... in the survey * Site-Specific Protocols Survey Administration Section A-1 will be administered at all survey locations With the exception of campgrounds, ... – PowerPoint PPT presentation

Number of Views:84
Avg rating:3.0/5.0
Slides: 18
Provided by: mtz6
Category:

less

Transcript and Presenter's Notes

Title: Placer County Water Agency


1
  • Placer County Water Agency
  • Middle Fork American River Project
  • (FERC No. 2079)
  • Recreation Technical Working Group Meeting
  • March 6, 2008

2
  • General VisitorSurvey Protocols

2
3
Proposed Sampling Effort
  • Table 5

3
4
General Protocols
  • Statistical sites will be sampled on weekdays,
    weekend days and holidays
  • Qualitative sites will be sampled on weekends and
    holidays
  • Sampling effort for statistical sites is
    stratified by month based on use distribution
    June, July, August
  • For each month, the number of holiday,
    weekend-day, and weekday sample-day are assigned
  • Fridays will not be scheduled for sampling to
    provide an open day for QA/QC and data management
    activities and to allow for adjustments to the
    sampling schedule, if needed
  • Each sample-day represents two sample-blocks
  • Each sample-block represents a four hour sample
    effort

4
5
General Protocols
  • Sampling-blocks dates for each month are first
    randomly selected for each day-type
  • Second, sampling blocks were systematically
    adjusted to account for staff loading
  • Staff load balancing only occurs within
    day-type categories
  • Example A weekday sampling block can be
    re-assigned to another weekday but not a
    weekend-day
  • Sampling block times are systematically selected
    based on survey location and facility type
  • Surveyors will remain on site 4 hours (AM, PM, or
    evening) for each designated survey block
  • Surveyors will survey all persons encountered
    during the sampling block, provided they are
    willing to participate

5
6
Site-Specific Protocols
  • Campgrounds
  • Surveys will be conducted during AM blocks (8-12)
    or evening blocks(4-8) only
  • Survey team will coordinate sampling dates for
    reserved group sites with Forest Service to
    ensure occupancy at site
  • All Other Individual Sites
  • Surveys will be conducted during AM blocks (8-12)
    or PM blocks(1-5)
  • Grouped Sites
  • Surveys will be conducted during AM blocks (8-12)
    or PM blocks(1-5)
  • Surveyors will rove through groups of sites over
    a 4-hour period
  • Starting points within each group of sites will
    be randomly selected
  • All persons encountered at any one site will be
    approached and asked to participate in the survey

6
7
Site-Specific Protocols
  • Survey Administration
  • Section A-1 will be administered at all survey
    locations
  • With the exception of campgrounds, each user will
    be asked to complete two additional relevant
    sections based upon the primary activities they
    identify
  • Users intercepted at campgrounds will be asked to
    complete all relevant sections
  • Survey administration may be adjusted pending the
    pre-test results and/or feedback from early
    sampling efforts

7
8
Site-Specific Protocols
  • Locations in ASRA
  • Surveys will be conducted during AM blocks (8-12)
    or evening blocks (1-5), and will target
    stream-based recreation users
  • Sections A-1 and A-5 will be administered at all
    locations
  • Section A-7 will also be administered, if
    applicable
  • Ruck-a-Chucky
  • Sections A-1 and A-5 will be administered to all
    users
  • One of the following sections will be
    administered - Section A-2, A-3, or A-7

8
9
Survey Log
  • Survey logs will be completed for each sampling
    location
  • Surveyors will record the following information
    on the survey log
  • Site Identification
  • Weather Conditions
  • Site Conditions
  • Surveyor Name
  • Date
  • Time Arrived at Site
  • Time Departed Site
  • Estimated Number of People at Site
  • Contact Number
  • Contact Time
  • Surveyed Previously (Y/N)
  • Willingness to Participate (Y/N)
  • Survey No.
  • Male/Female (M/F)
  • Part of Family? (Y/N)
  • Part of Larger Group (Y/N)
  • How may in family/group (/)

9
10
Proposed Sampling Schedule
  • Sampling schedule tables

10
11
Proposed Pretest Process and Schedule
  • Conduct surveys at Ruck-a-Chucky on Sunday, March
    9th
  • If no one is present at Ruck-a-Chucky, move to
    Confluence
  • Conduct interviews over a 4-hour period, from 1PM
    - 5 PM
  • Intercept all users present at site
  • Record survey participation notes on survey log
  • Report results and discuss proposed survey form/
    protocol revisions to group at March 26th TWG

11
12
Focus Groups
12
13
Focus Groups
  • Draft Invitation Letter(s)
  • Proposed Discussion Topics
  • Whitewater Boating Focus Group
  • Angler Focus Group
  • Trail Users/Stream Crossing Focus Group
  • Timing
  • February - March 2008 Identify Focus Group
    participants for each Focus Group
  • February - March 2008 Develop Focus Group
    topics
  • April - May 2008 Conduct Focus Group sessions

13
14
Whitewater Boating Flow Studies
14
15
Flow Study Implementation
  • Timing
  • March - April 2008 Develop flow study survey
    instruments
  • March - April 2008 Evaluate water-year data to
    refine windows for flow study Implementation
  • April - May 2008 Select flow study team members
  • June 2008 Orientation of study team members
  • July - October 2008 Implement studies in
    coordination with instream flow studies conducted
    as part of AQ 1 TSP

15
16
Flow Study Implementation
  • Study Reaches and Potential Target Flows

Oxbow PH to Ruck-a-Chucky 975 - 1,025 cfs 775 - 825 cfs 575 - 625 cfs
Ruck-a-Chucky to Mammoth Bar Mammoth Bar to Confluence Confluence to Oregon Bar 975 - 1,025 cfs 775 - 825 cfs 575 - 625 cfs 350 - 400 cfs
16
17
Flow Study Implementation
  • Whitewater survey form