Title: Modeling and Analysis of High Volume Manufacturing Systems
1Modeling and Analysis of High Volume
Manufacturing Systems
2Discrete vs. Continuous Flow and Repetitive
Manufacturing Systems(Figures borrowed from
Heizer and Render)
3Operation Process Chart Example for discrete
part manufacturing(borrowed from Francis et. al.)
4A typical (logical) Organization of the
Production Activity in Repetitive Manufacturing
Assembly Line 1 Product Family 1
Raw Material Comp. Inventory
Finished Item Inventory
S1,1
S1,n
S1,i
S1,2
Fabrication (or Backend Operations)
Dept. 1
Dept. 2
Dept. k
Dept. j
S2,1
S2,2
S2,m
S2,i
Assembly Line 2 Product Family 2
5Major Layout Types(borrowed from Francis et. al.)
6Advantages and Limitations of the various layout
types (borrowed from Francis et. al.)
7Advantages and Limitations of the various layout
types (cont. - borrowed from Francis et. al.)
8The product-process matrix
Production volume mix
Low volume, low standardi- zation
Multiple products, low volume
High volume, high standardization, commodities
Few major products, high volume
Process type
Jumbled flow (job Shop)
Commercial printer
Void
Disconnected line flow (batch)
Heavy Equipment
Connected line flow (assembly Line)
Auto assembly
Continuous flow (chemical plants)
Sugar refinery
Void
9A conceptual characterization of the considered
environments
- Flow line A sequence of workstations supporting
the production of a single part type. - Each workstation consists of one or more
identical servers executing one particular stage
of the entire production process. - The part processing time at each workstation
follows some general distribution which must be
defined in such a way that accounts for the
various detractors affecting the station
operations these detractors will include machine
downtime, lack of consumables, operator
unavailability, experienced set-up times,
preventive maintenance, etc. - Finished parts could constitute end items or raw
material for some other downstream process. - The operation of the line workstations can be
- synchronized through an interconnecting conveyor
system, or - decoupled through the installation of some
buffering capacity between them.
10Line Performance Measures
- Production rate or throughput, i.e., the number
of parts produced per unit time - Line capacity, i.e., the maximum sustainable
production rate - Line (expected) cycle time, i.e., the average
time that is spend by any part into the line
(this quantity includes both, processing and
waiting time). - Average Work-In-Porcess (WIP) accumulated at
different stations - Expected utilization of the station servers.
- Remark The above performance measures
essentially provide a link between the directly
quantifiable and manageable aspects and
attributes of the considered operational
environments and the primary strategic concerns
of the company, especially those of
responsiveness and cost efficiency.
11Production Authorization Mechanisms
- The issue here is to what extent part production
is triggered from actual orders or from
forecasted demand. - In a produce-to-stock scheme, a certain amount
of end-item inventory is maintained in an effort
to serve the experienced demand with zero lead
time. - Produce-to-stock operation is most appropriate
for highly commoditized and standardized items. - A key performance measure for produce-to-stock
production systems is the fill rate, i.e. the
percentage of the experienced demand that is
actually met from stock. A desired fill rate is
attained by maintaining an appropriate safety
stock level, that is computed from the statistics
of the experienced demand and cycle times. - In a produce-to-order scheme, end items are
produced in response to particular orders. - Produce-to-order operation is more appropriate
for (highly) customized items. - A key performance measure for produce-to-order
production is the attained service level, i.e.
the percentage of orders that are served within
the quoted lead time. A target service level is
attained through informed lead time quotation and
some appropriate capacity buffer. - Currently, many systems are a hybrid scheme
consisting of produce-to-stock and
produce-to-order components. In particular,
mass customization is supported by an
assemble-to-order scheme where end-items are
assembled to order from a number of
sub-assemblies that are produced to stock.
12Shop-Floor / Line Control Mechanisms
- Mechanisms that control the part release and
advancement through the line. - They are broadly distinguished into push and
pull mechanisms. - A push mechanism releases material into the
line according to a target production rate, and
material is advanced to downstream stations as
early as possible. - Typical instantiations of push systems are the
asynchronous transfer line and the synchronous
transfer line. - A pull system controls the part release and
advancement in the line taking into consideration
the status of the various workstations in the
line. - Typical instantiations of pull systems are the
KANBAN and the CONWIP (controlled) production
lines. - In general, pull systems reduce congestion,
since they take into consideration the actual
shop-floor status in their decision making, but
the same mechanisms will also make them more
inert in case of shifts in the production level. - Both mechanisms are effectively implementable in
a produce-to-stock or produce-to-order
context.
13Asynchronous Transfer Lines
W1
W2
W3
TH
TH
TH
TH
B1
B2
B3
M1
M2
M3
- Some important issues
- What is the maximum throughput that is
sustainable through this line? - What is the expected cycle time through the
line? - What is the expected WIP at the different
stations of the line? - What is the expected utilization of the
different machines? - How does the adopted batch size affect the
performance of the line? - How do different detractors, like machine
breakdowns, setups, and maintenance, affect the
performance of the line?
14Synchronous Transfer Lines
- The key issue Assembly Line Balancing (ALB)
- Given
- a set of tasks to be supported by the line
stations - each possessing a nominal processing time,
- a number of precedence constraints among these
tasks, - and a target throughput,
- determine
- a partitioning of these tasks to a number of
stations that observes the aforementioned
specifications, while it minimizes the resulting
number of stations (and therefore, the resulting
labor cost).
15KANBAN-based production lines
- Some important issues
- What is the throughput attainable by a certain
selection of KANBAN levels? - What is the resulting cycle time?
- How do we select the KANBAN levels that will
attain a desired production rate? - How do we introduce the various operational
detractors into the model?
16CONWIP-based production lines
- Some important issues
- Same as those for the KANBAN model, plus
- How can we compare the performance of such a
system to that of an asynchronous transfer line
and/or a KANBAN-based system?
17Module Objectives
- Provide an analytical characterization of the
operation of HVM systems and their performance,
based on queueing-theoretic models - Derive qualitative insights and quantitative
results on the attributes and factors that shape
the behavior and performance of these systems. - Demonstrate the application of these results to
the design and control of the considered class of
systems - Focus primarily on flow lines, since they are the
main layout used in the context of high-volume,
repetitive manufacturing. - Also, flow line dynamics are easier to trace and
analyze, and therefore, more enlightening in
terms of qualitative and quantitative insights. - However, many of the derived insights and results
are extensible to more complex environments
either directly or through some appropriate
decomposition.
18Plan for the remaining part of the module
- Modeling and Performance Analysis of Asynchronous
Transfer Lines through a Series of G/G/m queues - Modeling the impact of operational detractors
- Employing the above results in line diagnostics
- Design of Asynchronous Transfer Lines
- Design of Synchronous Transfer Lines (cf. the ALB
problem in the module on Sequencing, Dispatching
and Scheduling of HVM systems) - Modeling and Performance Analysis of CONWIP-based
production lines through Closed Queueing Networks - An integrating framework for bounding and shaping
the performance of a production line - Analyzing the impact of batching on the system
performance and designing optimized batching
policies - Understanding the relative advantages and
disadvantages of the various push and
pull-based production systems
19The G/G/1 model
- Modeling Assumptions
- Part release rate Target throughput rate TH
- Infinite Buffering Capacity
- m identical servers
- Server mean processing time te
- St. deviation of processing time ?e
- Coefficient of variation (CV) of processing
time ce ?e / te - Coefficient of variation of inter-arrival times
ca
20Performance measures for the G/G/1 station
- Server utilization
- Expected cycle time in the buffer
(Kingmans
approx.) - Expected cycle time in the station
- Average WIP in the buffer
(by Littles law) - Average WIP in the station
- Squared CV of the inter-departure times
21Some Important Remarks
- The entire analysis of the previous slide is an
approximation, since it derives from the provided
approximation for CTq. - The provided formula for CTq is exact for the
M/M/m and M/G/1 stations. - The station operation will be stable only if u
TH te / m lt 1.0, i.e., only if the effective
workload released into the station per unit of
time is less than the available processing time
of the station. Otherwise WIPq, CTq and CT will
grow infinitely large. - Notice that the requirement u lt 1.0 is also
suggested by the provided expression for CTq
since only then CTq takes finite positive values. - The expression for CTq comprises three factors,
each depending respectively upon (i) the
variability of the processing and inter-arrival
times, as expressed by the corresponding SCVs,
(ii) the server utilization, and (iii) the mean
processing time. An increase of any of these
factors results in an increase of CTq, and also
of CT, WIPq and WIP. - Assuming a non-zero mean processing time, CTq0.0
only if ca2 ce20.0 these are essentially the
conditions of a paced / synchronous production
line. - The SCV of the inter-departure times can be
approximated as a linear function of the SCVs of
the inter-arrival and processing times.
Furthermore, for u?1.0, cd2 depends primarily on
ce2, while for u?0, cd2 depends primarily on
ca2.
22Analyzing an entire Production Line
TH
- Key observations
- A target production rate TH is achievable only
if each station satisfies the stability
requirement u lt 1.0. - For a stable system, the average production rate
of every station will be equal to TH. - For every pair of stations, the inter-departure
times of the first constitute the inter-arrival
times of the second. - Then, the entire line can be evaluated on a
station by station basis, working from the first
station to the last, and using the equations for
the basic G/G/1 model.
23Modeling the impact of operational detractors
- Effective processing time time that the part
occupies the server - Effective processing time Actual processing
time - any additional non-processing time
- Actual or otherwise natural processing time
typically presents fairly low variability ( SCV lt
1.0). - Non-processing time is due to detractors like
machine breakdowns, setups, operator
unavailability, lack of consumables, etc. - Detractors are distinguished to preemptive and
non-preemptive. Each of these categories requires
a different analytical treatment. - Preemptive detractors are outages that take place
during the actual processing of the part. Typical
examples are machine breakdowns, lack of
consumables, operator unavailability, etc. - Non-preemptive detractors are activities that may
take place between the processing of two
consecutive parts. Typical examples are setups,
preventive maintenance, operator breaks, etc. - We want to determine the mean, variance and SCV
of the effective processing time from the
corresponding attributes of the natural
processing time and some additional attributes
characterizing the behavior of the various
detractors.
24Modeling the impact of preemptive detractors
- X random variable modeling the natural
processing time, following a general
distribution. - to EX ?o2VarX co?o / to .
- T random variable modeling the effective
processing time where - Ui random variable modeling the duration of the
i-th outage, following a general distribution,
and - N random variable modeling the number of
outages during a the processing of a single
part. - mrEUi ?r2VarUi cr ?r / mr
- Time between outages is exponentially distributed
with mean mf. - Availability A mf / (mfmr) percentage of
time the system is up. - Then,
- te ET to / A or equivalently re 1/te
A (1/to) A? ro -
25Breakdown Example
- Data Injection molding machine has
- 15 second stroke (to 15 sec)
- 1 second standard deviation (?o 1 sec)
- 8 hour mean time to failure (mf 28800 sec)
- 1 hour repair time (mr 3600 sec)
- Natural variabilityco 1/15 0.067 (which is
very low)
26Example Continued
Which is very high!
27Example Continued
- Suppose through a preventive maintenance program,
we can reduce mf to 8 min and mr to 1 min
(the same as before)
Which is low!
28Modeling the impact of non-preemptive detractors
- X random variable modeling the natural
processing time, following a general
distribution. - to EX ?o2VarX co?o / to .
- NS average number of parts processed between
two consecutive setups - It is also assumed that the number of parts
between two consecutive setups follows a
geometric distribution, which when combined with
the previous bullet, it implies that probability
for a setup after any given job 1/ NS. - Z random variable modeling the duration of a
setup - tS EZ ?S2 VarZ
- S random variable modeling the setup time
experienced by any given job - T random variable modeling the effective
processing time XS - Then,
- ES tS / NS VarS (?S2 / NS)
tS2((NS-1) / NS2) - te ET totS / NS
-
-
29Setup Example
- Data
- Fast, inflexible machine 2 hr setup every 10
jobs - to 1 hr
- Ns 10 jobs/setup
- ts 2 hrs
- re 1/te 1/(12/10) 0.8333 jobs/hr
- Slower, flexible machine (with no setups!)
- to 1.2 hr
- re 1/to 1/(1.2) 0.8333 jobs/hr
So with traditional analysis, there is no
difference!
30Example Continued
- Slower, flexible machine no setups
- to 1.2 hr
- co20.25
- re 1/to 1/(1.2) 0.8333 jobs/hr
- ce2 co2 0.25
- Conclusion
- Flexibility reduces variability
31Example Continued
- Considering mean and variability
- Fast, inflexible machine 2 hr setup every 10
jobs - to 1 hr and ts 2 hr
- co20.0625
- Ns 10 jobs/setup
- te 12/10 1.2 hrs
- re 1/te 1/(12/10) 0.8333 jobs/hr
- re 1/to 1/(1.2) 0.8333 jobs/hr
- ?e2 0.4475
- ce2 0.31
32Example Continued
Consider a third machine that is the same as the
previous machine with setups, but with shorter,
more frequent setups Ns 5 jobs/setup ts
1 hr
Analysis
- Conclusion
- Shorter, more frequent setups induce less
variability
33Example Employing the presented results for line
diagnostics
Desired throughput is TH 2.4 jobs / hr but
practical experience has shown that it is not
attainable by this line. We need to understand
why this is not possible.
34Diagnostics example continuedCapacity analysis
based on mean values
35Diagnostics example continuedAn analysis based
on the G/G/1 model
i.e., the long outages of M1, combined with the
inadequate capacity of the interconnecting
buffer, starve the bottleneck!
36Example Designing an asynchronous prod. line
- Design of a new 4-station assembly line for
circuit board assembly. - The four consecutive stations and the currently
considered technology options for them (each
option defines the processing rate in pieces per
hour, the CV of the processing time, and the cost
per unit in thousands of dollars). -
- The above data correspond to the effective
processing times. - Each station can employ only one technology
option. - The maximum production rate to be supported by
the line is 1000 panels / day. - The desired average cycle time through the line
is one day. - One day is equivalent to one 8-hour shift.
- Workpieces will go through the line in totes of
50 panels each, which will be released - into the line at a constant rate determined by
the target production rate. - Design task Identify a line configuration that
meets the above requirements while - minimizing the equipment cost.
- Also, estimate the expected WIP at every
station, when the line is operated at - maximum production rate.
37A baseline designMeeting the desired prod. rate
with a low cost
38Reducing the line cycle time by adding capacity
to Station 2
39Adding capacity at Station 1, the new bottleneck
40An alternative optionEmploy less variable
machines at Station 1
This option is dominated by the previous one
since it presents a higher CT and also a higher
deployment cost. However, final selection(s) must
be assessed and validated through simulation.
41Analyzing CONWIP-based flowlines with
single-machine stations as Closed Queueing
Networks (CQNs)
- Mean Value Analysis - the key underlying ideas
- A CONWIP-based flow line with single-machine
stations and its WIP level set to W, can be
modeled by a closed queueing network (CQN) with
general processing distributions, W jobs in it,
and the following structure - II. In a CQN with W jobs and exponential
processing times, the expected number of jobs
observed at the various stations by a job
arriving at some station Sj, is equal to the
expected number of jobs observed at any random
time at the same stations when the system is
operated with W-1 jobs in it. - III. Assuming that this effect applies in an
approximate sense for more general distributions
of the processing times, we proceed to develop an
algorithm that will compute the performance
measures of interest iteratively, for various W
levels, starting with W0. -
?
?
?
M1
M2
Mn
42Notation
n number of stations te(j) mean effective
processing time at station j ce2(j) SCV for
effective processing time at station j TH(W)
the line throughput when operated with WIP level
W CT(W) expected job cycle time through the
line CTj(W) expected job cycle time at station
j when the WIP level is W WIPj(W) expected WIP
level at station j when the WIP level is W uj(W)
utilization of the server at station j when the
WIP level is W
43Deriving the algorithm iteration
- CTj(W) Eremaining processing time for the job
at the server of Sj - (Enumber of jobs at station Sj-Enumber of
jobs in service)te(j) - te(j)
- But
- Eremaining processing time for the job at the
server of Sj - Prob(Server of Sj busy)?Eremaining process time
busy - uj(W-1)?Eremaining process time busy ?
- (b) Enumber of jobs at station Sj ? WIPj(W-1)
- Enumber of jobs in service ? uj(W-1)
- (d) uj(W-1) TH(W-1)? te(j)
44Deriving the algorithm iteration (cont.)
Combining the results of the previous
slide But then, Obviously, for W0, CT(0)
TH(0) WIPj(0) 0 Furthermore, application of
the above formulae for W1 gives
(from Littles law)
45Bounding the line throughputUpper bounds
- For W??, TH(W)?rb?minj1/te(j), the bottleneck
rate of the line. - rb can also be achieved with finite WIP in a
deterministic setting, i.e., in a line with
ce(j) 0, ?j, and synchronized with pace
tb1/rb. - However, by Littles law, a line with raw
process time To, in order to produce at rate rb,
will need a WIP level of WorbTo this WIP level
is known as critical WIP. - An interpretation of Wo is given by the
following formula - i.e., Wo is the level of WIP that we must
maintain in the system in order to maintain the
bottleneck utilization at 100. Otherwise, the
bottleneck will starve. - If WltWo, then in a deterministic setting we can
pace the jobs through the system in such a way
that CTTo. Hence, the maximal line throughput
will be
46Example Attaining the throughput upper bound
with balanced, deterministically paced line
47Bounding the line throughputLower bounds (under
global non-idleness)
- Clearly, 1/To is a lower bound to TH(W) under
global non-idleness, since this is the rate of a
line with only one job in it, and therefore, no
parallelism. - This bound is also achievable under any other
finite WIP level W, by a non-idling policy that
moves all W jobs as a single batch from station
to station. Indeed, for that policy
48Example Attaining the throughput lower bound
through batching
t1
t2
t3
t4
2.0
W3
T 0
T 6
T 12
T 18
T 24
TH W / (W? To) 3 / 24 1 / 8
49The W-TH(W) space
TH(W)
Ideal Operational Point
rb
1/To
1/To
1
WorbTo
W
50The W-CT(W) Space
The depicted curves are induced from those
depicted in the W-TH(W) space, through Littles
law. In particular, upper bounds in the W-TH(W)
space provide lower bounds in the W-CT(W) space,
and vice versa, as follows
51Practical System Performance
- The ideal performance is attained in an
optimized, deterministic setting. this
performance is typically compromised by - the variability that is inherent in the system
operations - the impact of the applied control policies
(e.g., the batching policy that defines the lower
bounds for the system throughput - Notice,
however, that these policies might be justified
from some broader considerations). - A benchmark case Maximizing the variability
inherent in the system operation - Single-machine stations
- Exponential processing times
- Balanced line, i.e., te(j) t, ?j
- Key feature All feasible states for this line
are equiprobable. - Mean Value Analysis (exact, since processing
times are exponential)
Remarks As expected, TH(1) rb/Wo 1/To and
TH(?) rb. A performance that is worse than that
of the benchmark case is a strong indication of
mismanagement / bad practice.
52Effective Mechanisms for Improving the System
Performance
The problem Given a line operating at a desired
throughput rate, TH, what are some possible
mechanisms to reduce the expected cycle time
through the line, CT (and through Littles law,
the line WIP, W) ? The key idea We need to
pull the curve describing the line performance
in the W-TH(W) space to the left. (i) Increase
rb (by adding capacity or making more effective
use of the existing capacity at the line
bottleneck(s))
53Effective Mechanisms for Improving the System
Performance (cont.)
(ii) Add capacity to some non-bottleneck
station(s) (this addition essentially enables the
better catering to the bottleneck needs, but it
can help only to a limited extent)
TH(W)
rbrb
TH
1/To
1/To
1/To
1/To
W
Wo
1
W
Wo
W
(iii) Reduce the inherent variability at the
different stations the corresponding reduction
of the station CVs will pull the performance
curve in the W-TH(W) space closer to the curve
characterizing the upper bound. (iv) Increase
the line flexibility, which essentially enables
the better utilization of the bottleneck capacity
(and takes us back to item (i) above).
54Demonstrating the inertia of CONWIP lines
Problem Consider a CONWIP line operated at 80
of its bottleneck rate. Furthermore, the
performance of the line compares favorably to
that of the benchmark case, and WgtgtWo so that
?CT??W/rb. Compute the relative increase ?W/W
that will increase the line throughput to 85 of
its bottleneck rate. Solution Let ?WW-WxW.
Then,
i.e., the necessary increase is almost 42 of the
original WIP!
55Batching
- Batching implies the physical or logical grouping
of a number of parts processed through (different
segments of) the system. - Possible reasons for batching
- High set up times and costs gt need for serial
process batching to control the capacity losses - Processes that require a large production volume
in order to maintain a high utilization (e.g.,
fermentors, furnaces, etc.) gt need for parallel
process batching - An excessive and/or costly material handling
activity gt need for move or transfer batching - From the vantage of the processing taking place
at the different stations, batching is an
additional source of variability in the
inter-arrival and/or processing times, and
therefore, a source of delays. - Hence, a pertinent batch size
- must be large enough to
- maintain feasibility of the production
requirements and/or - help control the target operational costs
- but not too large so that it incurs unnecessary
- part delays and/or
- inventory holding costs
56Example Optimizing Parallel Batches through a
queueing-theoretic approach
Model Parameters k (parallel) batch size B
maximum batch size ra arrival rate
(parts/hr) ca CV of inter-arrival times t
batch processing time (hrs) ce CV for effective
batch processing time
Then CT WTBT CTqt
From the above,
Remark Notice that CT? as u?1 but also as u?0 !
57Determining an optimal batch size
Let um ? rat . Then u um / k ? k um / u .
Substituting this expression for k in the
expression for CT, we get
and we get
Recognizing that
, we set
where
To minimize CT, it suffices to minimize y(u).
This can be achieved as follows
and
which further implies that
Remark If ce2 ? 0, the term ? in the original
expression for u will significant. In that case,
we can set
and obtain u and k as before.
58Some implications of the derived results
- Minimum feasible batch size may be greater than
one - If process times are long enough and batch
capacity large enough, cycle time will be
minimized with a batch size greater than one - Eventually cycle time grows proportionally with
batch size - Without wait-for-batch time, cycle time decreases
in batch size
59Parallel Batching Example
- Parameters
- k batch size (10)
- te time to process a batch (90)
- ce2 SCV for batch (1)
- ra arrival rate for parts (0.05)
- ca2 SCV of batch arrivals (1.0)
60Determining the minimum batch size
- Time to process batch te 90
- Arrival of batches ra/k 0.005
- Utilization u (ra/k)(te) 0.45
- For stability u lt 1 implies
61Estimating the delays experienced at the batch
station
- Average wait-for-batch time
- Average queue time at station
- Total cycle time
- WTBTCTqte 220.5
62Serial Batching ExampleSingle processing station
- Parameters
- k batch size (10)
- to time to process a singe part (1)
- ts time to perform a setup (5)
- ce2 SCV for batch (parts setup) (0.5)
- ra arrival rate for parts (0.4)
- ca2 SCV of batch arrivals (1.0)
63Determining a minimum batch size
- Time for batch te ts kto 15
- Arrival of batches ra/k 0.04
- Utilization u (ra/k)(tskto) 0.6
- For stability u lt 1 implies
64Estimating the experienced delays
- Average queue time at station
- Average cycle time depends on move batch size
- Move batch process batch (non-split)
- Move batch 1 (split)
65Serial Batching Effect
- Minimum feasible batch size may be greater than
one - If setup times are long enough, cycle time will
be minimized with a batch size greater than one - Eventually cycle time grows proportionally with
batch size
66Move Batches
- Cycle times over a segment of a routing are
roughly proportional to the move batch sizes used
over that segment.
For 2 machines in series
67Move Batching Effect
- Cycle time increases proportionally with the
move batch size - Low arrival rates cause long wait for batch
times - Inflation term does not depend on CV
- Batching delay is essentially separate from
variability delay - Congestion from batching is more bad control
than variation
68On the relative advantages of push and
pull-based production systems
- The WIP cap employed by pull systems provides a
feedback mechanism for reacting to operational
disruptions and prevents congestion. - The avoidance of congestion further facilitates
more flexible and responsive decision making in
reaction to arising contingencies. - Another benefit from avoiding congestion is that
the WIP necessary to elicit a certain throughput,
TH, from a pull system is typically lower than
the WIP accumulated in this system when it is
operated in a push mode and with the feeding
rate equal to TH. - WIP as a control variable is more easily
measurable than throughput. - The performance attained by a pull system is
robust to the selection of the WIP level. - However, this robustness also implies that the
production rate of a pull system cannot be
easily controlled through WIP cap adjustments,
which further implies that effective deployment
of pull systems necessitates non-volatile
demand profiles (and raises the issue of active
demand management). - CONWIP systems can achieve higher throughput than
their KANBAN-based counterparts because they
provide the aforementioned advantages of
pull-based operation while eliminating the
negative impact of (internal) blocking that is
inherent in the KANBAN mechanism.
69Suggested Readings
- Hopp Spearman, Factory Physics, 2nd ed.,
Irwin-McGraw Hill, 2001 - Cachon and Terwiesch, Matching Supply with
Demand An Introduction to Operations Management,
Irwin-McGraw Hill, 2006 - Buzacott and Shanthikumar, Stochastic Models of
Manufacturing Systems, Prentice Hall, 1993 - Viswanadham and Narahari, Performance Modeling of
Automated Manufacturing Systems, Prentice Hall,
1992