Transcript and Presenter's Notes

Title: Blasting Regulations


1
Blasting Regulations
  • Regulatory Requirements
  • for Blasting Operations

2
Legal Standards
  • 29 CFR Part 1910 - General Industry
  • 29 CFR Part 1926 - Construction
  • BATF
  • DOT

3
General Provisions
  • General requirements not specifically related to
    a particular operation or procedure
  • Usually broad in scope
  • Dos and Donts, Always and Nevers

4
Blaster Qualifications
  • Knowledge and Experience
  • Training
  • Physical Ability
  • Evidence of Competency

Certified Blaster
5
Storage of Explosives
  • Storage in Magazines
  • Separate Magazines for Explosives and Detonators
  • Separation Distances
  • barricaded
  • unbarricaded

6
Transporting Explosives
  • Requires CDL with
  • Hazmat Endorsement
  • Proper Placarding
  • No smoking, etc.
  • Same vehicle for explosives and detonators may be
    permitted
  • Route Plan

7
Loading Explosives
  • No operating equipment within 50 feet of loaded
    holes
  • Load only those holes intended to be fired in the
    next round
  • Warning signs posted
  • Check all holes for
  • depth prior to loading

8
Initiation of Explosives
  • Connections from boreholes back to source of
    firing current
  • Survey for extraneous electricity
  • Solid Connecting Lead wires
  • EB detonators all the
  • same kind
  • Proper resistance
  • Leg wires shunted

9
Initiation of Explosives - cont
  • Only the Blaster shall
  • be in charge of the blasting machine
  • connect lead wires to machine
  • test circuits with Blasting
  • Galvanometers
  • fire the shot
  • immediately disconnect lead
  • wires after firing the shot

10
Firing the Blast
  • Code of signals, familiar to everyone, must be
    posted
  • Loud warning signal prior
  • to firing the shot
  • Flagmen posted at every
  • roadway passing through
  • the blasting zone
  • Blaster must assure safety

11
Post Blast Inspection
  • Disconnect firing line immediately after blast
  • Allow sufficient time
  • for dispersion of fumes
  • Blaster must verify all
  • charges have fired before
  • others are allowed into blast area

12
Misfires
  • Exclude all employees from danger zone
  • No other work except that required to
  • clear the misfire
  • First attempt is to re-fire the hole
  • Explosives may be removed by washing
  • out with water if re-fire doesnt work
  • All non-electric misfires require 1 hr wait
  • Misfires handled by Blaster in charge

13
Personal Protective Equipment
  • Hard Hat
  • Safety Toed Shoes
  • Reflective Vest
  • Safety Glasses
  • Gloves
  • Hearing Protection

14
Other Regulated Operations
  • Underground Transportation - 1926.903
  • Use of Safety Fuse - 1926.907
  • Use of Detonating Cord - 1926.908
  • Underwater Blasting - 1926.912
  • Blasting in Excavation Work Under Compressed Air
    - 1926.913