Selective Coordination - PowerPoint PPT Presentation

About This Presentation
Title:

Selective Coordination

Description:

Title: Selective Coordination Overview of Short Circuit Selective Coordination with Square D Low Voltage Circuit Breakers Author: Ed Larsen Last modified by – PowerPoint PPT presentation

Number of Views:535
Avg rating:3.0/5.0
Slides: 52
Provided by: EdL88
Learn more at: https://ewh.ieee.org
Category:

less

Transcript and Presenter's Notes

Title: Selective Coordination


1
Selective Coordination
Justin Schroeder, P.E.
2
Introduction
  • Definition
  • NEC coordination requirements
  • 2011 and 2014 editions
  • NFPA 99-2012 requirements
  • NFPA 110-2013 requirements
  • Circuit breaker principles
  • Resources and product solutions
  • Challenges meeting the NEC requirements
  • Design guidelines
  • Summary

3
Definition What is selective coordination?
  • Article 100 defines selective coordination as
  • Coordination (Selective). Localization of an
    overcurrent condition to restrict outages to the
    circuit or equipment affected, accomplished by
    the selection and installation of overcurrent
    protective devices and their ratings or settings
    for the full range of available overcurrents,
    from overload to the maximum available fault
    current, and for the full range of overcurrent
    protective device opening times associated with
    those overcurrents.
  • In other words
  • Only the overcurrent protective device (OCPD)
    nearest to a fault should clear the fault

Change
4
Selective Coordination Definition
  • The concept of protective zones is a useful tool
    to visualize this.

5
NEC Selective Coordination Requirements
  • Article 517 Health Care Facilities
  • 517.17(B) Feeders.
  • Deleted the prohibition of a second step of GFPE
    on the generator feeder
  • 2 levels of GFPE when main has GFPE per 230.95(C)
  • No GFPE on load side of ATS
  • 517.17(C) Selectivity.
  • Deleted the requirement for 6 cycles of
    separation
  • GFPE must be selectively coordinated.
  • These changes should make coordination easier to
    achieve

Change
6
NEC Selective Coordination Requirements
  • Article 517 Health Care Facilities
  • 517.26 Application of Other Articles.
  • The life safety branch of the essential
    electrical system shall meet the requirements of
    Article 700, except as amended by Article 517 and
    NFPA 99 Chapter 6.
  • Informational Note No. 1 For additional
    information see NFPA 110-2010, Standard for
    Emergency and Standby Power Systems.
  • Informational Note No. 2 For additional
    information see 517.30 and NFPA 99 Chapter 6.

Change
7
Typical Health-Care Facility Electrical System
(Informational Note Figure 517.30)
Change
Must meet Article 700 per 2014 edition
Changed to branch in 2014 edition
Deleted in 2014 edition
Must meet Article 700 per 2005-2011 editions
8
Definitions
  • The equipment system (Equipment Branch) Meant
    for essential equipment loads
  • Feeds pumps, control systems, vacuums, essential
    heating, one elevator.
  • Can be fed by an alternate source at appropriate
    time-lag intervals.
  • The emergency system
  • Life safety loads (Life safety Branch) Meant
    for egress
  • Exit signs
  • Elevators
  • Automatic doors
  • Critical loads (Critical Branch) Meant for
    patient care
  • Select receptacles, power circuits related to
    patient care, task illumination

Change
9
NEC Selective Coordination Requirements
  • Article 517 Health Care Facilities
  • 517.30 Essential Electrical Systems for
    Hospitals.
  • (G) Coordination. Overcurrent protective devices
    serving the essential electrical system shall be
    coordinated for the period of time that a faults
    duration extends beyond 0.1 second.
  • Exception No. 1 Between transformer primary and
    secondary overcurrent protective devices, where
    only one overcurrent protective device or set of
    overcurrent protective devices exists on the
    transformer secondary.
  • Exception No. 2 Between overcurrent protective
    devices of the same size (ampere rating) in
    series.
  • Informational Note The terms coordination and
    coordinated as used in this section do not cover
    the full range of overcurrent conditions.

New
10
Exception No 1
11
Exception No. 2
12
Cable Riser Example
13
NEC Selective Coordination Requirements
  • Article 620 Elevators, Dumbwaiters, Escalators,
    Moving Sidewalks, Wheelchair Lifts, and Stairway
    Lift Chairs
  • 620.62 Selective Coordination.
  • Where more than one driving machine
    disconnecting means is supplied by a single
    feeder, the overcurrent protective devices in
    each disconnecting means shall be selectively
    coordinated with any other supply side
    overcurrent protective devices. Selective
    Coordination shall be selected by a licensed
    professional engineer or other qualified persons
    engaged primarily in the design, installation, or
    maintenance of electrical systems. The selection
    shall be documented and made available to those
    authorized to design, install, inspect, maintain,
    and operate the system.

Change
14
Inspection Form
Inspection form helps assure the AHJ that the
equipment supplied and installed meets code
requirements.
  • http//www.cooperindustries.com/content/dam/public
    /bussmann/Electrical/Resources/solution-center/ele
    ctrical_inspector_tools/BUS_Ele_Selective_Coord_Re
    q_ChkList.pdf

15
NEC Selective Coordination Requirements
New
  • Article 645 Information Technology Equipment
  • 645.2 Definitions.
  • Critical Operations Data System. An information
    technology equipment system that requires
    continuous operation for reasons of public
    safety, emergency management, national security,
    or business continuity.
  • 645.27 Selective Coordination. Critical
    operations data system(s) overcurrent protective
    devices shall be selectively coordinated with all
    supply-side overcurrent protective devices.

16
NEC Selective Coordination Requirements
  • Article 695 Fire Pumps
  • 695.3 Power Source(s) for Electric Motor-Driven
    Fire Pumps.
  • (C) Multibuilding Campus-Style Complexes.
  • (3) Selective Coordination.
  • The overcurrent protective device(s) in each
    disconnecting means shall be selectively
    coordinated with any other supply-side
    overcurrent protective device(s).

New
17
NEC Selective Coordination Requirements
  • Article 700 Emergency Systems
  • 700.28 Selective Coordination. Emergency
    system(s) overcurrent devices shall be
    selectively coordinated with all supply-side
    overcurrent protective devices.
  • Article 701 Legally Required Standby Systems
  • 701.27 Selective Coordination. Legally required
    standby
  • system(s) overcurrent devices shall be
    selectively coordinated with all supply-side
    overcurrent protective devices.
  • Exception to Both
  • Exception Selective coordination shall not be
    required between two overcurrent devices located
    in series if no loads are connected in parallel
    with the downstream device.

18
NEC Selective Coordination Requirements
  • Articles 700 Emergency Systems and 701 Legally
    Required Standby Systems
  • Added to 700.28 and 701.27
  • Selective coordination shall be selected by a
    licensed professional engineer or other qualified
    persons engaged primarily in the design,
    installation, or maintenance of electrical
    systems. The selection shall be documented and
    made available to those authorized to design,
    install, inspect, maintain, and operate the
    system.

Change
19
NEC Selective Coordination Requirements
  • Article 708 Critical Operations Power Systems
  • Added to 708.52(D) GFPE selectivity
  • Separation of ground-fault protection
    time-current characteristics shall conform to the
    manufacturers recommendations and shall consider
    all required tolerances and disconnect operating
    time to achieve 100 percent selectivity.
  • Same text as 517.17(C) GFPE selectivity for
    health care facilities

Change
20
NEC Selective Coordination Requirements
  • Article 708 Critical Operations Power Systems
  • 708.54 Selective Coordination. Critical
    operations power
  • system(s) overcurrent devices shall be
    selectively coordinated with all supply-side
    overcurrent protective devices.
  • Selective coordination shall be selected by a
    licensed professional engineer or other qualified
    persons engaged primarily in the design,
    installation, or maintenance of electrical
    systems. The selection shall be documented and
    made available to those authorized to design,
    install, inspect, maintain, and operate the
    system.
  • Exception Selective coordination shall not be
    required between two overcurrent devices located
    in series if no loads are connected in parallel
    with the downstream device.

Change
21
Where is it required again?
  • Article 620 Elevators, Dumbwaiters, Escalators,
    Moving Sidewalks, Wheelchair Lifts, and Stairway
    Lift Chairs
  • Article 645 Information Technology Equipment
    (Critical Operation Data Systems)
  • Article 695 Fire Pumps campus style building
    layouts
  • Article 700 Emergency Systems
  • Article 701 Legally Required Standby Systems
  • Article 708 Critical Operations Power Systems
    (COPS)

22
2014 NEC Errata Deleted Figures
Oops!
23
State Adoptions of NFPA -70 (NEC)
  • http//www.nema.org/Technical/Code-Alerts/pages/de
    fault.aspx
  • GA adopted the 2014 edition at the beginning of
    2015
  • FL, SC, NC, AL are all still on 2011
  • TN 2008 with 2009 amendments
  • How does this affect you?
  • Different states will have different requirements
    and amendments to different code cycles so be
    aware! Currently in GA, the 2014 code has been
    adopted.
  • NEC-2014 went to great lengths to standardize
    their terminology and definitions which may mean
    slightly different things to older code cycles.

24
NFPA 99-2012 Health Care Facilities Code
  • Added three new sections to read
  • Overcurrent protective devices serving the
    essential electrical system shall be selectively
    coordinated down to 0.1 seconds.
  • Added three new annex sections to read
  • It is important that the various overcurrent
    devices be coordinated, as far as practicable, to
    isolate faulted circuits and to protect against
    cascading operation on short circuit faults. In
    many systems, however, full coordination could
    compromise safety and system reliability
  • 6.4.2.1.2.1, 6.5.2.1.1.1, 6.6.2.1.1.1
    A.6.4.2.1.2, A.6.5.2.1.1, A6.6.2.1.1

Change
25
NFPA 110-2013 Standard for Emergency and Standby
Power Systems
  • 6.5 Protection.6.5.1 General. The overcurrent
    protective devices in the EPSS shall be
    coordinated to optimize selective tripping of the
    circuit overcurrent protective devices when a
    short circuit occurs.6.5.2 Short Circuit
    Current. The maximum available short circuit
    current from both the utility source and the
    emergency energy source shall be evaluated for
    the ability to satisfy this coordination
    capability.
  • A.6.5.1 It is important that the various
    overcurrent devices be coordinated, as far as
    practicable, to isolate faulted circuits and to
    protect against cascading operation on short
    circuit faults. In many systems, however, full
    coordination is not practicable without using
    equipment that could be prohibitively costly or
    undesirable for other reasons

26
Do NFPA 99-2012 and NFPA 110-2013 conflict with
the NEC? No!
  • NFPA 70 (NEC)
  • This Code covers the installation of electrical
    conductors, equipment,
  • NFPA 99
  • Chapter 6 covers the performance, maintenance
    and testing of electrical systems
  • NFPA 110
  • This standard covers performance requirements
    for emergency and standby power systems
  • Standards Council
  • NFPA 99 is considered the performance
    requirement and the NEC is considered the
    installation requirement. (Similar statement
    made regarding NFPA 110)

27
Circuit Breaker Principles
  • Time-Current Curves (TCCs)
  • Developed by testing a single circuit breaker by
    itself
  • Two regions
  • Overload region where the circuit breaker has an
    inverse time characteristic
  • Instantaneous region where the circuit breaker
    operates instantaneously
  • The instantaneous region is typically difficult
    to coordinate for two OCPDs connected in series
  • Source IEC/TR 61912-2

28
Circuit Breaker Principles
  • Selective Coordination with 2 Circuit Breakers in
    Series Time-Current Curves (TCCs) vs. Tested
    Levels
  • TCCs
  • Developed by testing a circuit breaker by itself
  • In the instantaneous region may not be valid for
    two circuit breakers connected in series
  • Tested Levels
  • Take into account the current limiting properties
    and dynamic impedance of circuit breakers
  • Developed by comparing the actual let-through
    current of the downstream circuit breaker with
    minimum instantaneous trip of the upstream
    circuit breaker
  • Same principle as fuse ratio tables

29
Resources
  • Manufacturer references?
  • Comparable selective coordination tables and
    tools are available from Schneider Electric,
    Eaton, GE and Siemens.
  • 3rd Party System Analysis Software
  • Selective coordination information available in
    SKM, ETAP and Easypower products
  • NEMA ABP 1-2010 Selective Coordination White
    Paper
  • Provides guidance on how to comply with selective
    coordination requirements for design engineers
    and AHJs.

30
Challenges Meeting the NEC
  • Is selective coordination required up to both the
    normal and alternate sources, or only up to the
    alternate source?
  • 700.1 Scope.
  • The provisions of this article apply
    toemergency systemsintended to supply,
    distribute, and control electricitywhen the
    normal electrical supply or system is
    interrupted
  • These systems are intended to automatically
    supply illumination, power, or bothin the event
    of failure of the normal supply...
  • The scope seems to imply only up to the
    alternate source

31
Challenges Meeting the NEC
  • Is selective coordination required up to both the
    normal and alternate sources, or only up to the
    alternate source?
  • Appendix B.1 of NFPA 110 seems to imply only up
    to the alternate source

32
Challenges Meeting the NEC
  • Is selective coordination required up to both the
    normal and alternate sources, or only up to the
    alternate source?
  • 700.28 Coordination.
  • Emergency system(s) overcurrent devices shall be
    selectively coordinated with all supply side
    overcurrent protective devices.
  • Some interpret all to mean up to both sources

33
Challenges Meeting the NEC
  • Is selective coordination required up to both the
    normal and alternate sources, or only up to the
    alternate source?
  • 2011 NEC proposal 13-197 panel statement
  • devices in the normal sourceare outside the
    scope of Article 700.
  • Use NEC Selective CoordinationUp to Which
    Source? (0600DB0902) to convince the AHJ that
    total coordination is required only up to the
    alternate source
  • Level of coordination up to the normal source is
    a matter of engineering judgment
  • In the 2014 NEC revision cycle CMP13 reversed
    itself, stating that selective coordination is
    required up to both sources (ROP 13-124 ROC
    13-83) March 8, 2012

34
Selective Coordination Update
  • Common misunderstandings and pitfalls
  • Terminology review 0.1s versus total
  • We dont say 0.01s, 0.05s, 0.001s, etc.
  • 0.1s selectivity determined by TCCs accounts
    for all initial arcing and ground faults
  • Total selectivity determined by tables
    comparing tested load-side let-throughs and
    line-side instantaneous trips (AND TCCs)
    selective for the entire operating ranges of the
    protective devices and for all levels of
    available fault current
  • 0.01s terminology used, we believe mistakenly,
    intended for total coordination
  • - SC selectivity based on test information

35
Selective Coordination Update
  • Common misunderstandings and pitfalls
  • Why we dont say 0.01s, 0.05s, 0.001s, etc.
  • If the fault current exceeds their current
    limiting point, current limiting fuses operate in
    less than 0.01s
  • Current limiting fuses that coordinate down to
    0.01s may not be coordinated at higher fault
    currents
  • Current limiting fuse TCCs cut off at 0.01s
    because only the ratio tables can be used to
    evaluate total coordination below that point

36
Challenges Meeting the NEC
  • Cautions
  • Make sure automatic transfer switches have an
    adequate withstand rating (30 cycle ratings vs. 3
    cycle ratings)
  • May need to move the switch away from the source,
    or
  • May need to increase the frame size of the
    switch, or
  • May need to specify a switch with a higher
    withstand rating (more than 3 cycles)
  • Make sure busway has adequate withstand ratings

37
Challenges Meeting the NEC
  • Cautions
  • Make sure the generator protection devices
    coordinate with the downstream circuit breakers
  • Some manufacturers provide a time delay
  • Generator fault current
  • SCAgen Gen FLC / xd
  • xd gt generator subtransient reactance
  • Gen FLC kVA / (kVL-L v3)

38
Challenges Meeting the NEC
  • Cautions
  • Mixing Overcurrent Protective Devices
  • TCCs may be used so long as the fault current
    does not exceed the instantaneous trip point of
    the upstream circuit breaker or current limiting
    point of the upstream fuse
  • OCPDs from different manufacturers or of
    different types usually cannot be mixed if the
    fault current is outside the parameters described
    above

39
Challenges Meeting the NEC
  • Cautions
  • Arc Flash
  • Selective coordination may impact arc flash
    incident energy levels
  • May be possible to reduce with
  • Zone Selective Interlocking
  • Use of breakers LSI rather than the traditional
    thermal magnetic breaker.
  • Other means

40
Design Guidelines
  • Conduct Preliminary Short-Circuit Selective
    Coordination Studies First
  • Reduce the number of levels (buses) that need to
    be coordinated to 3 or 4 if possible
  • Before letting a job out for bid, conduct
    preliminary short circuit and selective
    coordination studies first as they may affect the
    system design
  • Consider 3-phase and ground fault currents
  • If a lack of coordination seems to exist using
    the TCCs, use the Short Circuit Selective
    Coordination Tables
  • Work from the Bottom Up
  • Starting from the bottom of the system,
    coordinate the branch lighting panels first, then
    the power distribution panels, then the
    switchboard or switchgear

41
Design Guidelines
  • Overlapping Curves
  • If there is no overlap of the curves at any point
    below the available short circuit current at the
    downstream panel, the circuit breakers are
    totally coordinated
  • If there is overlap in the short circuit region,
    use the short circuit selective coordination
    tables

Downstream Available Short Circuit Current
42
Design Guidelines
  • Nest Curves
  • The time-current curve of a thermal-magnetic
    circuit breaker can sometimes be nested
    underneath the time-current curve of an upstream
    electronic trip circuit breaker

Downstream Available Short Circuit Current
43
Design Guidelines
  • Lighting Panelboard Recommendations
  • Dont feed lighting panelboards from
    lighting panelboards unless there is a
    transformer in between
  • Better levels of selective coordination are
    available with 225 A and larger panelboards,
    (larger selection of breakers)
  • Consider using main lugs panels, particularly at
    277 V
  • Dont daisy chain panel risers

44
Design Guidelines
  • Ground Fault
  • Make sure system is selectively coordinated for
    ground faults
  • Make sure the GFPE also coordinates with the
    downstream phase overcurrent devices, not just
    the downstream GFPE

45
Design Guidelines
  • Transformers
  • Use the higher protection limits in Article 450
    (e.g. 250 instead of 125 FLA on the primary)
  • Consider 30 to 75 KVA transformers100 to 225 amp
    panelboards with Mission Critical Mains
  • Increase the Frame Size of the Upstream Circuit
    Breaker
  • The upstream circuit breaker should be at least
    one frame size larger than the downstream circuit
    breaker. This may necessitate increasing the
    size of panelboards and feeder conductors.
  • Very high levels of short circuit selective
    coordination may be achieved by using high amp
    frame electronic trip circuit breakers with low
    amp sensors and/or lower ampere rating
    adjustments

46
Design Guidelines
  • Rarely needed, but as a last resort...
  • Change the Upstream Circuit Breaker Type
  • Insulated case circuit breakers or low voltage
    power circuit breakers
  • Reduce the Voltage
  • If the desired level of selective coordination
    cannot be achieved using a 480Y/277 Vac
    panelboard, consider feeding a 208Y/120 Vac
    panelboard through a transformer
  • Split Up Some of the Loads
  • Multiple smaller transformers
  • Insert Impedance
  • Longer run of wire, 11 or higher impedance
    transformer or reactors

47
Design Guidelines
  • What if the AHJ requires selective coordination
    up to both the alternate and normal sources?
  • Conduct a preliminary short circuit study from
    the source that can potentially produce the
    highest SCA to the bottom of the system
  • Conduct a preliminary selective coordination
    study on that part of the system
  • Conduct a preliminary short circuit study from
    the other source to the first bus on the load
    side of the transfer switch(es)
  • Conduct a preliminary selective coordination
    study from the other source to the transfer
    switch feeder(s)

48
Design Guidelines
  • Field Adjustment
  • Dont neglect to properly adjust circuit
    breakers in the field as they are often shipped
    from the factory with all but the ampere-rating
    switch in the lowest position

49
Summary
  • Use the correct terminology!
  • Terms to use
  • Coordination
  • System to be coordinated to 0.1 s
  • Selective coordination
  • System to be selectively coordinated
  • DO NOT use coordination to 0.01s when selective
    coordination is desired

50
Summary
System Coordination to Coordination to Reference(s)
System Which Source What Level Reference(s)
Healthcare essential electrical Alternate Optimize as far as practicable 0.1s NEC-2011 700.1, 700.27 NFPA 110 6.5.1 NEC-2014 517.30(G), NFPA 99-2012
Healthcare GFPE Normal alternate Total NEC 517.17(C)
Elevator Normal Unspecified Total 1. NEC-2011 620.62 2. NEC-2014 620.62
Fire pump feeders in multi-building campus Normal Unspecified Total 1. NEC-2011 695.3(C)(3) 2. NEC-2014 695.3(C)(3)
Emergency Alternate Optimize as far as practicable Total NEC-2011 700.1, 700.27 NFPA 110 6.5.1 NEC-2014 700.28
Legally required Alternate Optimize as far as practicable Total NEC-2011 701.1, 701.27 NFPA 110 6.5.1 NEC-2014 701.1, 701.27
COPS Alternate Optimize as far as practicable Total NEC-2011 708.1, 708.54 NFPA 110 6.5.1 2. NEC-2011 708.1, 708.54
51
Questions??? Thank you!!!Justin Schroeder,
P.E.Schneider Electric USA2979 Pacific Drive,
Suite E Norcross, GA 30071Justin.Schroeder_at_schnei
der-electric.comPhone 770-734-1367
Write a Comment
User Comments (0)
About PowerShow.com