Title: Straumann USA
1Straumann USA
60 Minuteman Road Andover, MA
Kevin Kaufman Mechanical Option
The Pennsylvania State University Architectural
Engineering
2Presentation Outline
Straumann USA
- INTRODUCTION
- Existing
- Conditions
- Design
- Objectives
- Mechanical
- Alternatives
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
- Existing conditions
- Design Objectives
- Mechanical Alternatives
- Electrical Breadth
- Construction Breadth
- Life Cycle Cost Analysis
- Conclusions
Kevin Kaufman Mechanical Option
3Building Background
Straumann USA
- Introduction
- EXISTING
- CONDITIONS
- Design
- Objectives
- Mechanical
- Alternatives
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
- Manufacturing Area
- Manufacturing storage and support areas
- Dental training and operatory
- Administrative offices
Kevin Kaufman Mechanical Option
4Original Project
Straumann USA
- Renovation of 153,000ft2
- Complete airside upgrade
- No central plant changes
- Construction May 2004 May 2005
- Cost 10.6 million
- Introduction
- EXISTING
- CONDITIONS
- Design
- Objectives
- Mechanical
- Alternatives
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
Kevin Kaufman Mechanical Option
5Mechanical Systems
Straumann USA
- 9 VAV AHUs
- 1 CAV AHU
- 2 natural gas boilers
- (11.3 MBH)
- Introduction
- EXISTING
- CONDITIONS
- Design
- Objectives
- Mechanical
- Alternatives
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
- 3 centrifugal chillers
- (750, 500, 350 tons)
- 2 cooling towers
- (750, 680 tons)
1st Floor
Mezzanine
Kevin Kaufman Mechanical Option
6Design Objectives
Straumann USA
- Introduction
- Existing
- Conditions
- DESIGN
- OBJECTIVES
- Mechanical
- Alternatives
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
- Educational experience
- Reduce annual energy costs
- Provide a lower 20 year LCC
Kevin Kaufman Mechanical Option
7System Comparisons
Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- MECHANICAL
- ALTERNATIVES
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
- Airside
- VAV vs DOAS
- Waterside
- Chillers
- Direct-fire Absorption
- Electric Centrifugal
- Waterside Free Cooling
- Series
- Parallel
Kevin Kaufman Mechanical Option
8VAV System Advantages
Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- MECHANICAL
- ALTERNATIVES
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
- Single system for ventilation and space cooling
- Full air side economizing available
- Lower pumping costs than DOAS
Kevin Kaufman Mechanical Option
9DOAS System Advantages
Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- MECHANICAL
- ALTERNATIVES
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
- Reduced fan energy costs
- Smaller air-handling units require less space and
are cheaper - Decouples sensible and latent loads
Kevin Kaufman Mechanical Option
10DOAS Rooftop Unit Zones
Straumann USA
- Reduced from 10 to 8 zones
- Introduction
- Existing
- Conditions
- Design
- Objectives
- MECHANICAL
- ALTERNATIVES
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
Kevin Kaufman Mechanical Option
11DOAS Design
Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- MECHANICAL
- ALTERNATIVES
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
- Radiant panel capacity 54 Btu/ft2
- Space DPT 55F
- Water MWT 56.5F
Radiant Panel (Sterling)
- Ventilation rate ASHRAE 62.1
- Design Temperatures
- Winter 7.7F
- Summer 90.8F/73.7F
Kevin Kaufman Mechanical Option
12Annual Energy Cost Comparison
Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- MECHANICAL
- ALTERNATIVES
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
Kevin Kaufman Mechanical Option
13Direct-fire Absorption Chiller
Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- MECHANICAL
- ALTERNATIVES
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
- Reduce electric load and demand
- Natural gas available on site
- Possibility for simultaneous heating and cooling
Absorption Chiller (Carrier)
Kevin Kaufman Mechanical Option
14Chiller Annual Energy Comparison
Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- MECHANICAL
- ALTERNATIVES
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
Kevin Kaufman Mechanical Option
15Waterside Free Cooling - Parallel
Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- MECHANICAL
- ALTERNATIVES
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
- Reject heat without a chiller
- Must be able to reject entire load
Kevin Kaufman Mechanical Option
16Waterside Free Cooling - Parallel
Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- MECHANICAL
- ALTERNATIVES
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
- Reject heat without a chiller
- Must be able to reject entire load
Kevin Kaufman Mechanical Option
17Waterside Free Cooling - Parallel
Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- MECHANICAL
- ALTERNATIVES
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
- Reject heat without a chiller
- Must be able to reject entire load
Kevin Kaufman Mechanical Option
18Waterside Free Cooling - Series
Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- MECHANICAL
- ALTERNATIVES
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
- Partially or completely rejects heat from chilled
water - Operates more hours than parallel
- Requires more complex controls
Kevin Kaufman Mechanical Option
19Waterside Free Cooling - Series
Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- MECHANICAL
- ALTERNATIVES
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
- Partially or completely rejects heat from chilled
water - Operates more hours than parallel
- Requires more complex controls
Kevin Kaufman Mechanical Option
20Waterside Free Cooling - Series
Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- MECHANICAL
- ALTERNATIVES
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
- Partially or completely rejects heat from chilled
water - Operates more hours than parallel
- Requires more complex controls
Kevin Kaufman Mechanical Option
21Waterside Free Cooling - Series
Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- MECHANICAL
- ALTERNATIVES
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
- Partially or completely rejects heat from chilled
water - Operates more hours than parallel
- Requires more complex controls
Kevin Kaufman Mechanical Option
22Waterside Free Cooling - Results
Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- MECHANICAL
- ALTERNATIVES
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
Kevin Kaufman Mechanical Option
23Electrical Breadth
Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- Mechanical
- Alternatives
- ELECTRICAL
- BREADTH
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
Kevin Kaufman Mechanical Option
24Electrical Breadth
Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- Mechanical
- Alternatives
- ELECTRICAL
- BREADTH
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
Kevin Kaufman Mechanical Option
25Construction Breadth
Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- Mechanical
- Alternatives
- Electrical
- Breadth
- CONSRUCTION
- BREADTH
- Life Cycle
- Cost Analysis
- Conclusions
Kevin Kaufman Mechanical Option
26Construction Breadth
Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- Mechanical
- Alternatives
- Electrical
- Breadth
- CONSRUCTION
- BREADTH
- Life Cycle
- Cost Analysis
- Conclusions
Kevin Kaufman Mechanical Option
27Life Cycle Cost Analysis
Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- Mechanical
- Alternatives
- Electrical
- Breadth
- Construction
- Breadth
- LIFE CYCLE
- COST ANALYSIS
- Conclusions
Kevin Kaufman Mechanical Option
28Conclusions
Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- Mechanical
- Alternatives
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- CONCLUSIONS
- DOAS has a higher initial cost but has a lower
annual operating cost and can be paid back in 3.7
years. - Absorption chillers increase annual operating
costs. - Series waterside free cooling adds a few
additional hours of free cooling but will add
more complex controls.
Kevin Kaufman Mechanical Option
29Acknowledgements
Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- Mechanical
- Alternatives
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
- AE Department
- Mechanical Faculty
- Bruce Chappell
- William McGee
- Paul Petrilli
- Straumann USA
- Brickstone Companies
- Justin Bem
- Markus Benzenhofer
Questions?
Kevin Kaufman Mechanical Option
30Chiller Heater Feasibility
Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- MECHANICAL
- ALTERNATIVES
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
- Heating requirements 3222 hrs
- Simultaneous heating/cooling available 733 hrs
- Capable of meeting heating load 507 hrs (16)
Kevin Kaufman Mechanical Option
31Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- Mechanical
- Alternatives
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
Costs/ft2 Costs/ft2 Costs/ft2 Costs/ft2 Costs/ft2
Component Electric Electric Absorption Absorption
Component Straumann VAV Straumann DOAS Straumann VAV Straumann DOAS
Air System Fans 0.47 0.33 0.47 0.33
Cooling 0.42 0.41 0.70 0.60
Heating 0.28 0.13 0.28 0.13
Pumps 0.12 0.16 0.14 0.19
Cooling Tower Fans 0.06 0.06 0.09 0.06
HVAC Sub-Total 1.35 1.09 1.69 1.32
Lights 0.45 0.45 0.45 0.45
Electric Equipment 2.77 2.77 2.77 2.77
Non-HVAC Sub-Total 3.22 3.22 3.22 3.22
Grand Total 4.57 4.31 4.91 4.53
Component Energy (MMBTU) Energy (MMBTU) Energy (MMBTU) Energy (MMBTU)
Component Electric Centrifugal Chiller Electric Centrifugal Chiller Direct-fired Absorbtion Chiller Direct-fired Absorbtion Chiller
Component Straumann VAV Straumann DOAS/VAV Straumann VAV Straumann DOAS/VAV
Air System Fans 1,564 1,093 1,564 1,093
Cooling 1,229 1,202 5,838 5,072
Heating 1,250 616 1,250 616
Pumps 356 455 439 542
Cooling Tower Fans 156 155 246 146
HVAC Sub-Total 4,554 3,521 9,337 7,468
Lights 1,509 1,509 1,509 1,509
Electric Equipment 9,326 9,326 9,326 9,326
Non-HVAC Sub-Total 10,835 10,835 10,835 10,835
Grand Total 15,389 14,356 20,172 18,303
Kevin Kaufman Mechanical Option
32Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- Mechanical
- Alternatives
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
Kevin Kaufman Mechanical Option
33Straumann USA
- Introduction
- Existing
- Conditions
- Design
- Objectives
- Mechanical
- Alternatives
- Electrical
- Breadth
- Construction
- Breadth
- Life Cycle
- Cost Analysis
- Conclusions
Kevin Kaufman Mechanical Option