UPGRADE - PowerPoint PPT Presentation

1 / 4
About This Presentation
Title:

UPGRADE

Description:

Title: No Slide Title Author: DZERO Last modified by: Philip Michael Tuts Created Date: 6/17/1995 11:31:02 PM Document presentation format: On-screen Show – PowerPoint PPT presentation

Number of Views:47
Avg rating:3.0/5.0
Slides: 5
Provided by: DZE2
Category:
Tags: upgrade | holmes

less

Transcript and Presenter's Notes

Title: UPGRADE


1
UPGRADE
New Systems
  • Fiber Tracker
  • 2T Super conducting Solenoid
  • Central Preshower
  • Intercryostat Detector
  • Luminosity Monitor
  • Forward Preshower
  • Silicon Tracker
  • Calorimeter Electronics
  • 3 Level Trigger DAQ
  • Online System
  • Offline Computing
  • Shielding
  • Central Muon Scintillators
  • Forward Muon Tracking
  • Forward Muon Trigger Pixels

2
Upgrade Status
  • Silicon
  • 800k ch barrels disks, SVXII readout
  • Detector production well along
  • Detector assembly starting
  • Fiber
  • 80k fibers w/ VLPC readout on 8 cylinders
  • Produced first cylinder with ribbons
  • Solenoid
  • 2T superconducting
  • Installed and tested
  • Preshowers
  • Scintillator extrusions, WLS, VLPC
  • Central complete installed
  • Forward in production

Double sided Si disk wedge
Si Barrel bulkhead w/ ladders flex cable
Si barrel ladder
Fiber cylinder w/ ribbons
8ch VLPC readout chip
Forward Preshower Module
Solenoid with central preshower being intalled
3
Upgrade Status
  • Calorimeter Electronics ICD
  • 60k ch preamp shaper, scint tiles for ICD
  • Production started
  • Muon System
  • Central scint tiles installed
  • Forward scint pixels fabricated, modules being
    assembled
  • Forward mini-drift tube fabrication well along,
    module assembly begun
  • Trigger DAQ
  • 3 level trigger
  • Production in many systems
  • Online
  • First systems purchased, central muon readout
  • Software being written

Central Muon Scintllator tiles Installed in D0
Forward Muon tracking system mini drift
tube octant
Forward Muon Trigger detector Scintillator
pixel w/ PMT readout
4
Schedule Milestones
  • Solenoid CPS installed 9/98
  • Muon central installed 6/99
  • Fiber Tracker assembly complete 3/00
  • VLPC cassette assembly complete 8/00
  • Calorimeter electronics fabricated 8/00
  • Muon Forward tigger pixels installed 8/00
  • Muon Forward tracking MDT planes installed 8/00
  • Silicon Tracker assembly complete 9/00
  • Remove shield wall for roll in 11/00
  • Rolled in and hooked up 2/01