CIVL202 Construction Engineering I

Description:

CIVL202 Construction Engineering I Tutorial 9 T1 Mon 11:00 11:50 T2 Wed 09:00 09:50 Tutorial Outline Parameters and algorithm of CPM A sample about AON ... – PowerPoint PPT presentation

Number of Views:39
Avg rating:3.0/5.0
Slides: 12
Provided by: Departm114
Category:

less

Transcript and Presenter's Notes

Title: CIVL202 Construction Engineering I


1
CIVL202Construction Engineering I
  • Tutorial 9
  • T1 Mon 1100 1150
  • T2 Wed 0900 0950

2
Tutorial Outline
  • Parameters and algorithm of CPM
  • A sample about AON

3
Parameters of CPM
EST(I) early start time of activity I EFT(I)
early finish time of activity I LST(I) late
start time of activity I EST(I) late finish
time of activity I
4
Algorithm of CPM
  • Forward-pass algorithm

EFT(I) EST(I) DUR(I)
(1)
(2)
5
Algorithm of CPM
  • Backward-pass algorithm

LST(J) LFT(J) - DUR(J)
(1)
(2)
6
Example about AON
7
Float
  • Float The amount by which an activity can be
    delayed without delaying the total project is
    called float.

Four types of float
  • Total Float
  • Free Float
  • Interfering Float
  • Independent Float

8
Total float
  • Total float
  • The total, or maximum, number of time units that
    an activity can be delayed without increasing the
    total project duration.

TF(I) LFT(I) EFT(I)
9
Free float
  • Free Float
  • The amount of time an activity can be delayed
    without impacting activities that follow it.

10
  • Interfering Float
  • The amount of the total float utilized that
    interferes with the following activities.

IF(I) TF(I) FF(I)
11