1SY120 Mixed-mode operation
- Mixed-mode operation uses
- The same optics in P1 and P2 beamline for
- stacking and SY120
- The same major dipole settings in P1/P2
- Different dipole trim settings
- Modes of operation for slow spill to SY
- Dedicated slow spill (initial mode)
- Mixed-mode (single batch to pbar, 7/9)
- Mixed-mode (2 batch slip-stacking to pbar, 8/19)
- All three modes use same MI ramp and timing,
- but different TLG modules
- All three modes have been commissioned
- The minimum cycle time 2.8 sec
- The spill length is 655 ms
2Optics n Such
Beams-doc-1243
400m
500m
MI
P1
P2
AP1
Stacking
Changed P1 P2 quads Q703 fixed AP1
quads fixed
F17
200m
P2
P3
SY120
Before
After
A0
Want to start with a matched solution for new SY
tune New lattice n orbit installed July 9th
3Two flavors of Mixed-mode (1 or 2 batch to Pbar)
Pbar batches
SY120 batch
RF recapture
Beam to pbar
Qh
Beam to SY
Losses _at_F18
QXR
Simple mixed-mode
Slip-stacking mixed-mode
4Issue losses during acceleration w/ slip stacking
3rd batch
2nd batch
1st batch
Data from Kiyomi
recapture
Need to adjust slip stacking curves to shift
recapture time to finish before SY120 batch
injected
5Issue Orbit through F17 and losses in Tev at F18
AP1 c-magnets
F17B3
F17
F17
6-8mm oscillation in P3
-8mm
P2 line
AP1
3v
SY120
TLMF18
- Raise upstream c-magnet interface
- ( 1/3 inch) to center lower beam
- pipe on P2-P3 median plane
- Install V Trim at F18
1.75 OD
Safe level (1/4 v)
6Issue Mixed-mode Cycle Duty Factor
TLG with 4 sec rep (with other study cycles)
Rms current H618
12 a
Trip limit
4 sec rep
5 sec rep
What to do? gtQuad moves (reduce corr.
current) gtCooling plates (as done for
NuMI)
8a
7Issue Spill Duty Factor
QXR 20A FS
RFSPILL
MHIERR
100 ma/div
Beam
From 4/2004 RunII meeting
Recall, that the horizontal quad bus produced a
measured tune shift of0.0146 /amp gt 70 mA will
produce a 0.001 tune shift which is the
equivalent to 10 amps on QXR (2 magnets).
EE Support implemented feedback to stabilize
average level of Qh and Qv due to asymmetric TLG
- Not been focused on up to this point
- Starting point gt model system over shutdown and
- implement feedback using MHIERR as input to kHz
bandwidth - bucker system.
- Need beam studies for commission bucker system
St