Title: SOUTHERN AFRICAN POWER POOL
1SOUTHERN AFRICAN POWER POOL SAPP REPORT TO 5TH
COORDINATION MEETING OF POWER POOLS IN
AFRICA Harare, ZIMBABWE 6-7 May 2010
2CONTENTS
- Installed and Available Capacity
- Commissioned Projects in 2009
- Planning for 2010
- Rehabilitation New Projects
- SAPP Mandate
- SAPP challenges
3- INSTALLED AVAILABLE CAPACITY
4- SADC region currently has an available capacity
equivalent to 48,849 MW. - This gives annual shortfall of 1,248MW for 2010.
- Power shortfall will persist until 2013 provided
that - Generation projects under construction are
completed and commissioned as planned.
5- COMMISSIONED PROJECTS IN 2009
- Planned supply in 2010 will be coming at a time
when Southern Africa will be hosting the 2010
FIFA World Cup - SAPP is adequately prepared and will provide a
dependable reliable supply to the event.
6- PLANNING FOR 2010
A total of 933 MW expected in 2010 Target is
2,200 MW
7- REHABILITATION NEW PROJECTS
8Planned Generation Projects 2011
9Planned Generation Projects 2012
10Planned Generation Projects 2013
11Planned Generation Projects 2014
12Planned Generation Projects 2015
13Rehabilitation New Generation Projects, MW
14New Generation Projects - Technologies
15 Completed Interconnections (1)
- Since 1995, the following transmission lines
have been commissioned by the SAPP - The 400kV Matimba-Insukamini Interconnector
linking Eskom of South Africa and ZESA of
Zimbabwe in 1995. - The 400kV Interconnector between Mozambique and
Zimbabwe was commissioned in 1997. - BPC Phokoje substation was tapped into the
Matimba line to allow for Botswanas tapping into
the SAPP grid at 400kV in 1998.
16 Completed Interconnections (2)
- Restoration of the 533kV DC lines between Cahora
Bassa in Mozambique and Apollo substation in
South Africa was completed in 1998. - 400kV line between Camden in South Africa via
Edwaleni in Swaziland to Maputo in Mozambique in
2000. - 400kV line between Arnot in South Africa and
Maputo in Mozambique in 2001. - 400kV line between Aggeneis in South Africa and
Kookerboom in Namibia in 2001. - 220kV line from Zambia to Namibia in 2007.
17ZAMBIA TANZANIA KENYA INTERCONNECTOR
- Priority Interconnector Project for SAPP
- Project to bring regional diversity in resources
- Project to transmit power in both directions in
future - Time difference of East and Southern Africa an
advantage for power exchanges - Project to interconnect SAPP and EAPP.
- Project is part of regional integration
18ZAMBIA TANZANIA KENYA INTERCONNECTOR - STATUS
- Power supply options supplied by SAPP especially
from Zambia - Power Purchase Agreements and electricity tariff
structure needs to be agreed - Consideration for 400 kV AC and or HVDC
interconnection options
19ZAMBIA TANZANIA KENYA INTERCONNECTOR - STATUS
- Project Management Unit (PMU) to be set up by 3
Governments - Feasibility studies being updated
- Transaction Advisor appointed
- Financial closure Sept 2011
- Target commissioning 2014
20Transmission Projects
Kenya
DRC
2010 -2011 ZIZABONA -220/330 kV
Tanzania
2012 Mozambique Malawi
2014 Z -T T- K - 400 kV
Malawi
Angola
Zambia
2015DRC - Angola 400 kV
Zimbabwe
Namibia
2015 MOZAMBIQUE BACKBONE -RSA
Mozambique
Botswana
2015-2025 765 kV Strengthening
Swaziland
2015 RSA Strengthening
Lesotho
South Africa
2015 Botswana Strengthening
21INTERCONNECTING POWER POOLS IN AFRICA
BURKINA FASO
POWER POOLS IN AFRICA
22COORDINATION CENTRE STRUCTURE
Current establishment (9 out of 12)
23SAPP COORDINATION CENTRE ACTIVITIES
- Advisory, surveillance and monitoring role
- Central function for DAM trading and wheeling and
loss charges calculation - Mandatory to use SAPP CC figures
- Invoicing done by CC for DAM
- Wheeling settled bilaterally
- Promote projects on behalf of Members.
- Seek project preparatory funds for Members
24SAPP MANDATE
- To fulfil SAPP Mission and Objectives set by the
Board. - To facilitate the development of a competitive
electricity market.
25SAPP CHALLENGES
- Shortage of generation surplus capacity in SADC
- Electricity reforms in most countries
- Promotion of independent country plans instead of
regional coordinated plans. - Regional Project Implementation
- Policy and Legislation differs between SAPP
countries - Harmonisation of regulatory rules
- Skills retention
26Thank You