ELC 347 - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

ELC 347

Description:

elc 347 day 8 – PowerPoint PPT presentation

Number of Views:70
Avg rating:3.0/5.0
Slides: 22
Provided by: TonyG82
Category:

less

Transcript and Presenter's Notes

Title: ELC 347


1
ELC 347
  • DAY 8

2
Agenda
  • Questions
  • Assignment 3 Corrected
  • 4 As , One non-submit
  • Assignment 4 Due
  • Capstone Proposal Due
  • Group Progress report due
  • Exam 2
  • Slight Change
  • 10 M/C (5 points each) 5 essays (10 points each)
  • 1 hour 15 minutes
  • Open book, Open Notes
  • Ghattas 4-8, Project 8-10
  • Group Project Meeting (30 Min)
  • Discussion on Network Analysis and Duration
    Estimating

3
Network Analysis and Duration Estimating
  • Laying the Groundwork for Commitment
  • Setting Duration Estimates
  • Determining the critical Path
  • Meeting external deadlines

4
Groundwork for commitment
  • Ask the people that actually doing the work
  • If more than one is capable ask the one with the
    most experience
  • Be realistic
  • Be an advocate for your team

5
Duration Estimating
  • Duration the elapsed time from the start of an
    activity until it is finished
  • Effort -- the actual time spent on the project
  • Example
  • Tony work on a project task for 20 hours at 4
    hours per day starting Monday mourning. The
    project task was completed Late Friday
  • Effort 20 hours
  • Duration 5 days

6
Techniques for Estimating Duration
  • Experience
  • Historical data
  • Research
  • Modeling
  • Experiments
  • Breakdown/roll-up
  • Delphi Method
  • Panel of experts
  • Consultants
  • Three outside Estimates
  • Ranging
  • Other techniques

7
Special Cases (Out of your hands)
  • Inspections
  • Deliveries
  • Breakdowns and repairs
  • Approvals

8
Normalizing Duration
  • Goal is most cost-efficient plan
  • Determine the most cost-efficient technical
    approach
  • Make and estimate of long the most cost efficient
    method will take to complete
  • Selectively adjust you estimate for any activity
    that is subject to common problems.

9
CPM versus PERT
  • PERT was developed by US Navy in the 1950s
  • CPM was developed by Remington Rand and DuPont
    around the same time.
  • Only difference is in durations estimating
  • Pert uses 3 cases Most optimistic, most
    pessimistic and most likely and determines
    probability for each
  • DoPo DpOp DePe final duration
  • CPM use only the most likely duration

10
Calculating a Project Duration
  • Determine each activity and its predecessors
  • Determine an estimated duration for each activity
  • Find the Critical Path
  • Add up the durations along the critical path

11
Whats the Critical Path
  • The longest path based on precedence of
    activities and durations through a PERT/CPM
    network
  • Its critical because
  • Its combined length determines the length of the
    project
  • It has NO slack
  • Delay of any activities on the critical path
    delays the entire project

12
Finding the critical path
  • Use forward pass Calculations
  • Each activity should have
  • EPS ?earliest possible Start time
  • EPF ? earliest possible finish time
  • DUR ? duration
  • EPF EPS DUR

EPS DUR EPF
Activity Activity Activity

13
Example
3 4 7
A A A

7 5 12
B B B

14
Special Case
  • If an activity has more than one processor its
    EPS is set to the latest EPF of all its processors

3 4 7
A A A

7 5 12
C C C

0 5 5
B B B

15
An example of forward pass
16 7 23
H H H

12 4 4 16 16
G G G G G

5 4 9
B B B

0 5 5
A A A

25 4 29
Finish Finish Finish

4 8 12
C C C

16 5 21
I I I

0 0 0
Start Start Start

8 4 12
F F F

21 4 25
J J J

0 4 4
D D D

4 4 8
E E E

16
Backwards Pass
  • Use to calculate Slack
  • LAS -gt Latest start time
  • LAF -gt Latest finish time
  • TS -gt total slack

EPS DUR EPF
Activity Activity Activity
LAS TS LAF
17
An example of backward pass
16 7 23
H H H
18 2 25
12 4 4 16 16
G G G G G
12 12 0 0 16
5 4 9
B B B
8 3 12
0 5 5
A A A
3 3 8
25 4 29
Finish Finish Finish
25 0 29
4 8 12
C C C
4 0 12
16 5 21
I I I
16 0 21
0 0 0
Start Start Start
0 0 0
8 4 12
F F F
12 4 16
21 4 25
J J J
21 0 25
0 4 4
D D D
0 0 4
4 4 8
E E E
8 4 12
18
Examine Critical Path for Reality Check
  • Is the total duration typical?
  • Are the durations of the CP activities typical?
  • Reexamine all CP activity durations
  • Reexamine assumptions

19
Optimizing the plan
  • Would bringing more expert talent to bear on the
    project speed it up?
  • Are there changes we could make in the resource
    procurement process to shorten wait times?
  • Would round the clock scheduling shorten
    duration?
  • Would more money motivate the team to work
    faster?
  • Would an organizational change speed things up?
  • Do we think it will take this long just because
    it always has, or are there other ways to so
    this, which we havent thought of yet, that would
    shrink the timetable?

20
3 Lines of defense
  • Relieve the critical path
  • Sharpen your pencil
  • Crash activities

21
Summary
  • Construct a CPM
  • Estimate normal durations
  • Do a forward pass
  • Identify Critical Path
  • Optional
  • Do a backward pass to identify slack times
  • Conduct a reality check
  • Optimize the plan
  • 1st line of defense - relieve the critical path
  • 2nd line of defense - sharpen your pencil
  • 3rd line of defense - crash activities
Write a Comment
User Comments (0)
About PowerShow.com