from RE
office
The CSV File can be loaded into Excel for summary
information and assisting in checking final. In
Excel, it can filter on each Pay Item to check
for weigh sheets, etc.
http//transportation.ky.gov/construction/sm/dwr/
4Pending Pay Estimates Links
- ARCHIVED http//transportation.ky.gov/constructio
n/sm/est/PENDING/archive/ - Current http//transportation.ky.gov/construction
/sm/est/PENDING/
5Approved Pay Estimates Links
- ARCHIVED http//transportation.ky.gov/constructio
n/sm/est/EST_ARCH/ - Current
- http//transportation.ky.gov/construction/sm/est/
6Approved Pay Estimates Links
http//transportation.ky.gov/construction/sm/est/p
ayments2008.xls
7Question
- What can be done to provide a better pay plane
for subcontractors for work done? - Pay estimates DWR csv on web. Our contract is
with prime.
8Question
- BETTER PLAN TO ADDRESS A QUICKER TURN AROUND TIME
ON RECEIVING PAYMENTS FOR WORK PERFORMED . - State Highway Engineer Gilbert Newman addressed
change order issue. Residents with their
inspectors keep track of work items. Need to
coordinate with RE if you feel you have completed
work not on pay estimate
9SiteManagerChange Orders
- During SiteManager Review, Resident Engineer
should forward by e-mail a copy of change order
to Contractor before sending for signature. - This will allow them to check supplemental prices
included in the change order.
10Change Order Signature Report
- Resident Engineer is to sign the change order on
requested by line and mail, deliver or fax to
contractor for signature and further submittal to
State Highway Engineers Office. - Contractor is to send change order with original
signature (no fax or copy) to - State Highway Engineers Office
- 6th Floor TCOB
- 200 Mero Street
- Frankfort, KY 40622
11Change Order Signature Report
- DSHE for Project Delivery forwards to State
Highway Engineer for signature approval - If approved, Change order then sent to account
for uploading program funding. - After funding finally secured the Change Order is
put in APRV status and payment can be made on
items. Approved Change order copies then mailed
out.
12Payment for Change Order Items
- After Change Order has been put in APRV status,
payment can be made on items included in the
change order. They are now part of the contract.
2008 Standard Bid Item List Project let after
1/1/08
http//transportation.ky.gov/construction/ITEMS/IT
EMS08.xls
13Question
- PLEASE ADDRESS THE LENGTH OF TIME THAT IT TAKES
TO GET A CHANGE ORDER PROCESSED. EXAMPLE-WORK
DONE IN SEPTEMBER OCTOBER ON CHANGE ORDER
STILL NOT PROCESSED. - State Highway Engineer Gilbert Newman addressed
this issue. Residents will keep current one
Change Order submittals.
14DBE payment information
- Required to pay within 7 days of receipt of
payment from KYTC. We pay every two weeks! - Submit copy of check with Contract ID reference
to - Office of Civil Rights Small Business
Development - DBE Payments
- 6th Floor West TCOB
- 200 Mero Street
- Frankfort, KY 40601
15Potential Final Estimates
- 143 Contracts needing Corrective Work Completed
to get Formal Acceptance
http//transportation.ky.gov/construction/projects
/correct/correctbycont.pdf
16Final Estimates
- Project Engineer will send copy when finished
checking. Please let them know of any problems.
They will forward to district in 15 days after
sending to contractor, so let them know if you
have a problem with quantities! - When Final Release sent from Central Office,
Contractor has 60 days to respond. If any errors
or disagreements be sure to send notice to both
Director of Construction Central Office and
District Construction. - Signing and sending Final Release as soon as
possible speeds up final payment!!!
17Question
- What should a Contractor do to get a job closed
out after 5 years? - Contact TEBM for Construction Director of
Construction. We are trying to get current on
our Finals!
18Pre-Qualified Contact Link
- http//transportation.ky.gov/Contract/Pqbook.pdf
- Provide the Resident Engineer an e-mail at
Pre-Construction meeting for submitting Change
Orders and Pay Estimates.
Poor sign placement erection (not a Road
Construction Project!!)