Title: ONONDAGA CREEK, NEAR SYRACUSE, NY. SITE 5-D
1ONONDAGA CREEK, NEAR SYRACUSE, NY. SITE 5-D
OTHER REACHESEngineered Rocked Riffles (with
all stones in compression), Traffic Control
Stones, LPSTP, transplanted Vegetation, a Boil-Up
Pool, a Viffle
2THE NATURAL, THEN CONSTRUCTED BOIL-UP POOL ON
UPPER ONONDAGA CREEK, NEAR SYRACUSE, NEW
YORKConstructed May 2006 The go-to guy, Mark
Schaub with the Onondaga County Soil and Water
Conservation District, Lafayette, NY.
3Looking US toward the left bank. Note the
interesting natural hook causing a Boil-Up pool.
4/18/2006
4Another view of the left bank, 4/18/2006
5Not much of a hook, but very effective at forming
a natural deep, circular, scour pool. 4/18/2006
6Natural Boil-Up Pool on Onondaga Creek. 4/18/2006
7Looking DS, construction has begun on DS riprap
and Engineered Rocked Riffle. 5/24/2006
8Looking DS, stone in, but not a great semi-circle
yet-5/24/06
9Looking DS, bank stone kicker in, still not a
good semi -circle 5/24/2006
10Looking US, note how bank kicks current, just a
little more tweaking needed (pull some toe stone
back) 5/24/2006
11The next day, flow right to left. All angles and
circles correct, note flow over curved kicker,
truly a thing of beauty!!!
12Looking DS. Planform now consists of two pools
a riffle within the bend 5/25/2006
13 Looking US at the Boil-Up Pool at bankfull
stage. Note thalweg down the center of the stream
14 Looking US at the Boil-Up Pool at bankfull
stage. Note thalweg down the center of the stream
153 YEARS AFTER PROJECT COMPLETIONPhotos by
Derrick JUNE 18, 2009
16Looking US _at_ the Boil-Up Pool 3 yrs after
construction, Boil-Up working well even under
base flow conditions, and streamside veg coming
on strong.
3 YEARS LATER - Onondaga Creek-Site 5-D.
-DERRICK 6-18-2009
17From the road looking downhill DS _at_ the US
Engineered Rocked Riffle the Boil-Up Pool.
3 YEARS LATER - Onondaga Creek-Site 5-D.
-DERRICK 6-18-2009
18UPPER ONONDAGA CREEK SITE 5-D CONSTRUCTED
JULY 2006
19THE UPPERMOST ENGINEERED ROCKED RIFFLE IN
REACH 5-D ALL STONES IN COMPRESSION
20Looking DS, two rows of stone in. Placing stone
in compression, working from DS to US
- Photo by Mark Schaub, OCSWCD
21ERR, 2 rows in, flow right to left
- Photo by Mark Schaub, OCSWCD
22Looking DS at the completed ERR
- Photo by Mark Schaub, OCSWCD
23Looking DS at the completed ERR, note nice pool
US.
- Photo by Mark Schaub, OCSWCD
24Looking DS, close-up of the ERR
- Photo by Mark Schaub, OCSWCD
25TRANSPLANTING EXISTING VEG AND/OR ROOT MATS
WITH THE TRACKHOE 2 MINI CASE STUDIES
26DIAMOND -ORIENTED TRAFFIC CONTROL STONES
TCS WITH BEDLOAD BENCH IN BETWEEN, WITH
TRANSPLANTED VEGETATION ON TOP OF TCS
BEDLOAD BENCH WITH SINGLE-STONE BENDWAY
WEIRS ON EVERY 4th TCS .
27TCS were typically 3 ft by 3 ft by 3 ft, spaced 6
to 8 ft apart, with bedload material choked in
between forming a continuous bench. Vegetation
was pulled down from top bank placed on the
bench. Every 4th TCS was keyed into the bank
had a single-stone Bendway Weir added to the
stream end.
28Typical stones used as Diamond Traffic Control
Stones
29Looking DS at a Diamond Traffic Control Stone-in
place, but not dug in yet
- Photo by Mark Schaub, OCSWCD
30Placing a Diamond Traffic Control Stone
- Photo by Mark Schaub, OCSWCD
31Traffic Control Stones
Bedload material placed between Traffic Control
Stones
- Photo by Mark Schaub, OCSWCD
32Looking at a Single Stone Bendway Weir a TCS
and key stone (one more key stone needed)
33BW
BW
Looking DS at Single Stone Bendway Weirs
Diamond-Oriented Traffic Control Stones (most
hidden)
343 YEARS AFTER PROJECT COMPLETIONPhotos by
Derrick JUNE 18, 2009
35Looking DS _at_ the US key Traffic Control Stones
(TCS) Single Stone Bendway Weirs (SSBW). Note
thalweg trace. Hydraulic Cover Stone in middle
of pool.
3 YEARS LATER - Onondaga Creek-Site 5-D.
-DERRICK 6-18-2009
36Close-up, looking DS _at_ TCS SSBW, note thalweg.
Slope at toe of bank come go dynamics
erosion, then deposition
3 YEARS LATER - Onondaga Creek-Site 5-D.
-DERRICK 6-18-2009
37Single Stone Bendway Weir with Traffic Control
Stone (key is hidden). Bank is stable vegged.
3 YEARS LATER - Onondaga Creek-Site 5-D.
-DERRICK 6-18-2009
38Traffic Control Stones with a narrow bench of
bedload material between. Note vertical bank
above.
Onondaga Creek, Site 5-D, constructed July 2006
39Onondaga Creek, Site 5-D, constructed July 2006
Traffic Control Stones
Bedload material placed between Traffic Control
Stones
40Slide that veg down the slope!
41Slide more veg down the hill
Onondaga Creek, Site 5-D, constructed July 2006
42Slide even more veg down the slope. Note long
Instant Shade over stream
43Right bank TCS with SSBW DS of the Rocked Riffle.
Bank mostly stable vegged
3 YEARS LATER - Onondaga Creek-Site 5-D.
-DERRICK 6-18-2009
44Right bank partly hidden, TCSs with a Single
Stone Bendway Weir. Stable bank with lush veg
bedload material between TCSs.
3 YEARS LATER - Onondaga Creek-Site 5-D.
-DERRICK 6-18-2009
45Right bank TCS SS Bendway Weirs.
3 YEARS LATER - Onondaga Creek-Site 5-D.
-DERRICK 6-18-2009
46KEYED LPSTP WITH TRANSPLANTED VEGETATION ON
TOP PLUS 2 SINGLE-STONE BENDWAY WEIRS.
47Pre-project-Looking DS at LPSTP project bend
- Photo by Mark Schaub, OCSWCD
48LPSTP with bedload choking that forms a mini
floodplain bench on top of the LPSTP.
Onondaga Creek, Site 5-D, constructed July 2006
49Sliding veg root mats downslope onto LPSTP bench
50Sliding veg root mats downslope onto LPSTP bench
51Digging placing buckets of gray dogwood onto
the LPSTP bench.
52Its an instant jungle!!!!
53This section is complete, 2 hrs of machine time
for LPSTP, 2 Single-Stone Bendway Weirs veg
transplant 100 ft of protection
Onondaga Creek, Site 5-D, constructed July 2006
54Approx. 6 months after installation, looking DS
55Looking DS _at_ LPSTP SS Bendway Weir.
3 YEARS LATER - Onondaga Creek-Site 5-D.
-DERRICK 6-18-2009
56THE VIFFLEA Derrick-McCullah idea hatched late
at night in the Seattle airport while headed to
Alaska
- Combining the best attributes of the
Cross-Vane and the Engineered Rocked Riffle (rock
vanes slowing currents near banks and riffle
improving fish passage and creating a properly
proportioned scour pool with flat sloped
tail-out) - Build the two Rock Vane arms of the Cross-Vane
- Downstream instead of a vertical drop build
the rocked riffle. At DS end of riffle the
stones are keyed into the bed all stones are
placed in compression
57THE FOLLOWING VIFFLE IS NEW CONSTRUCTION,
NOT A REPAIR OF AN EXISTING CROSSVANE
58Looking US at rock vane section of Viffle, rocked
riffle portion not constructed yet. Onondaga
Creek, Site 5-D, Aug 2006.
- Photo by Mark Schaub, OCSWCD
59Onondaga Creek, Site 5-D, Looking across US at
the completed VIFFLE (Vane rIFFLE), Rocked riffle
section choked with creek gravel
- Photo by Mark Schaub, OCSWCD
60Red line delineates location of crest stones
keys of completed Viffle
- Photo by Mark Schaub, OCSWCD
61Looking DS _at_ the Viffle with natural leaner
tree.
3 YEARS LATER - Onondaga Creek-Site 5-D.
-DERRICK 6-18-2009
62Looking US _at_ the same Engineered Rocked Riffle.
3 YEARS LATER - Onondaga Creek-Site 5-D.
-DERRICK 6-18-2009
63Additional headcuts from DS causing problems on a
Cross-Vane built in 2005, in response we will
rebuild these as Viffles!!
Photo by derrick-July 11, 2006, constructed 2004
64Onondaga Creek-Site 5-D. 14 months later
10-16-2007. We will start upstream and flow
downstream. All photos by Mark Schaub, Onondaga
County Soil Water Conservation District
65Looking US at US key for the TCS a TCS with a
Single-Stone Bendway Weir
Onondaga Creek-Site 5-D. 14 months later
10-16-2007-from Mark Schaub
66Looking DS at the US ERR with TCS with BW on
right bank.
Onondaga Creek-Site 5-D. 14 months later
10-16-2007-from Mark Schaub
67Looking DS at TCS TCS with BW on right bank.
Onondaga Creek-Site 5-D. 14 months later
10-16-2007-from Mark Schaub
68Looking across at Traffic Control Stones.
Onondaga Creek-Site 5-D. 14 months later
10-16-2007-from Mark Schaub
69Looking US at an ERR TCS on right descending
bank
Onondaga Creek-Site 5-D. 14 months later
10-16-2007-from Mark Schaub
70Looking DS at the LPSTP with Single-Stone BW in
foreground
Onondaga Creek-Site 5-D. 14 months later
10-16-2007-from Mark Schaub
71Looking DS at the LPSTP.
Onondaga Creek-Site 5-D. 14 months later
10-16-2007-from Mark Schaub
72Looking US at the Viffle. Key stone barely
visible on each bank
Onondaga Creek-Site 5-D. 14 months later
10-16-2007-from Mark Schaub
73Looking US at the Viffle with the LPSTP in
background
Onondaga Creek-Site 5-D. 14 months later
10-16-2007-from Mark Schaub
74Nov 8, 2006 a big tour for 60 fellow
professionals, show off cool innovative stuff to
folks, give everyone good ideas to use!!
75the Bassett as a mountain lion