Title: Electron Beam Systems ETC and Methodology


1
Electron Beam SystemsETC and Methodology
David Schultz E-Beams Systems Manager
  • Electron Beam Systems
  • Definition of terms
  • Schedule Overview
  • Start-Up Test Plan
  • E-Beams Costs
  • Risk Analysis

2
E-Beams Systems layout
Sector 21
Sector 20
Laser lab
BC1
LX
L1
Injector
Injector Commissioning complete
3
The electron gun in the Injector
Laser beam transport
Electron gun
4
E-Beams Systems layout
6 MeV
250 MeV
4.30 GeV
13.6 GeV
135 MeV
Linac-X L 0.6 m
Linac-0 L 6 m
rf gun
Linac-1 L ?9 m
Linac-2 L ?330 m
Linac-3 L ?550 m
Commissioned
Now Installing
...existing linac
undulator L 130 m
X
BC2 L ?22 m
BC1 L ?6 m
LTU L 275 m
L2/BC2/L3
Injector/BC1
SLAC linac tunnel
research yard
5
E-Beams Systems layout
Beam Transport Hall Transport the electron beam
to the Undulator
Undulator Hall Underground tunnel housing the
undulator.
Controls Beamline and diagnostics control for
e-beams systems.
SLAC Linac LCLS uses the last 1/3 of the
existing Linac.
Electron Beam Dump Underground facility for the
beam dump.
Near and Far Halls Areas for x-ray experiments
6
E-Beams Systems WBS structure
  • Injector WBS 1.02, 2.02
  • Jose Chan, Control Account Manager
  • Laser/Gun/L0/Spectrometer
  • Installed and commissioned
  • Create electrons, accelerate, analyze beam quality
  • Laser Heater
  • Accelerator RD activity

7
E-Beams Systems WBS structure
  • Linac WBS 1.03, 2.03
  • Jose Chan, CAM
  • L1/Lx/BC1 Installed and commissioned
  • Accelerate the beam,
  • initial beam bunch compression
  • L2/BC2/L3
  • Full beam acceleration,
  • second compression of bunch
  • LTU
  • Transport electron beam from Linac to Undulator
  • Electron dump
  • Safely dispose of the electron beam

8
E-Beams Systems WBS structure
  • Undulator WBS 1.04, 2.04
  • Generate x-rays as the high power electron beam
    passes through.
  • Undulator Systems at ANL, Geoff Pile, CAM
  • Fabricate components and supports for the
    Undulator system
  • Undulator Integration at SLAC, Rodd Pope, CAM
  • Tune, fiducialize, assemble, and install the
    Undulator system

9
E-Beams Systems WBS structure
  • Accelerator Controls WBS 1.02.02, 2.02.02,
  • 1.03.02, 2.03.02, 1.04.02,
    2.04.02
  • Hamid Shoaee, CAM
  • Controlling hardware, cable plant and software
    for Injector, Linac and Undulator Systems
  • Commissioning WBS 2.01.01, 2.02.17,
  • 2.03.07, 2.04.06
  • David Schultz, CAM
  • LOE manpower for LCLS personnel and maintenance
    groups during the electron beam commissioning
    process.

10
System Design Management
  • System engineering resource loaded schedule is
    controlled through P3.
  • Design process
  • Interface Control Documents specify which group
    has responsibility for each system.
  • Physics Requirements Documents are written by the
    LCLS Physics group specifying subsystem needs.
  • Engineering group holds Design Reviews, and
    writes Engineering Specification Documents to
    detail how the PRD is to be satisfied.
  • Physicists and Engineers sign-off on component
    assembly and testing prior to installation.

11
E-Beams Systems Level 3 Milestones
L3 milestones sufficient and properly distributed
to monitor performance.
12
E-Beams Systems Level 3 Milestones
13
LCLS Installation and Commissioning Time-Line
X-ray tunnel/FEH Install
LTU/Und/Dump Install
FEH X-rays milestone
Flux milestone
CF Early Occupancy
CD-4 (7/30/10)
FEE/NEH Install
S
O
N
D
J
F
M
A
M
J
J
A
S
O
N
D
J
F
M
A
M
J
J
A
S
O
N
D
J
F
M
A
M
2007
2008
2009
2010
PPS
PPS
LTU/Und Commissioning
Tunnel/FEH Commissioning
Linac/BC2 Commissioning
Linac/BC2 Install
FEE/NEH Commissioning
14
Start Up Test Planning
  • LCLS Safety Assessment Document is due 7/2008
  • LCLS Accelerator Readiness Review is needed
    10/2008
  • Systems installed, checked out, signed off by
    responsible parties.
  • Safety officers signoffs on approvals and
    installations.
  • Safety specific systems (Personnel Protection)
    certified.
  • Maintenance groups have procedures and training
    in place.
  • Procedures in place for Operations, and Operators
    trained.
  • Beam Authorization Sheet prepared.
  • Detailed commissioning schedule and performance
    goals are produced by the LCLS Physics group.
  • Approval to begin commissioning given by the
    Directors office

15
E-Beams Systems Cost Estimation
  • As installation is approaching, systems are well
    defined.
  • Installation costs
  • Based on experience in 2006 Injector
    installation.
  • Hardware install estimate done top-down and
    bottom-up.
  • Based on experience on undulator prototype at
    ANL.
  • Cable plant install estimated using R.S. Means.
  • Fabrication/procurement
  • Costs based on quotes and experience with
    prototypes at SLAC and ANL.
  • Engineering and Commissioning
  • Timetable for completion well understood.

16
Risk Assessment
  • Design maturity and cost/schedule exposure are
    used in the contingency analysis for all DCE
    activities.
  • Major risks are identified as Risk Registry
    entries, and assessed and maintained by the
    System Manager.
  • The Senior Management team reviews the Registry
    monthly.
  • Summary of E-Beams Systems entries
  • Linac (2)
  • Risk Linac diagnostics may need to be enhanced
    to have sufficient sensitivity for FEL
    commissioning.
  • Mitigation The upcoming BC2 commissioning will
    determine if an upgrade is warranted.

17
Risk registry
  • Summary of entries (cont.)
  • Undulator (3)
  • The assembly of the Undulator Girders is a
    pacing item for Undulator commissioning.
  • Several components from ANL are close to being
    the limiting factor
  • Risk Any rework or modification of parts at SLAC
    will delay girder assembly.
  • Mitigation We have multiple weekly video
    meetings with ANL and quarterly Undulator
    collaboration meetings to ensure coordination.
  • Integration engineers at ANL and at SLAC have
    been established to coordinate the receipt and
    assembly.

18
Summary
  • Electron Beams Systems are approaching final
    installation.
  • Systems are well defined,
  • Based on Project documentation.
  • Resource loaded schedule in P3.
  • Costs have a solid basis.
  • The start up test plan is based on the successful
    turn-on of the LCLS Injector.
  • Identified risks are being controlled.