Title: Application of the Competitive Dialogue in Practice
1Application of the Competitive Dialogue in
Practice
- Glenn Fletcher
- Achilles Information Ltd
The New Public Procurement Procedures and
Instruments Ankara, Turkey 5-6 February 2008
2Issues to be covered
- When should competitive dialogue be used?
- What contracts has it been used for?
- What lessons have been learned so far?
3When should competitive dialogue be used?
- A new procedure intended for contracts so complex
that open and restricted procedures are
impractical - Effectively replaces the negotiated procedure
with a call for competition (which had been used
by UK for public private partnership contracts
which required innovation and risk transfer)
4When should competitive dialogue be used?
- The procurement legislation emphasises the
importance of non-discrimination and the
transparency of procedures and decisions - It therefore regards negotiation with suspicion
and negotiated procedure is relatively rarely
used (represents less than 10 of UK contracts
advertised in the OJ?)
5When should competitive dialogue be used?
- Many large contracts require a degree of dialogue
between contracting authority and supplier - Authorities were therefore perhaps using
negotiated procedures inappropriately or were
negotiating (wrongly) within open or restricted
procedures
6When should competitive dialogue be used?
- The new procedure was designed to allow a degree
of negotiation in these complex contracts - whilst retaining a tendering stage to ensure
that the authoritys discretion was suitably
limited - to ensure non-discrimination
- The procedure is very similar to the best and
final offer approach used for some time in UK
and elsewhere
7When should competitive dialogue be used?
- Where the contracting authority is not able
objectively to define the technical means to meet
its objective (e.g. complex information systems) - Or is not able objectively to specify the
legal/financial make up of the project (e.g.
design build and operate projects) - And where the authority considers that open or
restricted procedures would not allow the award
of the contract
8What contracts has it been used for?
- Major information systems contracts (databases,
back office computer systems, network services) - Public private partnership contracts (where
supplier innovation is required and risk is
transferred to the supplier) (prisons, hospitals,
schools, urban redevelopment schemes)
9What contracts has it been used for statistics
from January 2008 search of OJ database
- Competitive Dialogue contract notices amounted to
1717 of 294849 total contract notices published
in the period (2006-2007) - So far no Competitive Dialogue contract award
notices have been published - Contract notice statistics for selected countries
(2006-2007) - France 670
- UK 658
- Germany 61
- Italy 3
- Ireland 44
- Denmark 21
- Netherlands 33
10What contracts has it been used for sample
contracts
- Admission tests for the selection of students for
undergraduate medical programmes. - Urban regeneration works
- Medical information systems
- Environmental-impact consultancy services
- Insurance services
- Fleet tankers for British Royal Navy
- Design and construction of highway
11What lessons have been learned so far?
- The procedure is unfamiliar to contracting
authorities and suppliers - Thus care must be taken to ensure all understand
the process - There are some aspects of the process that are
unclear in practice - European Commission guidance is only in draft at
present - No relevant European court cases
12What lessons have been learned so far?
- Procurement using the procedure takes
considerable time (1-2 years is not unusual) - This partly reflects the nature of the (very
large) projects involved - Costs of preparing tenders can be very high
- Some suppliers consider costs are greater using
this procedure than where the negotiated
procedure was used
13What lessons have been learned so far?
- The process is very time and resource intensive
for contracting authorities - Often the necessary technical resource is not
available within the authority - Leading to cost/delays to acquire necessary
consultancy - Meticulous planning at the start of the
procurement process is essential to ensure
success
14What lessons have been learned so far?
- The process is best suited for large, high risk
projects - Where the resource cost to the authority and
suppliers is not disproportionate to the size of
the benefits/profits to the parties - It is not an easy option to compensate for
inadequate thought by authorities about what they
really need
15Conclusions
- Competitive Dialogue has aroused great interest
amongst contracting authorities - There is little experience so far with this new
procedure but it is often used for projects in
substitution for the negotiated procedure with a
call for competition - Authorities have welcomed the fact that use of
the procedure is relatively easy to justify - Careful planning and the deployment of adequate
resources is essential to the successful
operation of the procedure