Measuring Sitework, Excavation, and Piling - PowerPoint PPT Presentation

1 / 23
About This Presentation
Title:

Measuring Sitework, Excavation, and Piling

Description:

www.rhinelander.k12.wi.us – PowerPoint PPT presentation

Number of Views:349
Avg rating:3.0/5.0
Slides: 24
Provided by: wius
Category:

less

Transcript and Presenter's Notes

Title: Measuring Sitework, Excavation, and Piling


1
Chapter 4
  • Measuring Sitework, Excavation, and Piling

2
Objectives
  • Upon completion of this chapter, you will be able
    to
  • Determine the likely soil conditions at a site by
    studying a soils report
  • Explain the use of swell factor and compaction
    factor when calculating volumes of excavation and
    backfill

3
Objectives (contd.)
  • Define bank measure and explain how it applies to
    sitework takeoffs
  • Describe and use the grid method of calculating
    cut and fill volumes
  • Describe and use the section method of
    calculating cut and fill volumes
  • Explain how piling work is measured in a takeoff

4
Objectives (contd.)
  • Explain how trenches and basements are measured
    in a takeoff
  • Complete a manual takeoff of sitework
  • Complete a computer takeoff of sitework using
    Excel spreadsheets and MC2 ICE software

5
Generally
  • Measuring sitework and excavation work
  • Different from measuring most other work
  • Current site condition may not be provided
  • Dimensions and shape of excavations may not be
    disclosed
  • Estimators must assess requirements before
    measuring site work

6
Soils Report
  • Provides subsurface condition information
  • Usually not a bid document
  • Includes data for foundation system design
  • Comments on sample soils report
  • Topsoil, moisture content, soil compaction, slope
    ratio, drainage, etc.

7
Bank Measure, Swell, and Compaction Factors
  • Extracted soil
  • Less dense and will occupy more space
  • Compaction factor
  • Difference between hole volume and fill material
    volume
  • Bank measure
  • Obtained using hole dimensions

8
Excavation Safety Considerations
  • Potential danger to workers
  • Cave-ins
  • OSHAs Construction Safety and Health Regulations
  • Requires shoring systems or cutting back sides to
    a safe angle
  • Strongly enforced

9
Use of Digitizers
  • Electronic devices
  • Enables user to take measurements from drawings
  • Input directly into computer program
  • Digitizer types
  • Sonic
  • Tablet

10
On-Screen Takeoff
  • Eliminates need for paper-based printouts
  • Number of formats
  • Cost savings
  • Speed
  • Convenience
  • Plans still have to be drawn to scale

11
Measuring NotesExcavation and Backfill
  • Include
  • Measure in cubic yards or cubic meters bank
    measure
  • Classify and measure separately
  • Excavations
  • Materials
  • Hand excavation
  • Disposal of surplus soil

12
Calculation of Cut and Fill Using the Grid
Method
  • Requires a site survey
  • Showing elevation of existing grade
  • Each intersection point on the grid
  • Plotted at each intersection point
  • Depth of cut can be obtained at each point
  • Refer to Figures 4.1 and 4.2
  • Accuracy depends on grid spacing

13
Calculation of Cut and Fill Using the Section
Method
  • Mostly used with long, relatively narrow areas of
    cut and fill
  • Road and railroad construction
  • Results quality depends on accuracy of plotting
  • Refer to Figure 4.3

14
Trench Excavations
  • Formula for trench volume
  • Trench Volume Length of Trench Centerline
    Average Width of Trench Average Depth of Trench
  • Refer to Figure 4.4
  • Sides of trenches often cut-back due to
  • Safety reasons
  • Soil will not stand vertically

15
Trench Backfill
  • Volume of backfill for a trench
  • Generally equal to volume of excavation minus
    volume of what is to be contained
  • Surplus occurs when volume of excavation exceeds
    amount required for backfill
  • Item for disposal of surplus material is required

16
Greater Accuracy
  • Formula used to calculate volume of excavation
  • Usually sufficient
  • Some situations require more accuracy
  • Example pit and basement excavations

17
Measuring NotesPiling
  • Often subcontracted to specialized companies
  • Typical general contractor items
  • Layout of piles
  • Cutting off tops of piles
  • Removing excavated material

18
Bearing Piles
  • Generally
  • Measure in linear feet or meters
  • Include a separate lump-sum item for equipment
  • Piles that are measures separately
  • Measurement may be subdivided
  • Enumerate splicing and lengthening of piles

19
Bearing Piles (contd.)
  • Additional considerations
  • Classification of bearing piles
  • Timber piles
  • Steel piles
  • Precast concrete piles
  • Poured-in-place concrete piles

20
Sheet Piling
  • Generally
  • Described and measured in square feet or square
    meters
  • Separately measure piles
  • Measurement may be subdivided
  • Measure withdrawing of piles
  • Cutting off of sheet piling measured in linear
    feet or meters

21
Sheet Piling (contd.)
  • Splices described and measured by number
  • Timber sheet piling, concrete sheet piling, and
    steel sheet piling measured according to
    foregoing principles
  • Extraction of piles measured separately

22
Additional Examples
  • Drawings
  • Refer to Figures 4.11 and 4.12
  • Sitework takeoff
  • Example 1The House Project
  • Takeoff Shown as Figure 4.6a
  • Example 2The Office/Warehouse Project
  • Takeoff Shown in Figure 4.14a
  • Sitework Takeoff Using ICE Software

23
Summary
  • The estimator has to make an assessment of
    sitework requirements
  • Based on plans and specifications
  • Site visit
  • Soils report
  • Efficiency can be increased using a digitizer
  • Sitework takeoffs can be done manually or via
    computer
Write a Comment
User Comments (0)
About PowerShow.com