Southern African Large Telescope Prime Focus Imaging Spectrograph Management, Schedule, & Budget Jeffrey W Percival Kenneth H Nordsieck University of Wisconsin - Madison – PowerPoint PPT presentation

Number of Views:81
Avg rating:3.0/5.0
Slides: 12
Provided by: KennethN4
Learn more at: http://www.sal.wisc.edu
Category:

less

Transcript and Presenter's Notes

Title: SALT PFIS Preliminary Design Review


1
Southern African Large TelescopePrime Focus
Imaging Spectrograph
  • Management, Schedule, Budget
  • Jeffrey W Percival
  • Kenneth H Nordsieck
  • University of Wisconsin - Madison

2
PFIS Organization Chart
  • All team members in place
  • PFIS PI
  • Director of Space Astronomy Laboratory
  • Professor of Astronomy
  • Reports to the Chairperson of the UW Dept. of
    Astronomy

3
Management Details
  • Quarterly reports, including schedule budget
  • Monthly status reports posted to web site within
    5 working days after end of month
  • Document numbering use SALT standard
  • File formats various, according to need.
    AutoCAD, Word, Excel, STEP, IGES, etc. PDF for
    publishing.
  • Schedule management Microsoft Project
  • Budget management
  • MS Project for big picture, estimated cost to
    complete
  • Excel for detailed budgeting and accounting

4
Interface Management
  • Three interfaces Rutgers, SAAO, SALT.
  • Governed by Statements of Work and ICDs
  • Finalize SOWs and ICDs at CDR
  • Interface changes categorized
  • Refinement of detail, all parties in agreement
  • Modification of interface, no effect on
    performance, cost, or schedule
  • Modification, affects performance, cost, and/or
    schedule
  • 3rd category of change involves SALT Project
    Scientist

5
Quality Assurance
  • SAL has extensive experience in building
    spaceflight hardware
  • Wisconsin Ultraviolet Photo-Polarimeter
    Experiment
  • Hubble Space Telescope High Speed Photometer
  • Sounding Rocket Payloads
  • Star Trackers
  • Will apply this experience to PFIS
  • Ruggedized manufacture
  • Multi-level testing (component, subsystem,
    system)

6
Contingency Management
  • Procurement contingency 15 for all purchased
    items
  • Budget Contingency 6 months of labor (3 for
    Critical Design, 3 for Fabrication Test)
  • Schedule Contingency very tight (risk)
  • Critical path items
  • Slips in design and fabrication
  • Delivery of Detector Subsystem
  • Timely access to the telescope
  • Earliest possible notification of problems,
    between all affected parties, is essential
  • Cross-institutional impacts on cost schedule...

7
Schedule Approach
  • 5 Sequential phases
  • Concept Design
  • Preliminary Design
  • Critical Design
  • Fabrication and Test
  • Delivery and Installation
  • 4 parallel efforts
  • Long Lead Optics
  • Slit Mask Factory
  • Etalon Assemblies
  • Detector Subsystem

8
Budget Approach
  • Some people (ME, IS, PM) assigned at 100 for
    duration of summary tasks
  • Effort-driven work (Mechanical Designer,
    Machinist) assigned per task
  • Design and fabrication estimates (both labor and
    materials) taken from detailed analysis by Swales
    Aerospace.
  • UW charges
  • 45.5 for overhead
  • 33 for fringe benefits on labor expenses
  • 0 for capital equipment (optics, electronics)

9
Management Controls
  • Vigilant oversight as work proceeds
  • For each task, compare degree of completion with
    expended resources red flag for tasks that fall
    off the curve
  • Frequently re-estimate cost to complete, and
    compare with remaining resources

10
Schedule (page 1/2)
11
Schedule (page 2/2)