Referee Report for OLYMPUS - PowerPoint PPT Presentation

About This Presentation
Title:

Referee Report for OLYMPUS

Description:

Referee Report for OLYMPUS Elke Aschenauer / Naohito Saito Observation The collaboration has worked out the installation scenario with DESY local group. – PowerPoint PPT presentation

Number of Views:39
Avg rating:3.0/5.0
Slides: 4
Provided by: 33996
Learn more at: http://web.mit.edu
Category:

less

Transcript and Presenter's Notes

Title: Referee Report for OLYMPUS


1
Referee Report for OLYMPUS
  • Elke Aschenauer / Naohito Saito

2
Observation
  • The collaboration has worked out the installation
    scenario with DESY local group.
  • The collaboration also established a first draft
    of commissioning and data taking schedule.
  • Funding from the US side is critical to start the
    experiment still under discussion
  • Expect feedback soon (today?)
  • Funding proposal in Germany involving three
    Universities may not go through
  • 235 k Euro for trigger and DAQ PD positions
  • Funding Source(s) for followings are not
    identified
  • New intersection 280 k Euro
  • DORIS modification 500 k Euro
  • DORIS ops 450k Euro
  • OLYMPUS ops 600 k Euro

3
Recommendation
  • Collaboration is encouraged
  • to further explore the technical aspects of the
    experiment
  • Critical review of the installation process with
    a possible backup plans
  • Commissioning strategy robust enough for timely
    completion
  • to identify DEDICATED Person-Power
  • Critical for the experiment with limited time
    window
  • to actively search for funding possibilities
  • Another review might be necessary before summer
    with the input from the all funding
    possibilities, especially the ones from the US ?
    drop dead date of the project
  • May need labs help to support this kind of small
    experiments, not included in the five year plan
Write a Comment
User Comments (0)
About PowerShow.com