Field Period Assembly - PowerPoint PPT Presentation

About This Presentation
Title:

Field Period Assembly

Description:

Has adequate training ... disassembled into two 3-packs for installation over the VV Modular coils installed over VV in Station 3 The use of the overhead crane ... – PowerPoint PPT presentation

Number of Views:110
Avg rating:3.0/5.0
Slides: 14
Provided by: reiersen
Learn more at: https://ncsx.pppl.gov
Category:

less

Transcript and Presenter's Notes

Title: Field Period Assembly


1
Field Period Assembly
Wayne Reiersen SC Project Review PPPL May 2006
2
Preparations for FPA have been going well
  • FPA processes have been defined in the MIT/QA
    Plan
  • Magnetic alignment of coils into field periods
    has been adopted
  • Facility-level planning and safety documentation
    is in place
  • Manufacturing Facility Operations Plan updated to
    include FPA activities
  • Project Hazard Analysis approved by the PPPL
    Safety Review Committee
  • The firs VVSA has arrived
  • We are ready for the ACC review of Station 1
  • MIT/QA Plan is being signed
  • Receipt inspection and assembly procedures
    written
  • Turning fixtures fabricated
  • Preparations for subsequent stations are on track

3
Field period assembly process
4
Turning fixtures fabricated for Station 1
  • Two turning fixtures fabricated to allow parallel
    operations
  • Provide easy access for installation of components

A ratchet locking system has been added to
enhance safety
5
Assembly procedure written for Station 1
  • Magnetic loops (65-80 flux loops, 4 toroidal
    loops), coolant lines (64), heater tapes, and
    thermocouples will be installed

6
Modular coils assembled into 3-packs in Station
2a
  • The coils will be positioned based on inspection
    data using three adjustable spherical seats
  • Custom shims will be placed between the flanges
  • Coils will be secured with insulated bolts

Adjustable support stand
Type-C assembly being lowered in place
Completed half-period assembly
7
6-pack completed using magnetic alignmentin
Station 2b
  • Second support fixture allows assembly of the
    mating half-period using magnetic alignment
  • Magnetic alignment involves nulling symmetric
    differences in mutual inductances
  • Requires an array of pick-up coils symmetrically
    placed about the symmetry plane
  • Reduces the risk of unacceptable field errors
    relative to using physical measurements alone
  • 6-pack disassembled into two 3-packs for
    installation over the VV

Fiberglass tube with 20 wire loops on each side
of the parting plane.
Symmetric alignment of Type A coils
8
Modular coils installed over VV in Station 3
  • The use of the overhead crane for rotating the
    modular coils over the VV described at previous
    SC review
  • After installation with overhead crane, modular
    coils are supported by a rolling ground support
    system
  • The interfacing Type-A flanges are then shimmed
    and bolted together into a full field period and
    VV support hardware installed

9
TF coils are assembled into 3-packs in Station 4
  • TF coils wedged together in an accurately
    machined fixture
  • TF coils retracted slightly in the radial
    direction (1/4 in) to provide clearance during
    the final machine assembly
  • Temporary structures are needed for upper and
    lower structure for TF half-period assembly and
    final field period assembly

10
Final field period assembly in Station 5
  • Two stations planned for final field period
    assembly provide schedule robustness
  • Assembly sequence
  • Weld ports on MC/VVSA subassembly
  • Rotate TF coil half-period assemblies into
    position
  • Install external trim coils
  • Install temporary blocking around vacuum vessel
    to inhibit movement during transport
  • Completed field periods transported to the NCSX
    Test Cell at C-site for final assembly

Ports welded on
TF coils rotated into position
Completed field period
11
Station 1 is ready for the ACC review
  • The MIT/QA Plan is out for signature - it
    provides
  • A description of the FPA sequence including a
    process outline
  • A description of each station including tooling
    and fixtures
  • A listing of specifications (which identify
    applicable drawings and models, define
    requirements, and verifications) for each station
  • A listing of procedures and documentation
    requirements for each station
  • The procedure for material receipt and
    verification is approved
  • The assembly procedure for installing the
    magnetic diagnostics, coolant tubes, heater
    tapes, and thermocouples has been drafted
  • Installation of the flux loops has been
    prototyped on the PVVS
  • Hoisting and rigging will be performed per PPPLs
    Hoisting and Rigging Program (ENG-021)
  • Two turning fixtures have been fabricated
  • The first VVSA has arrived

12
Preparations for other stations are on track
  • Tooling is being designed for Stations 2 and 3
  • Models have been completed for tooling required
    on Stations 2 and 3
  • A magnetic alignment system is being designed for
    assembling modular coils into 6-packs
  • The design of the coil-to-coil interface hardware
    (a WBS 14 activity) is also planned for this FY
  • Detailed design of tooling for Stations 4 and 5
    will begin after design activities on Stations 2
    and 3 are completed

13
Next steps
  • ACC will review readiness of Station 1 for
    operation and provide a report which addresses
    the charge questions
  • Have the facility hazards for the work on Station
    1 been appropriately identified, e.g. in the
    Manufacturing Facility PHA?
  • Have appropriate safety controls, e.g. those
    identified in the identified in the Manufacturing
    Facility Operations Plan, been implemented for
    the work on Station 1? 
  • Has personnel safety been adequately addressed in
    the design of the turning fixture?
  • Has adequate training been provided (or planned
    to be provided in a timely manner) for the work
    to be conducted safely?
  • NCSX will respond to any issues raised by ACC
  • When issues have been resolved to the
    satisfaction of the Project Manager (Neilson) and
    RLM (Dudek), the RLM will provide authorization
    to the ATI (Viola) to commence operations on
    Station 1
Write a Comment
User Comments (0)
About PowerShow.com