Title: Integrating Environmental, Engineering and Constructability Considerations in Wind Power Development
1Integrating Environmental, Engineering and
Constructability Considerations in Wind Power
Development
- Anntonette Alberti, JD
- Tetra Tech, Inc.
2Goals of the Presentation
- Provide an overview of the wind generating
facility development process - Describe the inter-relation of environmental,
engineering and constructability data on each
phase of wind farm development - Site Screening
- Conceptual Design
- Final Design
- Permitting
- Construction
- Operations and Maintenance
- Stress the importance of designing and permitting
constructable and economic wind projects
3Overview of the Development Process
4Site Selection/Screening
- Two most basic questions
- Is the site windy?
- Is the site near adequate take away
transmission? - If you pass the basic questions then
- Investigate availability of land
- Investigate public and local government
acceptability - Investigate environmental and engineering
considerations - Critical Issues Analysis
- Regulatory Strategy
5Critical Issues Analysis
- Critical Issues Analysis is a study that
- Identifies conditions at the proposed project
site - Identifies likely siting issues
- Projects impacts on schedule/budget
- Provides management strategies to reduce impacts
on schedule/budget - Components include
- Phase I - Desktop studies - Available a la carte
(Biological, Cultural, Aesthetics, Geotechnical,
Telecommunications, Aviation, Land Use and
Permitting, etc.) - Phase II Reconnaissance-level Field Studies
- Critical Issues Analysis Report- Documents key
issues that warrant special consideration-
Provides permit matrix, recommendations, and
schedule
6Common Critical Issues Analysis Omissions
- Aviation Screening
- Telecommunications Screening
- Engineering/Constructability Issues
- Steep slopes
- Unstable geotechnical conditions
- Inadequate work space
7Moving on to the Conceptual Layout
- You now know you have a potential wind site!
- Client should have an idea of the turbine
technology that should be used in subsequent
studies - Move on to the conceptual layout
8What is the Conceptual Layout?
- Initial layout that includes turbine locations,
access roads, electrical collection system,
switchyard(s) and substation(s), transmission
lines, OM building, and construction work areas. - Necessary for obtaining land rights, performing
preliminary studies, beginning the regulatory
process, etc. - Typically the developer or the meteorological
firm will take a first cut at the conceptual
layout of turbines on a constraint map.
9Defining the Conceptual Layout
- Preliminary Selection of Turbine Technology
- Important for turbine spacing
- Important for defining setbacks
- Define Project Constraints
- Wind
- Land
- Setbacks from Homes/Infrastructure
- Engineering/Access
- Environmental
- Cultural
- Political
- Create Conceptual Layout
10Constraints Map
11Typical Setbacks and Constraints
- Setbacks from sensitive buildings such as
residences, schools, hospitals and churches - Setbacks from outbuildings such as barns,
garages, and hunting camps - Setbacks from roads, trails, and recreational
areas - Setbacks from transmission lines, oil and gas
wells, oil and gas transmission, gathering and
service lines, sub-surface mining operations and
other such infrastructure/facilities - Setbacks from non-participating parcel
boundaries - Wetlands, surface waters, and any regulatory
buffers around them - Sensitive cultural resources and any regulatory
boundaries around them - Locations of special status wildlife or
vegetation species and/or critical habitat - Areas of known geotechnical instability
- Fresnel zones and other communication/radar
related constraints - Areas impacted by air traffic (both civilian and
military) and - Any other environmental and land use constraints
identified for the site.
12Agricultural Siting Considerations
- Locate structures along field edges where
possible - Locate access roads along ridge tops where
possible to eliminate the need for cut and fill
and reduce the risk of creating drainage problems - Avoid dividing larger fields by locating access
roads along the edge of agricultural fields - All existing drainage and erosion control
structures such as diversions, ditches, and tile
lines shall be avoided or appropriate measures
taken to maintain the design and effectiveness of
the existing structures - Minimize loss production, crop damage and top
soil
13Engineering Tasks for Conceptual Layout
- Perform desktop study to evaluate subsurface
conditions and geologic hazards - Desktop Transportation Analysis
- Initial Road/collection system Layout
- Initial Constructability review
14Moving from the Conceptual Layout to the Final
Layout
- Wind projects have a lot of moving parts wind
resource, property, landowner preferences,
setbacks, environmental constraints, cultural
resources, engineering constraints,
transportation issues, constructability, etc.
influence where project facilities will be sited - There must be communication among team members
and impact on layout must be understood and
incorporated - The best team includes a meteorologist, a land
man, an environmental scientist, an engineer, a
constructability expert, and a lawyer - Data management with multiple team members can be
a challenge
15What is the Final Horizontal Layout?
- This layout depicts all project facilities for
permitting and land acquisition purposes - In many cases, permits must be obtained for
exactly what will be built, so a certain amount
of engineering must be done at an early stage - In a perfect world, micrositing occurs prior to
submitting major permit applications and
conducting NEPA (or state equivalent) review - Failure to do so often means the need to do
permit modifications, supplemental EISs, and/or
variances during construction - In the real world things arent that simple.
- If possible, permit for flexibility
16Studies that Support Final Horizontal Layout
- Field Studies
- Site specific environmental and cultural
fieldwork - Site specific engineering field work
- Constructability considerations
- Adjust Horizontal Layout and Review for
- Wind resource
- Constructability
- Engineering
- Environmental/cultural resources
- Land owner acceptability
- Final Horizontal Layout
17Engineering Tasks for Final Layout
- If topo exists, may need to commission a fly-over
to perform digital photography from which a
topographic base map can be prepared - Perform site walkdown of all project facilities
to assess access feasibility (slope and terrain
issues, etc.) - Perform geotechnical investigations needed for
design of roadway cross-sections, collection
system routing and wind turbine foundations
18The Timing of Studies
- This is the hardest part of advising a wind
client - Provide enough preliminary study for siting, but
not waste money by providing detailed study on
facilities that are not in their final location - If possible, only perform full wetland and
cultural delineations on the exact locations of
project facilities when they are in their final
location - Consider timing when running visual simulation,
shadow flicker analysis, writing up noise study,
etc. - Because siting is an iterative process, there
will always be some inefficiency in study
19Transportation Study
- Perform traffic and transportation study, for
oversized or heavy deliveries, to assess adequacy
of existing offsite roadways, bridges, crossings
over culverts, overpasses/underpasses, turning
radii, utilities, etc. - Within project boundary, determine whether
turning radii at existing intersections along the
delivery route need to be modified - Assess whether surface replacements or upgrades
will be required
20Wildlife Studies
- Typically include
- Avian use surveys
- Raptor nesting surveys
- Habitat inventory
- Threatened, endangered, sensitive species focused
surveys if appropriate - Bat habitat inventory and/or risk analysis
- State Natural Heritage database/USFWS TE species
inquiries - Plant and noxious weed surveys, if appropriate
- Studies will vary geographically and by state
21Wetland Studies
- It often makes sense to start with reconnaissance
level study, saving complete delineation until
the layout is final - All project facilities must be cleared for
wetlands - Public road improvements, especially public road
culvert replacements, are often forgotten - Good communication between wetland staff and
design engineers is critical - Data management is critical
- Keep a change log
22Cultural Resource Studies
- Consult with State Historic Preservation Office
(SHPO) - Define the Study Area for Archeology and for
Historic Architecture - Define the Area of Potential Effects (in
consultation with SHPO) as Project is more
precisely defined - Archeology
- Historical Architecture
23Transmission Interconnection Studies
- Feasibility Study estimates cost of
interconnection - System Reliability Impact Study determines
cost and equipment for maintaining reliability of
existing system - Complete Facility Upgrade Study determines final
cost of all interconnection and system upgrade
equipment - Negotiate Interconnection Agreement with
transmission utility
24Other Important Studies
- Noise
- Shadow Flicker
- Visual Assessment
- Property Values
- Conduct Phase 1 Environmental Site Assessment
(ASTM AIA Standards) - Etc.
25Permitting Phase -- Local
- Local
- At most proposed wind energy project sites, one
or more local approvals will be required. - The issuing authority may be a local planning
commission, zoning board, town, city or village
council, county board of supervisors or
commissioners, or a similar entity. - Although some state siting boards are authorized
to override local objections, most must first
demonstrate that the proposed project would be
consistent with local ordinances and that there
is no reasonable objection to the development of
the project.
26Permitting Phase -- Local
- Local
- Similar to the state regulatory process, the need
for local approvals and the process for obtaining
approvals vary throughout the country. - In some areas, the local approval process will be
time-consuming and the project will be subject to
close scrutiny. In contrast, some
municipalities require only a building permit. - The development team should assess which local
approvals will be required and consult with local
counsel.
27Permitting Phase -- State
- State
- Numerous state regulatory programs are likely to
be triggered by a proposed wind energy project.
While such programs often mirror, implement
(through delegated authority), or complement
similar federal laws, the state version is
typically more stringent than its federal
counterpart. - Little NEPA
- State Siting Statutes
- Endangered Species
- Wetland Permits
- Stream Crossing Permits
- Use Authorizations for State Owned Aquatic Land
- Historic Preservation
- Stormwater
- Agricultural Protection
- DOT (Roadway) Permitting
28Permitting Phase -- Federal
- National Environmental Policy Act
- Federal Wetland and Waterbody Laws
- National Pollutant Discharge Elimination System
(NPDES) permits for stormwater during
construction and operation - Endangered Species Act and other Wildlife
Protection Laws - National Historic Preservation Act
- Federal Aviation Administration Clearances
- Federal Land Use Authorizations
- Federal Transmission Line Interconnections
29Final Engineering Design Outline
- Establish Design Team including
- Professional Engineer / (Engineer of Record)
- Develop Design Criteria
- These should capture design requirements for
permits and plans - Client should review
- Preliminary (Draft) Design
- Drawings
- Technical Specifications
- Calculations
- Final Design
- PE Sealed
- Issued for Construction
30Design Disciplines
- Design Disciplines Capabilities - Civil
- Site Civil
- Site civil drawing is a base map which is
topographic survey obtained from client, or TtEC
commissions a survey to develop the base map - Usually perform a pre-design constructability
walkdown of WTG locations and intended access
road routes to consider site natural features and
landowner impacts - Roadway design layout / direction / cross
section / radii - Perform stormwater drainage calculations Size
and locate new culverts and identify soil erosion
controls (e.g., silt fencing, stone rip-rap,
etc.) - Geotextile Use
- Structural
- Foundation Design
- Bridge Improvements
31Design Disciplines
- Design Disciplines Capabilities
- Geotechnical
- May need to perform a geotechnical investigation,
as a pre-design task, to obtain site specific
information at WTG locations and some locations
along access roads - Detailed geotechnical investigation report serves
as a basis for access road and WTG foundation
design - Field Investigations
- Geotechnical Reports as design input
32Design Disciplines
- Design Disciplines Capabilities
- Electrical
- WTG collector system,
- Substation(s)
- Transmission Line
33Final Engineering Design - PE
- Design requires supervision by licensed civil,
structural and electrical PEs (if applicable) - PEs typically need to be licensed in State where
project is located
34Preconstruction
- Finalize Turbine and Long-Lead-Time Item
Procurement - Identify and requisition long lead time purchased
items, such as wind turbines and transformers - Approvals for the later plans and permits (Storm
Water Pollution Prevention Plan (SWPPP), Spill
Prevention, Containment and Countermeasure Plan
(SPCCP) and State DOT and US Army Corps wetlands
permits) - Final Construction Plans and Drawings
- Secure Construction Contractor
- Develop Environmental Construction Compliance
Plan - Develop Mobilization Plan
35Construction
- Mobilization Make sure you have obtained the
right pre-construction permissions - Construction Trailers
- Initial Laydown Areas
- Sediment and Erosion Control
- Safety and Environmental Training
- Send out construction start notifications as
required in permits
36Construction
- After the Notice to Proceed --
- Clearing and Grading
- Access Roads and Public Road Improvements
- Foundations
- Electrical Collection System
- Transmission Line
- Substation and Interconnection Facilities
- Tower and Turbine Erection
- OM Building/Visitor Kiosks
- Commissioning
- Mitigation Areas
- Reclamation
37Construction
- Engineering support during construction
- Provide home office support of construction
activities following construction release of
design drawings, to review contractor submittals
and administer Field Change Requests (FCRs)
and/or issue Design Change Notices (DCNs) - Provide field engineer, preferably from the
design team, to assist with construction
activities and ensure compliance with the design
38Tetra Tech, Inc.
- Tetra Tech, Inc. is a leading, U.S.-based
national and international firm delivering
solutions in, consulting, construction,
engineering, remediation and restoration - Publicly traded company (TTEK)
- Chosen by Smart Money magazine as one of the 10
Stocks for the Next 10 Years - Annual revenues in excess of 1.4 billion
financial strength to stand behind large wind
energy projects, including EPC BOP - Over 8,500 employees in 250 offices world-wide
- Consistently ranked in Engineering News Record as
one of the top ten
39Tetra Tech, Inc.
- Acquisition of The Delaney Group a
well-respected leader in renewable energy
construction - Experienced energy staff in all disciplines
- More than 6 million hours without a lost work day
over past two years - Injury rate is ¼ the national average
- 70 National Safety Council awards
- Employee health and safety perception rating in
top 2 nation-wide - ISO 14001 Certification for all services
- First major full-service firm to earn
certification with such broad coverage - ISO 9001 Certification for Wind Engineering
- Documented quality procedures and systems to meet
global standards and expectations
40Full-Service Energy Solutions
41Recognized Expertise
- Tetra Tech and Nixon Peabody chosen to write
American Wind Energy Association (AWEA) Wind
Facility Siting Manual - Frequent speaker on energy topics at AWEA, World
Wind Energy Association and other renewable
energy industry events - Papers on environmental compliance during
construction - Included in New York Energy Research and
Development Authority (NYSERDA) Wind Energy Tool
Kit - Published in North American Windpower Journal
- Through our Energy Management Services Supporting
Energy Programs at More Than 60 DoD Installations
World-Wide
42Contact
- Anntonette Alberti, JD
- 518-488-8588
- Anntonette.Alberti_at_tteci.com