Title: E. Fred Steennis
1THE INTRIGUING BEHAVIOUR OVER TIME OF PD'S FROM
DEFECTS IN MV CABLES AND ACCESSORIES LESSONS
LEARNED WITH SCG, an on-line monitoring system
- E. Fred Steennis
- on behalf of
E.Fred Steennis Netherlands Session 1 Paper
0875
2Content
- how to measure PDs on-line in MV cables
- some results
- lessons learned the intruiging behaviour of
PDs - conclusions
3Content
- how to measure PDs on-line in MV cables
- some results
- lessons learned the intruiging behaviour of
PDs - conclusions
4How to measure PDs on-line
- applied method SCG
- SCG means Smart Cable Guard
5How to measure PDs on-line
- with SCG
- diagnose cables ( 8 km)
- data via internet to KEMA server, 1 h updates
- customers have accessto their PD plots
- KEMA experts recom-mend on action if needed
6Content
- how to measure PDs on-line in MV cables
- some results
- lessons learned the intruiging behaviour of
PDs - conclusions
7Some results
4 days
PILC of 666 m with water at 396 m
8Some results
3 weeks
XLPE cable of 4.3 km with joint at 1678 m
9Some results
gt 4 weeks
XLPE cable of 7 km with various weak spots
10Some results
top view
3 months
PILC of 2.2 km with liquid filled joint at 1794 m
11Content
- how to measure PDs on-line in MV cables
- some results
- lessons learned the intruiging behaviour of
PDs - conclusions
12Lessons learned PDs are intruiging
- How effective is SCG?
- 4 years SCG
- 158 km cable monitored
- 41 defects found
- in 7 cases (17 ) no PD at all
- in 34 cases (83 ) clear PD activity and time
to act - SCG is effective in warning for upcoming failures
13Lessons learned PDs are intruiging
- SCG . . . . how much time for repair?
14Lessons learned PDs are intruiging
- SCG . . . . how much time for repair?
- water in PILC
- joints with hot conductor
- screen interruption in XLPE
- liquid filled joints in PILC
15Lessons learned PDs are intruiging
- SCG . . . . how much time for repair?
- water in PILC days )
- joints with hot conductor
- screen interruption in XLPE
- liquid filled joints in PILC
- ) between start of heavy PD activity and failure
16Lessons learned PDs are intruiging
- SCG . . . . how much time for repair?
- water in PILC days )
- joints with hot conductor days )
- screen interruption in XLPE
- liquid filled joints in PILC
- ) between start of heavy PD activity and failure
17Lessons learned PDs are intruiging
- SCG . . . . how much time for repair?
- water in PILC days )
- joints with hot conductor days )
- screen interruption in XLPE weeks )
- liquid filled joints in PILC
- ) between start of heavy PD activity and failure
18Lessons learned PDs are intruiging
- SCG . . . . how much time for repair?
- water in PILC days )
- joints with hot conductor days )
- screen interruption in XLPE weeks )
- liquid filled joints in PILC months - years )
- ) between start of heavy PD activity and failure
19Content
- how to measure PDs on-line in MV cables
- some results
- lessons learned the intruiging behaviour of
PDs - conclusions
20Conclusions
- SCG can diagnose PILC, XLPE or mix
- up to 8 km, with 1 length accuracy
- exp. so far 4 years 158 km monitored
- effective to see defects on time 83 !
- PDs from many types of defects only visible for
a few days before the failure, in others cases
there is (much) more time - SCG most effective if monitoring over longer time