Title: JAWAHAR LI SCHEME (NETTAMPADU)
1(No Transcript)
2JAWAHAR LI SCHEME (NETTAMPADU)
1 Project Profile Project Profile To Lift 20 Tmc of water from PJP Reservoir to Godemdoddi and Relampadu Balancing reservoirs to irrigate 2,00,000 acres in Gadwal and Alampur constituencies.
2 Administrative Sanction Administrative Sanction G. O. Ms. No. 25, Dt 19-2-2003 for Rs. 50 Crores G. O. Ms. No. 108, Dt 22-6-2005 for Rs.1428 Crores
3 No. of EPC Packages 14 Nos. No. of EPC Packages 14 Nos. No. of EPC Packages 14 Nos. No. of EPC Packages 14 Nos.
4 Agt. Value of 14 Pkgs Agt. Value of 14 Pkgs Rs. 1294..31 Crs.
5 Budget Provision for 2006-07 Rs. 234.20 Crs.
6 Expenditure
2004-05 2004-05 - -
2005-06 2005-06 Rs. 123.36 Crs.
TOTAL Rs. 123.36 Crs.
7 Utilisation 22 TMC
8 Ayacut 2.00 Lakh Acres
3JAWAHAR LI SCHEME (NETTAMPADU)
9 Land Acquisition Land Acquisition
Required 20,378 Acres
Acquired Nil
Requisitioned 7,291 Acres
10 Lift-I
Lift Height 40 M
No. of Pumps 4 Nos.
Total pumps capacity 68 MW
11 Lift-II
Lift Height 60 M
No. of Pumps 3 Nos.
Total pumps capacity 51 MW
12 Total Power Required Total Power Required 139 MW
4JAWAHAR LI SCHEME (NETTAMPADU)
13 Est. Cost for LA Rs. 90 Crs.
14 Est. Cost for R R Nil
15 Mobilisation Advance Paid Recovered
2004-05 - -
2005-06 Rs. 103.52 Crs. -
Total Rs.103.52Crs. -
16 Target date for completion 10/2007
5JAWAHAR (Nettampadu) LI PROJECT
Pkg No. Description Awarded Bid Amount Rs. in Crs.
98 Formation of Approach channel and Guddemdoddi B.R M/s Manisha Mulay (JV) 60.00
99 EWE FE of LMC of 8Km and RMC of 36Km from GDBR M/s AKR Coastal (JV) 48.07
100 EWE FE of RMC of 36Km to 76Kms M/s Srinivasa civil works pvt Ltd., 57.00
101 Formation of Balancing Reservoirs under Right Main Canal of Gudemdoddi Balancing Reservoir of Nettampadu to a total capacity of 2.00TMC of water. M/s Lakmu Reddy Kranthi Constructions 62.910
102 Excavation and formation of embankment Gravity main canal from GDBR to a length of 8.20Km including CM CD Works M/s SV Engineering Constructions B. Kumaraswamy Reddy (JV) 51.480
103 Formation of Ralampadu BR of 3Km Length M/s SV Engineering Constructions B. Kumaraswamy Reddy (JV) 55.99
104 EWE FE of LMC under RBR of length 43KM M/s A. Prabhakar Reddy Co., 40.74
105 EWE FE of RMC under RBR (1st Reach) of length 11.25Km M/s Srinivasa civil works Pvt. Ltd., 36.270
6JAWAHAR (Nettampadu) LI PROJECT
Pkg No. Description Awarded Bid Amount Rs. in Crs.
106 EWE FE of RMC under RBR (2nd Reach) from length 11.25Km to Km.26.00 M/s Prathibha constructions and contract Pvt. 67.34
107 EWE FE of RMC under RBR (3rd Reach) from length Km.26.00 to Km.51.00 M/s Prathibha constructions and contractors (India) 54.85
108 Formation of 5 Nos. Balancing Reservoirs under RMC reach I II under RBR M/s P. Laxma Reddy Kranthi constructions 55.29
109 Formation of 5 Nos. Balancing Reservoirs under RMC reach III under Relampadu Balancing Reservoir M/s Reddy Veeranna Constructions 51.00
OC Lift-I M/s Patel Engineering Ltd, Hyd 338.530
OC Lift-II M/s Patel Engineering Ltd, Hyd 314.083
TOTAL 1294.31
7JAWAHAR (Nettampadu) LI PROJECT
Package No. 98 Formation of Approach channel
and Guddemdoddi B.R
Name of the Contractor M/s Manisha Mulay
(JV) Agreement Amount Rs. 60.00
Crores. Agreement Date 02-09-2005 Period of
Completion 24 Months
- Investigation (2.80 Km approach channel)
Completed - Designs (reservoirs) Under approval
- (Structures) Approved
- Earthwork done 6.50 Lakh cum
- Expenditure Rs. 6.00 Crs. (Mob. Adv. Only)
- Land Acquisition Required 1681 acres
8JAWAHAR (Nettampadu) LI PROJECT
Package No. 99 EWE FE of LMC of 8Km and RMC
of 36Km from GDBR
Name of the Contractor M/s.AKR-COASTAL(JV) Agree
ment Amount Rs. 48.07 Crores. Agreement
Date 25-10-2005 Period of Completion 24 Months
- Investigation (44 Kms canals) Completed
- Distributaries Under
preparation - Structures Under
preparation - Designs Under preparation
- Expenditure (2005-06) Rs. 2.40 Crs. (Mob. Adv.
Only) - Land Acquisition Required 109.58 acres
9JAWAHAR (Nettampadu) LI PROJECT
Package No. 100 EWE FE of RMC of 36Km to 76Kms
Name of the Contractor M/s.Srinivasa Civil
Works Pvt. Ltd. Agreement Amount Rs.
57.00Crores. Agreement Date 24-10-2005 Period
of Completion 24 Months
- Investigation (40 Km Canal) Completed
- Structures Under Progress
- Distributaries under Progress
- Designs 10 Km length submitted to CE, CDO
against 40 Km - Expenditure (2005-06) Rs. 2.85 Crs. (Mob. Adv.
Only) - Land Acquisition Required 82.50 acres
10JAWAHAR (Nettampadu) LI PROJECT
Package No. 101 Formation of Balancing
Reservoirs under Right Main Canal of Gudemdoddi
Balancing Reservoir of Nettampadu to a total
capacity of 2.00TMC of water.
Name of the Contractor M/s P. Laxmu Reddy
Kranthi Constructions Agreement Amount Rs.
62.91Crores. Agreement Date 24-08-2005 Period
of Completion 24 Months
- Investigation (2 Nos. Reservoirs) Completed
- Designs (Bund Portion) Approved
- weir OT Proposals submitted
to CE, CDO - Earth work done 60,000 cum of COT done
- Expenditure (2005-06) Rs. 5.72 Crs. (Mob. Adv.
Only) - Land Acquisition Required 2820 acres
11JAWAHAR (Nettampadu) LI PROJECT
Package No. 102 Excavation and formation of
embankment Gravity main canal from GDBR to a
length of 8.20Km including CM CD Works.
Name of the Contractor M/s. S.V Engineering
constructions B. Kuamara Swamy Reddy
(JV) Agreement Amount Rs. 51.48Crs. Agreement
Date 26-09-2005 Period of Completion 24 Months
- Investigation (8.75 Km canal) Completed
- Designs (Canal) Under progredd
- Structures Under progress
- Earth work done 4,00,000 cum
- Expenditure (2005-06) Rs. 2.57 Crs. (Mob. Adv.
Only) - Land Acquisition Required 800 acres
12JAWAHAR (Nettampadu) LI PROJECT
Package No. 103 Formation of Ralampadu BR of
3Km Length
Name of the Contractor M/s. S.V Engineering
constructions B. Kuamara Swamy Reddy
(JV) Agreement Amount Rs. 55.99Crs. Period of
Completion 24 Months
- PRESENT STATUS
- Investigation work in progress
- Agreement concluded
- Land Acquisition Required 2650Acres
- Mob. Adv. Paid Rs. 2.80Crores.
13JAWAHAR (Nettampadu) LI PROJECT
Package No. 104 EWE FE of LMC under RBR of
length 43KM
Name of the Contractor A.Prabhakar Reddy Co.
Agreement Amount Rs. 40.74Crs. Agreement
Date 24-10-2005 Period of Completion 24
Months
- Investigation (Canal) 10 Km completed against
43.10 Km - Distributaries Under Progress
- Structures Under Progress
- Earth work done 85,000 cum against 6,00,000 cum
- Expenditure (2005-06) Rs. 2.04 Crs. (Mob. Adv.
Only) - Land Acquisition Required 700 acres
14JAWAHAR (Nettampadu) LI PROJECT
Package No. 105 EWE FE of RMC under RBR (1st
Reach) of length 11.25Km
Name of the Contractor M/s. Srinivas Civil
works Pvt. Ltd. Agreement Amount
Rs.36.27Crs. Agreement Date 24-10-2005 Period
of Completion 24 Months
- Investigation (11.25 Km Canal) Completed
- Distributaries Under progress
- Structures under Progress
- Designs (9.5 Km canal) Submitted to CE, CDO
- Expenditure (2005-06) Rs. 1.80 Crs. (Mob. Adv.
Only) - Land Acquisition Required 643 acres
15JAWAHAR (Nettampadu) LI PROJECT
Package No. 106 EWE FE of RMC under RBR (2nd
Reach) from length 11.25Km to Km.26.00
Name of the Contractor Prathibha Consts.
Contractors (India) Pvt.Ltd. Agreement Amount
Rs.67.34 Crs. Agreement Date 24-10-2005
Period of Completion 24 Months
- Investigation (14.75 Km Canal) Completed
- Designs Under preparation
- Expenditure (2005-06) Rs. 3.37 Crs. (Mob. Adv.
Only) - Land Acquisition Required 930 acres
16JAWAHAR (Nettampadu) LI PROJECT
Package No. 107 EWE FE of RMC under RBR (3rd
Reach) from length Km.26.00 to Km.51.00
Name of the Contractor Prathibha Consts.
Contractors (India) Pvt.Ltd. Agreement Amount
Rs.54.85Crs. Agreement Date 24-10-2005
Period of Completion 24 Months
- Investigation (21.00 Km Canal) Completed
- Designs Under preparation
- Expenditure (2005-06) Rs. 2.75 Crs. (Mob. Adv.
Only) - Land Acquisition Required 758 acres
17JAWAHAR (Nettampadu) LI PROJECT
Package No. 108 Formation of 5 Nos. Balancing
Reservoirs under RMC reach I II under RBR
Name of the Contractor M/s. P. Laxmu Reddy
Kranthi Constructions Agreement Amount Rs.
55.29Crs. Agreement Date 24-08-2005 Period of
Completion 24 Months
- Investigation (5 Nos. Bal. Reservoirs)
Completed - Designs (Bal. Reservoirs) 2 Nos. approved
- Earth work done 1,38,000 cum
- Expenditure(2005-06) Rs. 5.53 Crs. (Mob. Adv.
Only) - Land Acquisition Required 2845 acres
18JAWAHAR (Nettampadu) LI PROJECT
Package No. 109 Formation of 5 Nos. Balancing
Reservoirs under RMC reach III under Relampadu
Balancing Reservoir
Name of the Contractor M/s. Reddy Veeranna
Constructions Agreement Amount Rs.51.00
Crs. Agreement Date 27-10-2005 Period of
Completion 24 Months
- Investigation (5 Nos. Bal. Reservoirs)
Completed - Designs (Bal. Reservoirs) 3 Nos. under
preparation - Expenditure (2005-06) Rs. 2.55 Crs. (Mob.
Adv. Only) - Land Acquisition Required 4631 acres
19JAWAHAR (Nettampadu) LI PROJECT
Package No. Lift-I
Name of the Contractor M/s. Patel Engineering
Ltd. Agreement Amount Rs.338.53Crs. Agreement
Date 08-8-2005 Period of Completion 42 Months
- PRESENT STATUS
- Agreement concluded
- Mobilization Advance paid Rs. 32.55 Crores.
- Exp. On works Rs. 12.21 Crores.
- TOTAL Rs. 44.76 Crores.
- Investigation Completed
- Designs Under preparation
- Earth work done (Surge pool) 3.40 Lakh cum
20JAWAHAR (Nettampadu) LI PROJECT
Package No. Lift-II
Name of the Contractor M/s. Patel Engineering
Ltd. Agreement Amount Rs. 319.08Crs. Agreement
Date 08-8-2005 Period of Completion 42 Months
- PRESENT STATUS
- Agreement concluded
- Mobilization Advance paid Rs. 30.60 Crores.
- Exp. On works Rs. 7.63 Crs.
- TOTAL Rs. 38.23 Crs.
- Investigation Completed
- Designs Under progress
- Earth work done (Surge pool) 75,000 cum