Title: Energy Security Masterplan
1Energy Security Masterplan Phase 1
- Parliament Portfolio Committee Presentation
- 18 June 2008
2Introduction - Energy Masterplan
- Developing an integrated energy Masterplan in 2
phases (electricity and liquid fuels) - Some issues in liquid fuels sector could not wait
- Phase 1
- Energy Security framework
- Energy planning approach
- Liquid fuels short to medium plan
- Phase 2
- Presented in October 2007
3Introduction Masterplan (Phase 1)
- In the short-term
- the Master Plan focuses on developing supply
chain solutions to South Africas liquid fuels
supply challenges, management of liquid fuels
demand and emergency response tactics. - In the medium to long-term
- the approach is broader and begins to integrate
supply, demand, macroeconomics, geopolitics and
climate change
4Introduction Masterplan (Phase 1)
- The Masterplan seeks to allow for the making of
well-informed choices in respect of energy
supply, energy carriers, demand sector
strategies, as well as energy transformation
approaches, cognisant of the need to minimise
negative impacts on the environment and the
economy
5Presentation Outline
- Energy security framework
- Energy planning approach
- Liquid fuels industry short to medium plan
- Review of key findings
- Proposed interventions
- Special considerations
6Energy Security
7Energy Security - definition
- Energy security means ensuring that diverse
energy resources, in sustainable quantities and
at affordable prices, are available to the South
African economy in support of economic growth and
poverty alleviation, taking into account
environment management requirements and
interactions among economic sectors.
8GDP loss due to fuel supply interruptions
- Based on 2005 terms, South Africa would lose R925
million per day if there is no fuel
9Electricity supply options
- Whilst dealing with growth in electricity demand,
we need to also worry about replacing existing
capacity
10Economy drives Energy (Oil)
1st Oil crisis, OPEC
Kuwait war
2nd Oil crisis
Asian crisis
11World Oil Reserves
Thousand Million barrels
12Liquid fuels supply issues
End of oil will demand a change in how we deal
with transport
13RSA primary energy supply
Supply
Transform
Transport
End Use
Oil Refineries
Rail Road Pipeline
Liquid Fuels
Oil
Natural Gas
PetroSA
Gas
Pipeline
Sasol
Export
Road/Rail
Washing
Coal
Coal
Eskom and Others
Electricity
Transmission Wires
Hydro
Koeberg
Nuclear
Biomass
Wood
Person/Road
14World projected energy use by fuel type(1980 -
2030)
15World Liquids Production
Source eia March 2007
16World Liquids ProductionUnconventional Liquids
Source eia, March 2007
17Comparative light, heavy and bitumen crude oil
price
Light crude oil price quoted in media (West Texas
Intermediate)
Heavy crude oil price at Hardisty
Estimated bitumen price netback
Source eia, March 2007
18Energy Security Framework
- Energy security is not only about security of
supply
Local production
Foreign relations
Reserve margins
Climate change (mitigation adaptation)
Energy infrastructure planning
Energy security
Standards specifications
Demand management
Diversity of supply
Macro-economic framework
Import Export policies
19Energy modelling planning
20The proposed energy modelling planning
approaches
- Provision of high-quality, energy information, in
a manner that promotes sound policymaking,
efficient markets and public understanding, to - Cabinet
- National, provincial local governments
- Markets
- the public
- Meeting of this challenge requires
- Adoption of transparent approach, methodology and
presentation of results - Avoidance of developing or advocating positions
21Integrated Energy Planning and Modelling
- Provision of high-quality, unbiased energy
information, in manner that promotes sound
policymaking, efficient markets and public
understanding, to - Cabinet
- National, provincial local governments
- Markets
- the public
Requires
Requires
Planning An integrated planning approach is to
ensure that all the constituting elements are
addressed in a coordinated manner
Modelling An integrated energy modeling
capability which would be instrumental in the
development of energy plans and evaluation of
options that are proposed by policy-makers
22Integrated Energy Planning and Modelling
- Separation of modeling, planning and coordination
- Decentralised planning by various entities
- Coordination and integration of such planning
done centrally
Coordination
Integrated Energy Planning
Policy
Other
Options
,
Factors
Strategies
Unbiased
-
Modelling
Modelling Agency
Government
Depts
,
Entity
1
Entity
2
Entity
...
Entity
3
Entity
...
Entity n
SOEs
Individual Policies
,
Strategies
,
Plans
,
Infrastructure
23The modelling process
- Collect, compile and publish reliable energy
data, information and analyses - Produce short and medium-term energy projections
- Analyse impact of proposed energy programs and
policies - Prepare reports on energy issues and legislation
for Cabinet - Prepare special analyses on energy issues and
legislation for the Minister - Prepare special analysis for policy making
departments
24Energy Modelling System (NIEMS)
25Energy Planning and Modelling Process
Annual Forecasts
Modelling
Scenarios/ Options
Policy Decisions
Political Other Factors
Political Other Factors
Integrated Plan
Individual Sectoral Plans
26Modelling vs Planning
Modelling
Planning
- Should be descriptive and policy-neutral (i.e.
avoid policy advocacy) - Modeling should, as a basis for the development
of energy plans, be undertaken in such a way as
to use - prevailing policy,
- legislative arrangements,
- proven or almost proven technology or industry
structural conditions
- Is essentially prescriptive, and not
policy-neutral. - Involves deliberate policy choices, which may go
beyond empirical evidence - Should be about handling of sometimes conflicting
objectives
27Refining
28Refining Competition for Available Flows
FSU
North America
Europe
Pacific Asia
Middle East
Africa
Latin America
Inter Regional Flows Only Not Intra Regional Flows
MT in 2004
29Key refining issues
- South Africa has run out of refining capacity
30Refinery Capacity - Long term supply solutions
Analysis
Graphs
- In order to meet demand a new 85000 BPCD CTL
plant is needed every 3-4 years - If we relied on a 200000 BPCD crude refineries,
two refineries can be absorbed. - Prior to investments in new capacity, significant
imports are expected
The impact of new CTL plants on Imports - 100
utilization on Day 1
Key Issues
- High imports are still periodically required if
one assumes start-up coincides with 100
utilisation - Refinery economics improve with high initial
utilisation - Government might have to incentive CTL/GTL to
minimise Balance of Payment concerns
Source FSSTT study (November 2006)
31Ports
32Ports issues
- Initial analysis indicated problems at the ports,
but further indicates - inadequate interconnections between industry
facilities and berths - In adequate discharge and loading rates in the
system - Discharge and loading rates much lower than those
of vessels and berth loading arms - Not all oil companies have access to all berths
- Berth 9 only - Sasol and Total
- Berth 7 and 8 - Shell, BP and Engen
- Management of unplanned incidents
- Significant volumes when ship cargo is offspec
- Limited ability to move product out of Durban
33Ports issues
- Ports have adequate capacity until 2025
Berth Capacity at 1500 m3/hr Ship Dependant
Discharge Rate 9 ships per week
34Ports proposed interventions
- Oil vessels should be afforded as high a priority
as container vessels - The use of the back of port tanks for anything
other than offloading and loading need to be
prohibited - Back of the port should be operated by an
independent player - TNPA has to address concerns raised by industry
participants with respect to the current lease
agreement held by the various oil companies - DME to provide regulatory certainty
35Fuel Storage
36Storage issues
- Inability of most storage facilities to receive
the large pipeline parcels - New pipeline capacity expected to exacerbate the
situation - Further depot capacity required for
- Strategic stock (60 days crude and products)
- Commercial stock (28 days)
- Most airports operating at maximum five days
stockholding versus 30 days global best practise - Fuel stock holding for Eskom OCGTs
- Diesel fuel demand can increase six fold from 5
load factor to 30 load factor
37Proposed storage facility interventions
- Enforce the stock holding by all customer groups
- Ensure that consumers pay for the stock holding
costs - Include unregulated commercial consumers
- Correct past inequities
- Complete review of petroleum pricing framework
- Limit cross subsidisation all customer groups to
pay for their own insurance
38Inland supply
39Inland supply short term pipeline issues
Pipeline capacity
40Inland supply (road rail)
Graphs
Analysis
- At present 25 of the non-pipeline product
moved inland is by rail - Only 30 of deliveries are for coast to inland
- Unless inland rail transport is increased, more
than 10 road tankers per hour will have to leave
Durban for inland in 2010
4.5 growth and excludes jet by rail to ORTIA
Source FSSTT study (November 2006)
41Inland supply real rail issues
42Inland supply real rail issues
43Inland supply - Proposed rail interventions
- Operational improvements to alleviate potential
congestion along the supply chain, through - Consolidation of the route tankers and route
substitution - Switching to block trains/ block loads thus
exiting inefficient routes - Turnaround time improved from 14 days to 4 days
- Re-allocation of capacity to the Durban-Gauteng
corridor - Additional costs to be borne by Oil industry
- Investments in rail sidings
- Weekend and overtime work
44Inland supply beyond 2010
45Inland supply beyond 2010
- The approval of the NMPP is the most critical
project for the liquid fuels industry - Some changes required to Petronets design
- Cannot leave the approval process to external
processes
46Pipeline sizes costs
47Current state of affairs
- Current growth in demand for petroleum products
used for electricity generation is unsustainable - Potential diesel shortages
48Inland supply proposed pipeline intervention
- Expedite approval and implementation of the NMPP
- Implement split tariff approach
- Direct usage tariff levied on all users
- Initial reserve capacity financed through
security of supply levy on all product - Raise required state equity participation through
dedicated levy
49Summary of recommendations of phase 1 Masterplan
- Manufacturing of petroleum products
- Recommend promotion of local production of
petroleum products - Recommend that at least 30 of products be
manufactured from indigenous raw materials - Climate change be considered an important
component of integrated energy planning - Will require data collection and climate change
monitoring - Alignment of our fuels specification and other
standards (including housing and building
standards) to global standards
50Summary of recommendations of phase 1 Masterplan
- 30 of all crude consumed in South Africa be
procured through PetroSA - Policy of limited imports of petroleum products
be re-endorsed - Energy efficiency be strongly promoted in all
energy consuming sectors of the economy - The energy demand management approach should
include appropriate selection of energy carriers - Demand management requires appropriate demand
sectors strategies, starting from the industrial
strategy through to appropriate transport
strategies - Level of coordinated infrastructure investments
planning
51Summary of recommendations of phase 1 Masterplan
- Keep certain levels of strategic stocks
- Airlines to be forced to keep certain stocks
- Eskom to keep stocks for OCGTs
- Approve Petronets new Multi Product Pipeline
project - In the short term, rail should be operated in
block train format, so as to improve rail turn
around times - Also prioritise Durban to Gauteng route
52Summary of recommendations of phase 1 Masterplan
- The management of the back-of-the-port
operations should be run by an independent
operator - Most importantly, South Africa must build
- an ability to develop properly thought-out energy
plans - a tool to evaluate proposed energy related
policies
53Overall Project Status
- Consultants appointed to manage overall
implementation of programme in September 2007 - Initial briefing meeting with oil industry
executives in December 2007 - Governance structure formalised
- Project kick-off workshop in December 2007
- Key deliverables identified
- Task teams for each stream identified
- High-level steering committee in March 2008
- Accession to PDR
- Follow up project workshop in March 2008
- Task teams for each workstream formalised
- Task-team project meeting currently in progress
- Detailed implementation schedule from each task
team due end May 2008 - Ongoing implementation and monitoring
54I Thank You