Title: Production modules


1
JEM Status and plans
  • Production modules
  • Status
  • Plans

2
JEM1.3 (production)
  • Sum processor XC2V2000
  • Jet processor XC2V3000
  • 4 input modules (IM) v1.1 (XC2V1500, SCAN921260)
  • TTCdec module
  • Control Module (CM) v1.3
  • CAN
  • VME control
  • Fan-out of configuration lines
  • G-link readout module (RM) v1.2

3
From pre-production to production
  • Minor modifications of JEM wrt pre-production
    modules silk screen, pads for CLKdes2
    terminators, reduced bypass capacitance on 3.3V
    supply due to crate supply oscillations
  • 4 pre-production 41 production 45 fully
    functional modules to be used on ATLAS
  • 32 in JEP crates 13 spares !
  • Yield so far
  • 2 defective JEMs found NO BGA issues, just one
    short on connector and one chip mounted in wrong
    orientation
  • 8 input modules with BGA issues (replace?)
  • 7 input modules with minor issues (rework?)
  • small numbers of defective control and G-link
    modules

4
Module production story
  • Many production issues with prototypes and
    pre-production
  • All production steps have taken far longer than
    scheduled, minimum a factor of two
  • Problems were reported only shortly before
    delivery dates, even if they were known for quite
    a while
  • 3 iterations of input module PCB (impedance
    issues and others)
  • 2 iterations of JEM PCB (impedance)
  • Wrong component (SMB voltage sensor) mounted on
    control module
  • Inverted tantalum on control module ? rework
  • Insufficient cleaning and drying of input modules
    leading to malfunction ? rework

5
Acceptance tests (Bruno)
  • Record electronic serial number
  • JTAG B/Scan
  • Input modules
  • Control modules
  • JEM main boards
  • Flash and check CPLDs and CAN controller
  • Basic LVDS link tests lock / no lock to 40MHz
    square

6
System tests, Mainz trigger lab
  • Interface tests only, using counter patterns
    (linear ramp)
  • Error detection mainly in firmware
  • Basically using features built into production
    firmware for timing calibration
  • Interfaces tested
  • LVDS inputs - ramp pattern required for timing
    calibration (PPM!)
  • FIO - pattern detection required for timing
    calibration (not yet included in jet production
    firmware)
  • DAQ and ROI links - software error detection
  • CMM - parity detection, pattern generation (so
    far) in dedicated firmware
  • For details see Markus / Andrea
  • Full system tests with ROD readout at CERN only

7
Plans
  • ship 8 crate-tested JEMs on March 19 to make a
    full crate of JEMs available for system tests at
    CERN
  • continue production tests in Mainz ( 2 weeks)
  • delay further module shipment until crate
    situation at CERN becomes clear
  • full JEP system tests at CERN as soon as
    infrastructure complete
  • Meanwhile cabling, crate issues, firmware,
    software