The Treatment of - PowerPoint PPT Presentation

1 / 10
About This Presentation
Title:

The Treatment of

Description:

The Treatment of Spare / Sterilised Capacity Draft for discussion purposes only – PowerPoint PPT presentation

Number of Views:47
Avg rating:3.0/5.0
Slides: 11
Provided by: mart7186
Category:

less

Transcript and Presenter's Notes

Title: The Treatment of


1
The Treatment of Spare / Sterilised Capacity
  • Draft for discussion purposes only

2
High Level Policy
  • As part of TPCR three new measures were
    introduced to ensure that sterilised / spare
    capacity would not be withheld from the wider
    market
  • Capacity substitution
  • Trades and transfers
  • Reduction in capacity held back for shorter term
    auctions now 10
  • In addition Ofgem consider that the charging
    methodology and IECR should take account of these
    developments
  • The key is now to develop the measures to
    implement these policies and to ensure they are
    complementary

3
Implementation of these policies
  • On the assumption that baselines broadly
    reflect the physical capability of the network, a
    number of options have been developed to consider
    how TT and capacity substitution could be
    enacted
  • The options try to cover the broad range of
    possibilities from the very dynamic application
    to the stable and predictable.
  • The intent is to seek feedback on these options
    today and to receive any written input until the
    31/8.
  • We will then further develop and circulate the
    favoured options ahead of the workshop on the
    12/9.

4
Range Of Options
  • Option 1 The Fast Furious
  • Capacity substitution
  • triggered at QSEC (implemented Sept 08)
  • applicable from Y2
  • all available capacity subject to substitution
  • no NPV test
  • no limit on exchange rates
  • Trades and transfers
  • embedded in RMSEC AMSEC, covering M1 to Y2
  • no limit on exchange rates

5
Range Of Options
Option 1 The Fast Furious
  • Option 5 Driving Miss Daisy
  • Capacity substitution
  • undertaken every 5 years as part of TPCR
    following consulted upon Ofgem methodology
  • Trades and transfers
  • embedded in RMSEC only covering M1
  • limit on exchange

6
Range Of Options
Option 1 The Fast Furious
  • Option 2
  • Capacity substitution
  • triggered at QSEC (implemented Sept 08)
  • applicable from Y2
  • all available capacity subject to substitution
  • lower NPV test
  • limit on exchange rates
  • Trades and transfers
  • embedded in RMSEC AMSEC, covering M1 to Y1
  • no limit on exchange rates

Option 5 Driving Miss Daisy
7
Range Of Options
Option 1 The Fast Furious
  • Option 3
  • Capacity substitution
  • triggered at QSEC (implemented Sept 08)
  • applicable from Y2
  • only certain capacity subject to substitution
  • lower NPV test
  • limit on exchange rates
  • Trades and transfers
  • embedded in RMSEC AMSEC, covering M1 to Y1
  • no limit on exchange rates

Option 5 Driving Miss Daisy
8
Only certain capacity available for substitution
  • The key issue seems to be to define sterilised /
    spare capacity. This could be based just on long
    term bookings or alternative metrics could be
    considered.
  • For example where there is a degree of long term
    bookings and short term usage the capacity should
    not be substituted away as this would not be
    sterilised / spare capacity e.g.
  • If there are bookings in 2 quarters for four
    consecutive years at 50 of the existing baseline
    and flows during the last year have been 90 of
    the baseline no capacity will be substituted
    away.

9
Range Of Options
Option 1 The Fast Furious
  • Option 4
  • Capacity substitution
  • triggered at QSEC (implemented Sept 08)
  • applicable from Y4
  • only certain capacity subject to substitution
  • same NPV test as for incremental
  • limit on exchange rates
  • Trades and transfers
  • embedded in RMSEC AMSEC, covering M1 to Y1
  • limit on exchange rates

Option 5 Driving Miss Daisy
10
Open discussion
  • Do the options presented represent the full range
    of credible possibilities?
  • Are their other aspects that should be developed
    ahead of the 12 September workshops?
  • What are your initial reactions?
  • Please provide your written comments on the
    options to National Grid NTS by 31/8.
Write a Comment
User Comments (0)
About PowerShow.com