Title: Check out the bingo sign!
1Check out the bingo sign!
CAZENOVIA CR. _at_ STEPHENSON ST. BRIDGE
2REPLACEMENT OF ONE BANK OF A CONCRETE-LINED
CHANNEL CAZENOVIA CREEK _at_ STEPHENSON STREET
BRIDGE SPONSOR CITY OF BUFFALO,
NYCONSTRUCTED OCTOBER 2005 - MARCH 2006
3CAZENOVIA CREEK _at_ STEPHENSON STREET BRIDGE
- Urban Urban Urban!! Steep bank slopes-fenced off
for public safely, concrete lined channel - Roads on top of both banks within feet of sloped
bank of stream - Dense urban single-family dwellings
- Floods fairly often due to flow, ice jams,
backwater effects from the Buffalo River - City of Buffalo, NY project
- Pool-riffle-pool stream, less than 1 slope
4PRE-PROJECT PHOTOSby Lallman RambaliNYSDOT
REGION 9WINTER 2003
5Ice on US side of Stephenson Street bridge.
- Pix by Lallman Rambali 2003
6From Stephenson St. bridge, looking US
- Pix by Lallman Rambali 2003
7PRE-PROJECT PHOTOSby Dave Derrick FEBRUARY
24, 2005
8Looking across stream, left bank in background.
9CONSTRUCTION PHOTOSby Jeff Fisk, Project
Engineer, OCTOBER 2005
10Looking across _at_ left bank, US end of project.
- Pix by Jeff Fisk - Oct. 2005
11Positioning driving sheetpile. Note worker
- Pix by Jeff Fisk - Oct. 2005
12CONSTRUCTION PHOTOSby Dave Derrick NOVEMBER
4, 2005
13Looking DS. Old sheetpile removed, new
installed.
14Looking DS. Driving sheetpile toe. Project is
1,000 ft long.
15CONSTRUCTION COMPLETEPhotos by Derrick MAY
18, 2006
16Looking DS. Toe-sheetpile. Mid-bank-cut stone
with willows.
- Pix by Derrick - 5/18/2006
17Looking DS. Trees-fence-shrubs-riprap-stone-sheet
pile.
- Pix by Derrick - 5/18/2006
18Looking DS. Opposite bank typical concrete.
- Pix by Derrick - 5/18/2006
19Looking DS. Close-up of soil-choked riprap
mid-bank upper bank shrubs. Note engineered
soil-clay-gravel-organic mix for stability
plant growth of shrubs.
- Pix by Derrick - 5/18/2006
20Robust upper bank rooted stock shrubs .
- Pix by Derrick - 5/18/2006
21Gravel-clay-soil-organic mix planting medium.
- Pix by Derrick - 5/18/2006
22Looking DS. Shrubs and top-bank trees.
- Pix by Derrick - 5/18/2006
235 MONTHS AFTER PROJECT COMPLETIONPhotos by
Derrick AUGUST 23, 2006
24Mid Upper bank vegetation growing well
Trees
No protection, 2 rows of shrubs
Riprap with grasses
Square cut stone with willow dogwood whips
Sheetpile
- Pix by Derrick - 8/23/2006
2522 MONTHS AFTER PROJECT COMPLETIONFEB 3-4,
2008
26Looking DS _at_ left bank. Water level has dropped,
ice has collapsed
- Pix by George Cotroneo - 2/3/2008
27WHAT A BIG DIFFERENCE ONE DAY MAKES Feb 5,
2008 (3/4 inch of rain warm temps10 ft high
stage ice out) ALSO WHICH BANK DO YOU
LIKE, LEFT OR RIGHT??
28LEFT BANK Warm temps rain high water quick
ICE OUT. All veg still looking very very good.
- Pix by Joe Kassler - 2/5/2008
293 YEARS 1 MONTH AFTER PROJECT
COMPLETIONPhotos by Derrick JUNE 12, 2009
30Looking DS _at_ left bank. Veg looking good!!
3YRS 1 MONTH AFTER-CAZENOVIA CR. _at_ STEVENSON
ST-DERRICK 6-12-09
31Looking DS _at_ left bank. All veg is robust!!
3YRS 1 MONTH AFTER-CAZENOVIA CR. _at_ STEVENSON
ST-DERRICK 6-12-09
32Looking DS _at_ left bank. Nice species diversity
of plants.
3YRS 1 MONTH AFTER-CAZENOVIA CR. _at_ STEVENSON
ST-DERRICK 6-12-09
33Looking DS _at_ left bank. Even toe veg is coming
on.
3YRS 1 MONTH AFTER-CAZENOVIA CR. _at_ STEVENSON
ST-DERRICK 6-12-09
34Vines some veg growing amongst large toe stone
3YRS 1 MONTH AFTER-CAZENOVIA CR. _at_ STEVENSON
ST-DERRICK 6-12-09
35Close up of robust mid upper bank veg.
3YRS 1 MONTH AFTER-CAZENOVIA CR. _at_ STEVENSON
ST-DERRICK 6-12-09
36Top bank tall trees to left upper bank veg on
right.
3YRS 1 MONTH AFTER-CAZENOVIA CR. _at_ STEVENSON
ST-DERRICK 6-12-09
374.66 YEARSAFTER PROJECT COMPLETIONPhotos by
Derrick JUNE 16, 2010
384.66 years after completion. From bridge looking
DS _at_ the entire project. All planted material
showing robust growth
4.66 YRS LATER-CAZENOVIA CR. _at_ STEVENSON
ST-DERRICK 6-16-2010
394.66 years after completion. From the bridge
looking DS. Except for narrow band of stone at
toe, dense veg has covered the entire bank.
4.66 YRS LATER-CAZENOVIA CR. _at_ STEVENSON
ST-DERRICK 6-16-2010
404.66 years after completion. From the bridge
looking DS. Good diversity of plant species with
some volunteer plants (Cottonwood, Black Locust,
herbacious, some invasive Japanese Knotweed).
4.66 YRS LATER-CAZENOVIA CR. _at_ STEVENSON
ST-DERRICK 6-16-2010
414.66 years after completion. From bank looking
DS.
4.66 YRS LATER-CAZENOVIA CR. _at_ STEVENSON
ST-DERRICK 6-16-2010
424.66 years after completion. From the bank
looking DS. Willow is growing well in the riprap
section.
4.66 YRS LATER-CAZENOVIA CR. _at_ STEVENSON
ST-DERRICK 6-16-2010
434.66 years after completion. Looking at top bank
overbank
4.66 YRS LATER-CAZENOVIA CR. _at_ STEVENSON
ST-DERRICK 6-16-2010
444.66 years after completion. Looking at top bank.
4.66 YRS LATER-CAZENOVIA CR. _at_ STEVENSON
ST-DERRICK 6-16-2010
455 YEARSAFTER PROJECT COMPLETIONPhotos by
Chuck Godfrey Feb. 18, 2011
465 YEARS AFTER PROJECT COMPLETION. Its
back-looking DS _at_ ice pounding project, all
plants safe for now!!
5 YRS LATER-CAZ CR. _at_ STEVENSON ST-CHUCK
GODFREY 2-28-2011
47Brothers separated at birth!!