Title: Sliding Scale Contingencies
1Sliding Scale Contingencies
Transportation Estimators Association Annual
Conference Omaha, Nebraska September 24, 2009
- For Transportation Projects
A Delphi Study
Niyi Olumide Stuart Anderson Texas A M
University
2Outline
- Introduction
- Background
- Contingency Estimating
- Research Questions
- Study Objectives
- Methodology
- Contingency Matrices
- Results
- Applications of Sliding Scales
- Conclusions
3Introduction
What is a Base Estimate?
The most likely project cost estimate in any
phase at any time, which normally includes all
estimated known project costs, but does not
include project contingency
What is Contingency?
An estimate of costs associated with identified
risks, the sum of which is added to the base
estimate.
4Cost Estimate at Any Phase
- Total Project Estimate Base Contingency
5- Introduction
- Background and Motivation
- NCHRP 8-60 Risk Analysis Tools and Management
Practices to Control Transportation Project Costs
6Background
NCHRP 8-60
Published Definition of Contingency 48 of 52
SHAs responding
7Motivation
- Contingency
- Provides costs for uncertainties associated with
projects cost estimates - Reduces over planning and project development
time cycle, therefore, so does the amount of
contingency - Enhances accuracy of cost estimates
- Improves communication to stakeholders
8- Introduction
- Background
- Contingency Estimating
- Contingency and the Project Development Process
(PDP) - Risk in the Cost Estimation Process
- Contingency in the Highway PDP
9Contingency Estimating and PDP
- The Project Development Process (PDP)
- Project 8-49 (Report 574)
10Risk in the Cost Estimation Process
Phases of Project Development
Compare
Uncertainty
Contingency
Re-evaluate
11Cost Estimates and Contingency (w/Total Project
Cost Estimate Baseline Estimate)
Baseline Estimate Total Project Cost Estimate
Project Cost
Cost Range
Contingency
Contingency
Contingency
Base Estimate
Base Estimate
Base Estimate
Base Estimate
Planning
Preliminary Design
Final Design
Programming
Project Development Process
12Cost Estimates and Contingency
Total Project Cost Estimate Baseline Estimate
Baseline Estimate Total Project Cost Estimate
Contingency
Contingency
Project Cost
Base Estimate
Base Estimate
Base Estimate
Preliminary Design
Final Design
Programming
Total Project Cost Estimate lt Baseline Estimate
Baseline Estimate
Contingency
Total Project Cost Estimate
Contingency
Project Cost
Base Estimate
Base Estimate
Base Estimate
Programming
Preliminary Design
Final Design
13Contingency in the Highway PDP
- SHA methods of setting contingency
- Standard Predetermined Contingency across
projects - Unique Project Contingency (Estimators/Engineers)
- Formal Risk Analysis and associated contingency
- NCHRP 8-60
- 16 of 48 SHAs stated use of standard
predetermined contingencies - Majority indicated that they use unique project
contingencies - Formal risk analysis not as widely used
14Sliding Scale Contingency Ohio DOT Approach
15Contingency in the Highway PDP
- Major Problems in Contingency Estimation
- Inconsistencies in application of contingencies
- Poor definitions of what constitutes contingency
- Inappropriate application of contingency amounts
to cover other issues instead of the intended
purpose - Contingency estimation methods One method may
not necessarily serve all project types - Rationale for selecting method may not
sufficiently address major issues like project
complexity
16- Introduction
- Background
- Contingency Estimating
- Research Questions
17Research Questions
- How does the application of contingency change
across the PDP? - How do the ranges of contingency change across
the PDP in the Highway Industry? - How do factors such as the following impact
contingency estimates? - Project Size/Complexity
- Estimation method
- Level of scope definition
18Research Questions
- When using contingency scales, do the contingency
bands narrow linearly or decrease exponentially
or in some other form across the PDP? - What is the relationship between uncertainty,
risk and contingency?
19- Introduction
- Background
- Contingency Estimating
- Research Questions
- Study Objectives
20Study Objective
- Main Objective
- To develop sliding scale contingencies that can
be used in the estimation and management of the
cost of highway projects taking into account the
effects of project complexity, level of project
definition, estimation methodology, and phase of
project development
21- Introduction
- Background
- Contingency Estimating
- Research Questions
- Study Objectives
- Methodology
- The Delphi Technique
- Panel of Experts
22The Delphi Technique
- What is the Delphi Technique?
- An iterative method used to gather opinions from
a group of qualified individuals to solve a
complex problem - The method relies mainly on the judgment of
experts to solve problems - It lends its application to solve problems where
there is little or no empirical evidence - It is conducted through the application of a
series of questionnaires called rounds typically
a minimum of 2 rounds - The main aim of the Delphi technique is to
achieve consensus among the experts
23The Delphi Technique
- Key Features
- Anonymity minimizes the effects of bias,
conflict, individual status and intimidation - Effectively structures group communication
- Eliminates the draw backs of face-to-face
participation - Controlled feedback to participants at the end of
each round enables participants make fully
informed decisions
24The Delphi Technique
- Caution!!!
- Repeated rounds may lead to fatigue or loss of
interest of the panel members - May take a substantial amount of time and
participant effort to complete if questionnaires
are not carefully structured - Panel members should represent several relevant
disciplines to guarantee a wide knowledge base
25The Delphi Technique
- Round 1 Group Response Analysis
- Controlled Feedback in round 2
- Round 2 Group Response Analysis
- Controlled Feedback in subsequent rounds
26Panel of Experts
- Profile
- Invitations sent to approximately 80 potential
participants - 23 professionals agreed to participate and made
up the panel - Majority had experience
- Estimating (5 to 20 years experience)
- Risk Assessment (2 to 5 years experience)
- Majority of participants were from SHAs
27Panel of Experts
- Expertise
- Project Managers
- Project Engineers
- Risk Coordinators
- Cost Estimators
- Construction Managers
- Program Managers
- Design Engineers
- Contract Managers
- Project Planners
28- Introduction
- Background
- Contingency Estimating
- Research Questions
- Study Objectives
- Methodology
- Contingency Matrices
- Complexity Classifications
- Representative Risks
- Matrices
29Contingency Matrices
- Participants were provided 3 contingency matrices
for 3 complexity scenarios across the phases of
project development - Complexity definitions from NCHRP 8-49 (Report
574) - Non-Complex (Minor) Projects
- Moderately Complex Projects
- Most Complex (Major) Projects
- Typical risks were associated with the complexity
levels
30Complexity Classifications
- Levels of Complexity are distinguished using
- Roadway attributes
- Traffic control approaches
- Structures
- Right of way
- Utilities
- Environmental requirements
- Stakeholder involvement
31Complexity Classifications
- Examples of complexity classifications (full
definitions in Report 574)
Project Types based on Complexity Project Types based on Complexity Project Types based on Complexity
Most Complex (Major) Moderately Complex Non-Complex (Minor)
New highway major relocations New interchanges Capacity adding/major widening Major reconstruction (4R 3R with multi-phase traffic control) Congestion Management Studies are required 3R and 4R projects which do not add capacity Minor roadway relocations Certain complex (non-trail enhancements) projects Slides, subsidence Maintenance betterment projects Overlay projects, simple widening without right-of-way (or very minimum right-of-way take) little or no utility coordination Non-complex enhancement projects without new bridges (e.g. bike trails)
32Representative Risks
- Examples of the Representative Risks for the 3
project complexity scenarios
Project Type Most Complex Moderately Complex Non-Complex
REPRESENTATIVE RISKS Unresolved constructability issues Geotechnical Issues Contractor delays
REPRESENTATIVE RISKS Design Complexity Changes in materials/ foundation Changes in Program priorities
REPRESENTATIVE RISKS Political Factors Delays in permitting process Errors in cost estimating
REPRESENTATIVE RISKS Complex environmental requirements Bridge redesign/ analysis Inaccurate Technical assumptions
33Contingency Matrices
- For each complexity scenario, participants were
asked to input appropriate ranges of contingency
(Low, Most Likely Estimate, High) in the matrices
based on - Phase of Project Development
- Level of Project definition
- Type of Estimate
- Historic Data
- Representative Risks for the different project
types
34Matrices
35Project Type/ Complexity No. of Phases Phase of Project Development Phase Description Level of Definition Estimate Type Historic Data
Non-Complex (Minor) 5 Planning 10 to 20 yrs from letting 1 - 3 Parametric with Historical Percentages Cost per Lane mile, Past Projects
Non-Complex (Minor) 5 Programming/ Preliminary Design 5 to 10 yrs from letting 5 -15 Bid based (80/20 rule) with other Recent Bids, Past Projects
Non-Complex (Minor) 5 Design 1 4 yrs or less from letting 15 - 40 Bid based with 75 line items identified Recent Bids
Non-Complex (Minor) 5 Design 2 less than 4 yrs from letting 40 - 70 Bid based with 90 Line items identified Recent Bids
Non-Complex (Minor) 5 Design 3 less than 4 yrs from letting 70 - 100 Bid based, Cost based. All items (Pay) Recent Bids and/or Labor, Material, Equipment Costs
Moderately Complex 5 Planning 10 to 20 yrs from letting 4 - 7 Parametric with Historical Percentages Cost per Lane mile, Past Projects
Moderately Complex 5 Programming/ Preliminary Design 5 to 10 yrs from Letting 15 - 25 Bid based (80/20 rule) with other Recent Bids, Past Projects
Moderately Complex 5 Design 1 4 yrs or less from letting 25 - 35 Bid based with 75 line items identified Recent Bids
Moderately Complex 5 Design 2 less than 4 yrs from letting 35 - 70 Bid based with 90 Line items identified Recent Bids
Moderately Complex 5 Design 3 less than 4 yrs from letting 70 - 100 Bid based, Cost based. All items (Pay) Recent Bids and/or Labor, Material, Equipment Costs
Most Complex (Major) 4 Planning 10 to 20 yrs from letting 7 - 15 Parametric with Historical Percentages Cost per Lane mile, Past Projects
Most Complex (Major) 4 Programming/ Preliminary Design 5 to 10 yrs from letting 15 - 35 Bid based (80/20 rule) with other Recent Bids, Past Projects
Most Complex (Major) 4 Design 2 less than 4 yrs from letting 35 - 75 Bid based with 80 Line items identified Recent Bids
Most Complex (Major) 4 Design 3 less than 4 yrs from letting 75 - 100 Bid based, Cost based. All items (Pay) Recent Bids and/or Labor, Material, Equipment Costs
36Round 1 Matrices
37Round 2 Matrices
38- Introduction
- Background
- Contingency Estimating
- Research Questions
- Study Objectives
- Methodology
- Contingency Matrices
- Results
- Overview of Rounds
- Contingency Inclusions and Exclusions
- Results
39Overview of Rounds
- Round 1 formed the basis for subsequent rounds
contingency ranges were very wide - Contingency ranges provided were between 0 and
500 contingency across the categories - In Round 2 ranges tightened between 0 and 400
contingency across the categories - In round 3, majority of participants did not make
any significant changes made to earlier
assessments
40Overview of Rounds
- Mean was used as the main feedback to
participants at the end of each round - Participants were provided all summary statistics
from previous rounds as part of the feedback at
the end of each round - Response rate was 100 for all three rounds all
23 participants responded - Stability was achieved in the results after 3
rounds
41Contingency Inclusions
- Some participants indicated a few of the major
items included in the contingency - Cost Overruns
- Change orders during construction
- 5-10 for minor items
- 5 for supplemental work not identifiable at time
of estimate preparation
42Contingency Exclusions
- Some participants indicated a few of the major
items NOT included in the contingency - An allowance for cost escalation
- Allowances for items known to be required as part
of the base project but not yet quantified in
cost estimate - Funds available for cost adjustments driven by
predetermined market factors and incentives
43Results
- Median ranges were slightly lower than the mean
ranges for most of the categories - The median was used as the final results to
eliminate bias in the results
44Mean Contingencies
Phase Planning Programming Design 1 Design 2 Design 3
Non-Complex Projects Non-Complex Projects Non-Complex Projects Non-Complex Projects Non-Complex Projects Non-Complex Projects
Ranges () 24-68 21-56 16-38 11-25 5-14
MLE () 41 34 25 17 9
Moderately Complex Projects Moderately Complex Projects Moderately Complex Projects Moderately Complex Projects Moderately Complex Projects Moderately Complex Projects
Ranges () 33-92 27-68 21-50 15-32 8-20
MLE () 59 43 31 22 13
Most Complex Projects Most Complex Projects Most Complex Projects Most Complex Projects Most Complex Projects Most Complex Projects
Ranges () 47-125 36-89 20-48 12-32
MLE () 75 59 31 21
- MLE Most Likely Estimate of Contingency
45Non-Complex Projects
Phase Planning Programming Design 1 Design 2 Design 3
Ranges () 22-50 20-40 14-30 9-20 5-15
MLE () 35 30 20 15 8
- Median Contingencies
- Ranges Range Estimating
- MLE Deterministic Estimating
- Estimator can pick values within ranges based on
project risks
46Non-Complex (Minor) Projects
47Moderately Complex Projects
Phase Planning Programming Design 1 Design 2 Design 3
Ranges () 30-75 25-60 20-40 13-30 7-19
MLE () 50 40 30 20 10
- Median Contingencies
- Ranges Range Estimating
- MLE Deterministic Estimating
- Estimator may pick values within ranges based on
project risks
48Moderately Complex Projects
Planning Programming Design 1 Design 2
Design 3
49Most Complex Projects
Phase Planning Programming Design 2 Design 3
Ranges () 40-100 34-75 20-40 11-30
MLE () 60 50 28 20
- Median Contingencies
- Ranges Range Estimating
- MLE Deterministic Estimating
- Estimator may pick values within ranges based on
project risks - Higher level of definition in the programming
phase due to complexity of project
50Most Complex (Major) Projects
Planning Programming
Design 2 Design 3
51- Introduction
- Background
- Contingency Estimating
- Research Questions
- Study Objectives
- Methodology
- Contingency Matrices
- Results
- Application of Sliding Scales
- 5 major steps, Benefits, Limitations,
52Application of Sliding Scales
- To successfully apply these scales estimators
must perform 5 major steps - Remove all contingencies and conservative biases
from the base estimate - Classify the project by complexity as most
complex, moderately complex or non-complex - Determine current phase of project development at
time of estimate preparation - Identify risks as drivers of contingency
- Add appropriate contingency to the base estimate
consistent with risks - Repeat the process at each major phase of project
development
53Benefits
- Creates consistency in defining and applying
contingency to projects - Relatively easy to use
- Implied retirement of contingency across the
phases of project development
54Limitations
- Contingencies are not directly tied to risks and
uncertainties - Risks should be identified and monitored
- A risk list could provide justification to
stakeholders for contingency included in estimate - For larger moderately complex and all complex
projects - Analysis of unique project risks is recommended
in developing contingencies - Focus on contingency related to construction
costs only
55- Introduction
- Background
- Contingency Estimating
- Research Questions
- Study Objectives
- Methodology
- Contingency Matrices
- Results
- Applications of Sliding Scales
- Conclusions
56Conclusions
- The Sliding Scales provide a defensible top-down
method for estimating contingency - Takes into account the effect of major factors
that affect contingency - Note!!!
- For successful application, estimators must
remove all contingencies and conservative biases
from base estimate before applying sliding scale
contingencies
57Questions / Comments?