Title: Remediation of PCB-containing Building Materials in Student Housing


1
Remediation of PCB-containing Building Materials
in Student Housing
2
PCBs in Building Materials Opportunities and
Strategies
  • Areas of Concern
  • Building Focus Windows, Expansion Joints,
    Masonry
  • Other Campus High Occupancy Areas
  • Strategy
  • Proactive Response to an Accidental Discovery
  • Boundary Repair vs. Renovation, Demolition
  • Community Education and Involvement Throughout
  • Multi-Media Panel Medical, EHS, Risk Assessment
  • Design the Plan, Revise in Response to Occupants
  • Where theres PCB, theres probablyasbestos

3
PCB Use Traditional Sources
  • Dielectric fluids transformers and capacitors
  • Other electrical equipment including voltage
    regulators, switches, reclosers, bushings, and
    electromagnets
  • Hydraulic oils elevators, etc.
  • Light ballasts
  • Cable insulation
  • Analytical standards for laboratories

4
PCBs in Building Components
  • Caulking
  • Elevators/ Hydraulic Oils
  • Sealants in heating systems
  • Thermal insulation material including fiberglass,
    felt, foam, and cork
  • Oil-Based Paint

5
Popular press picks up on the PCB issue in
primary/secondary schools
6
Harvard University Study Used Soil Samples to
Implicate Caulking as PCB Source
7
Building Photo, Schematic of Planned Remediation
Work
8
Site Conditions
  • Action levels
  • 10 ppm for high-occupancy, 1 ppm for soil
  • Contaminated Caulking
  • 200,000 ppm
  • Contaminated Building Materials
  • Brick _at_ 400 ppm
  • Concrete _at_ 5-2,300 ppm
  • Soils
  • 2 ppm

9
Pilot Test
  • Activities
  • Caulking Removal
  • First Row of Bricks Removed
  • Chemical Washing of Concrete Surfaces
  • Encapsulation of Select Concrete Surfaces
  • Prior EPA Approval required
  • Technically feasible, but disruptive to occupants

10
(No Transcript)
11
(No Transcript)
12
(No Transcript)
13
Revised Approach
  • Any Plan Revisions Require EPA Approval
  • Less material removal and with hand tools only
  • Caulking removal
  • Chemical washing of horizontal surfaces only
  • Encapsulate all adjacent building surfaces

14
(No Transcript)
15
(No Transcript)
16
(No Transcript)
17
Continued OM
  • Long-Term Monitoring and Maintenance
  • Semi-Annual Visual Inspections
  • Annual Sampling
  • Long-Term Maintenance
  • Material Characterization
  • Requirement upon Demolition
  • Deed Restriction

18
Lessons Learned
  • Technical Points
  • Length of EPA Review Process
  • Value of Expert Risk Assessor
  • Contractor Knowledge Still New Ground
  • Communications Points
  • Building Occupants Savvy and Initiative
  • Value of In-House Occupational Health Physician
  • Value of Town-Hall Meetings w/ Residents
  • Websites are sprouting around this issue

19