1Ohana Delay Line
- Installation at the summit
- Friday, October 13th 06
- Pierre Fedou, LESIA
2Agenda
- Background
- Delay Line Installation
- Road Map
3Background
- Ohana will connect
- CFHT and Gemini telescopes
- Via a fiber link
Main sub systems - Injection modules - Optical
fiber links - Delay Line, ? our topic today -
Beam combiner and IR camera
4Background
Injection modules status
- CFHT Jun and Aug 02,
- J, H, K band
- Keck I, Dec 02, K
- Gemini, Jul 03,
- H, K
5Background
Fiber link status
- Keck, installation Aug 04
- Tests Dec 04, Jun 05, K band
- May 06, H and K
6Background
Beam combiner IR camera status
- Jun 03 Oct 03 on IOTA,
- H, K band
- Jun 06, J, H, K
7Delay Line
- Designed in 03 and before
- Built and tested, in France, mid 04 to mid 06
- Now ready to be re-installed at CFHT
8Delay Line
Translating stage
Translating stage
Input 1
Input 2
Fast scan
Central carriage
Output 2
Output 1
9Delay Line
- 3 or 4 missions of 3 weeks
- Oct 06 Hardware
- Jan 07 Opto-mechanical first lignment
- Mar 07 Alignment continued
- May 07 Optional
10Delay line subsystem
- Translating stage Aerotech
- Translating stage Schneeberger
- Central carriage
- Railways
- 6 metallic frames
- Fast Scan
- One computer
11(No Transcript)
12Dec 03
Module 1, version 1.0
13New Module 1
Stone
14SchneeBerger end
Aerotech end
Control command
15Schneeberger end, looking outside
Schneeberger trans. stage
Central carriage
Module 6
Module 5
rails
16Schneeberger end, looking inside
Module 3
rails
Module 4
Module 5
Central carriage
17Aerotech end, looking outside
Aerotech translation stage
Module 1
Driving belt
MeterDrive
Stone
18Aerotech end, looking inside
Aerotech
Stone
Module 1
19Delay line
- Our goals for this mission
- Opening crates
- Moving big hardware in Coude Room
- Make first alignment of structure
- Rails positioning 1 mm over 12.50 m
20Delay line
- Here is the line just before leaving
21Delay line
22Delay line
The 7th crate concerns injection modules
7 crates 6 1 2 metallic frames 2 metallic
frames Aero metallic frame Schnee metallic
frame Rails Aerotech on its stone bed
Open question where do we stock this
7th? Closed? Opened?
23Delay line
OK, lets open crates!
Nail draw
Hammer
24Delay line
One module weighs 80 kg and is 210 cm long
One crate, two modules
25Delay line
Small parcels
26Delay line
rails
Small parcel
27Delay line
wedges
Need a (transportable) lifting jack
28Delay line
Metallic paper
Thermal soldering
29Delay line
Vacuum cleaner
Thermal soldering
30Delay line
Stabilized air
Plastic film
31Delay line
Ready to be closed
In progress
Wedge
32Delay line
Wall of wood
Wedge
33Delay line
Need a Nail Puller?
Electric Hammer
34Delay line
Roof of wood
Plastic film
35Delay line
We did it!
36Delay line
Aerotech side
Beam combiner Table
Schnee side
Total Length 14390mm Total Width 930mm
37Delay line
Beam combiner Table
38Delay line
Week 1, Monday 16th crates opened and all
heavy parts moved in the Coude Room, Day Crew and
Meudon Week 2, Monday 23rd small pieces are
moved and alignment made by Meudon Week 3,
Monday 30th continued, overturning, extra time
just in case
39Road map
- Delay Line installation Oct 06 -gt spring 07
- Injection Modules time has been asked on Keck
- Fiber Link beetween Gemini and CFHT summer 07
- Beam Combiner installation spring to summer 07
- Determination of length of the base on going
effort with IGN and OCA - First light when ready, fall 07?