Title: Cryo Capture Cavity II Progress


1
Cryo Capture Cavity II Progress
  • Mike McGee
  • April 6, 2005

2
DESY will Provide
  • 1.3 GHz cavity
  • Helium vessel
  • Magnet shielding (short)
  • 2 VAT valves
  • Input coupler assembly

3
Status at Fermilab
  • Finalizing US AND DS warm-to-cold transition and
    VAT valve to cavity spool design
  • 316 L bellows specified and ordered (to arrive
    4/24)
  • 316 LN material and tube ready to order
  • Designing VAT valve supports, shipping/installatio
    n fixture (to be made of 316 L)

4
US warm-to-cold transition
5
DS warm-to-cold transition
6
Fermilab will Provide
  • To be send to DESY
  • Cleaned US and DS warm-to-cold transitions
    (w/isolation flanges on ends and slight positive
    Ar pressure)
  • Cleaned spool between cavity and VAT valve (also
    capped on ends)
  • Cleaned helium vessel support clamps
  • Cleaned VAT valve supports
  • Shipping/installation fixture
  • Drawing and procedure for assembly with fixture
    to be shipped

7
Fermilab will Provide
  • Currently at Fermilab
  • Vacuum vessel and instrumentation
  • 80 K shielding
  • 5 K manifold
  • Tuner
  • 2 Spare VAT valves

8
Process
  • Send to DESY (May 2005)
  • Cleaned US and DS warm-to-cold transitions and
    spool
  • Under argon positive pressure

valve w/filter
blank flange
9
Process cont
  • 2 helium vessel support clamps

10
Process cont
  • VAT valve supports

11
Process cont
  • Shipping/installation fixture with temporary
    supports for bellows with crate

12
Process cont
  • Work at DESY (May-June 2005)
  • Clean US and DS warm-to-cold transitions
  • Assemble
  • Cavity and helium vessel
  • Spool between VAT valve and cavity
  • VAT valves with supports
  • Warm-to-cold transition
  • Magnet shielding

13
Process cont
  • Send to Fermilab (July 2005)
  • Assembled cavity with VAT valves, shielding,
    spool and transitions

14
Process cont
  • Work at Fermilab (July-August 2005)
  • Pressure test helium vessel
  • Modify helium return
  • Install cavity assembly into vacuum vessel
  • Make up cryogenic connections
  • Test fit feedcan and leak check circuits

15
Process cont
  • Install cavity assembly into vacuum vessel

16
Layout
17
Layout
18
Process cont
  • Make up cryogenic connections
  • Test fit feedcan and leak check circuits
  • Commission Cryo Capture Cavity II

19
Questions and Requests
Need DESY cleaning procedure
Need to confirm critical measurements
20
Schedule