high_voltage_direct_current

About This Presentation
Title:

high_voltage_direct_current

Description:

Wind turbines operating at variable speed generate power at different ... Photovoltaic cells also produce electricity as DC, ... ( breakers, disconnectors ... –

Number of Views:436
Avg rating:3.0/5.0
Slides: 49
Provided by: egto
Category:

less

Transcript and Presenter's Notes

Title: high_voltage_direct_current


1
High Voltage Direct Current
(HVDC)Transmission Systems An Overview.
2
  • What is HVDC?
  • HVDC stands for High Voltage Direct Current and
    is today a well-proven technology employed for
    power transmission all over the world. In total
    about 70,000 MW HVDC transmission capacity is
    installed in more than 90 projects.
  • The HVDC technology is used to transmit
    electricity over long distances by overhead
    transmission lines or submarine cables.
  • It is also used to interconnect separate power
    systems, where traditional alternating current
    (AC) connections can not be used.
  • There are three different categories of HVDC
    transmissions 1. Point to point
    transmissions2. Back-to-back stations3.
    Multi-terminal systems

3
  • The development of the HVDC technology started in
    the late 1920s, and only after some 25 years of
    extensive development and pioneering work the
    first commercially operating scheme was
    commissioned in 1954.
  • This was a link between the Swedish mainland and
    the island of Gotland in the Baltic sea.
  • The power rating was 20 MW and the transmission
    voltage 100 kV.
  • At that time mercury arc valves were used for the
    conversion between AC and DC, and the control
    equipment was using vacuum tubes.
  • A significant improvement of the HVDC Technology
    came around 1970 when thyristor valves were
    introduced in place of the mercury arc valves.
    This reduced the size and complexity of HVDC
    converter stations substantially.
  • The use of microcomputers in the control
    equipment in today's transmissions has also
    contributed to making HVDC the powerful
    alternative in power transmission that it is
    today.

4
  • Historical Perspective on HVDC Transmission
  • The first commercial electricity generated (by
    Thomas Alva Edison) was direct current (DC)
    electrical power.
  • The first electricity transmission systems were
    also DC systems.
  • However, DC power at low voltage could not be
    transmitted over long distances, thus giving rise
    to high voltage alternating current (AC)
    electrical systems.
  • Nevertheless, with the development of high
    voltage valves, it was possible to once again
    transmit DC power at high voltages and over long
    distances, giving rise to HVDC transmission
    systems.
  • Important Milestones in the Development of HVDC
    technology
  • Hewitts mercury-vapour rectifier, which appeared
    in 1901.
  • Experiments with thyratrons in America and
    mercury arc valves in Europe before 1940.
  • First commercial HVDC transmission, Gotland 1 in
    Sweden in 1954.
  • First solid state semiconductor valves in 1970.
  • First microcomputer based control equipment for
    HVDC in 1979.
  • Highest DC transmission voltage (/- 600 kV) in
    Itaipú, Brazil, 1984.
  • First active DC filters for outstanding filtering
    performance in 1994.
  • First Capacitor Commutated Converter (CCC) in
    Argentina-Brazil interconnection, 1998
  • First Voltage Source Converter for transmission
    in Gotland, Sweden ,1999

5
  • The Classic HVDC Transmission
  • Using HVDC to interconnect two points in a power
    grid, in many cases is the best economic
    alternative, and furthermore it has excellent
    environmental benefits.
  • The HVDC technology (High Voltage Direct Current)
    is used to transmit electricity over long
    distances by overhead transmission lines or
    submarine cables.
  • It is also used to interconnect separate power
    systems, where traditional alternating current
    (AC) connections can not be used.
  • In a high voltage direct current (HVDC) system,
    electric power is taken from one point in a
    three-phase AC network, converted to DC in a
    converter station, transmitted to the receiving
    point by an overhead line or cable and then
    converted back to AC in another converter station
    and injected into the receiving AC network.
  • Typically, an HVDC transmission has a rated power
    of more than 100 MW and many are in the 1,000 -
    3,000 MW range.

6
Aerial overview of the 3000MW HVDC converter
station at Longquan, China( Three
Gorges-Changzhou HVDC transmission)
  • HVDC transmissions are used for transmission of
    power over long or very long distances, because
    it then becomes economically attractive over
    conventional AC lines.
  • With an HVDC system, the power flow can be
    controlled rapidly and accurately as to both the
    power level and the direction. This possibility
    is often used in order to improve the performance
    and efficiency of the connected AC networks.

7
Why HVDC? Its Advantages Power stations
generate alternating current, AC, and the power
delivered to the consumers is in the form of AC.
Why then is it sometimes more suitable to use
direct current, HVDC, for transmitting electric
power? The vast majority of electric power
transmissions use three-phase alternating
current. The reasons behind a choice of HVDC
instead of AC to transmit power in a specific
case are often numerous and complex. Each
individual transmission project will display its
own set of reasons justifying the choice of HVDC,
but the most common arguments favoring HVDC are
1. Lower investment cost2. Long distance water
crossing3. Lower losses4. Asynchronous
interconnections5. Controllability6. Limit
short circuit currents7. Environment
8
  • In general terms the different reasons/ADVANTAGES
    for using HVDC can be divided in two main groups,
    namely
  • HVDC is necessary or desirable from the technical
    point of view (i.e. controllability).
  • HVDC results in a lower total investment
    (including lower losses) and/or is
    environmentally superior.

The Baltic Cable HVDC Link, Overview of Herrenwyk
station
9
  • 1) HVDC transmission for lower investment cost.
  • A HVDC transmission line costs less than an AC
    line for the same transmission capacity. However,
    the terminal stations are more expensive in the
    HVDC case due to the fact that they must perform
    the conversion from AC to DC and vice versa. But
    above a certain distance, the so called
    "break-even distance", the HVDC alternative will
    always give the lowest cost.
  • The break-even-distance is much smaller for
    submarine cables (typically about 50 km) than for
    an overhead line transmission. The distance
    depends on several factors (both for lines and
    cables) and an analysis must be made for each
    individual case.
  • The importance of the break-even-distance concept
    should not be over-stressed, since several other
    factors, such as controllability, are important
    in the selection between AC or HVDC.

10
Typical investment costs for an overhead line
transmission with AC and HVDC.
11
Relative Cost of AC versus DC
  • For equivalent transmission capacity, a DC line
    has lower construction costs than an AC line
  • A double HVAC three-phase circuit with 6
    conductors is needed to get the reliability of a
    two-pole DC link.
  • DC requires less insulation ceteris paribus.
  • For the same conductor, DC losses are less, so
    other costs, and generally final losses too, can
    be reduced.
  • An optimized DC link has smaller towers than an
    optimized AC link of equal capacity.

12
Typical tower structures and rights-of-way for
alternative transmission systems of 2,000 MW
capacity.
Source Arrillaga (1998)
13
AC versus DC (continued)
  • Right-of-way for an AC Line designed to carry
    2,000 MW is more than 70 wider than the
    right-of-way for a DC line of equivalent
    capacity.
  • This is particularly important where land is
    expensive or permitting is a problem.
  • HVDC light is now also transmitted via
    underground cable the recently commissioned
    Murray-Link in Australia is 200 MW over 177 km.
  • Can reduce land and environmental costs, but is
    more expensive per km than overhead line.

14
AC versus DC (continued)
  • Above costs are on a per km basis. The remaining
    costs also differ
  • The need to convert to and from AC implies the
    terminal stations for a DC line cost more.
  • There are extra losses in DC/AC conversion
    relative to AC voltage transformation.
  • Operation and maintenance costs are lower for an
    optimized HVDC than for an equal capacity
    optimized AC system.

15
AC versus DC (continued)
  • The cost advantage of HVDC increases with the
    length, but decreases with the capacity, of a
    link.
  • For both AC and DC, design characteristics
    trade-off fixed and variable costs, but losses
    are lower on the optimized DC link.
  • The time profile of use of the link affects the
    cost of losses, since the MC of electricity
    fluctuates.
  • Interest rates also affect the trade-off between
    capital and operating costs.

16
Increased Benefits of Long-Distance Transmission
  • Long distance transmission increases competition
    in new wholesale electricity markets.
  • Long distance electricity trade, including across
    nations, allows arbitrage of price differences.
  • Contractual provision of transmission services
    demands more stable networks.
  • Bi-directional power transfers, often needed in
    new electricity markets, can be accommodated at
    lower cost using HVDC

17
2) HVDC cable transmissions for long distance
water crossing. There are no technical limits
for the length of a HVDC cable. In a long AC
cable transmission, the reactive power flow due
to the large cable capacitance will limit the
maximum possible transmission distance. With HVDC
there is no such limitation, why, for long cable
links, HVDC is the only viable technical
alternative. The 580 kilometer-long NorNed link
will be the longest underwater high-voltage cable
in the world in 2007 and thereby surpassing the
present longest, the Baltic Cable transmission
between Sweden and Germany with its 250 km.
18
  • 3)HVDC transmission has lower losses.
  • HVDC transmission losses come out lower than the
    AC losses in practically all cases.
  • An optimized HVDC transmission line has lower
    losses than AC lines for the same power capacity.
  • The losses in the converter stations have of
    course to be added, but since they are only about
    0.6 of the transmitted power in each station,
    the total HVDC transmission losses come out lower
    than the AC losses in practically all cases.
  • HVDC cables also have lower losses than AC
    cables.

An optimized DC line has lower
losses than an AC line
19
Comparison of the losses for overhead line
transmissions of 1200 MW with AC and HVDC.
20
4)HVDC link for asynchronous interconnections
Many HVDC links interconnect incompatible AC
systems
  • Several HVDC links interconnect AC systems that
    are not running in synchronism with each other.
  • For example the Nordel power system in
    Scandinavia is not synchronous with the UCTE grid
    in western continental Europe even though the
    nominal frequencies are the same. And the power
    system of eastern USA is not synchronous with
    that of western USA.
  • The reason for this is that it is sometimes
    difficult or impossible to connect two AC
    networks due to stability reasons. In such cases
    HVDC is the only way to make an exchange of power
    between the two networks possible. There are also
    HVDC links between networks with different
    nominal frequencies (50 and 60 Hz) in Japan and
    South America.
  • For smaller asynchronous interconnections HVDC
    Light is the proper choice.
  • A HVDC link can be a firewall against cascading
    disturbances

21
  • 5) HVDC transmission for controllability of power
    flow.
  • Controllability One of the fundamental
    advantages with HVDC is that it is very easy to
    control the active power in the link.
  • In the majority of HVDC projects, the main
    control is based on a constant power transfer.
    This property of HVDC has become more important
    in recent years as the margins in the networks
    have become smaller and as a result of
    deregulation in many countries.
  • An HVDC link can never become overloaded!
  • In many cases the HVDC link can also be used to
    improve the AC system performance by means of
    additional control facilities.
  • Normally these controls are activated
    automatically when certain criteria are
    fulfilled. Such automatic control functions could
    be constant frequency control, redistribution of
    the power flow in the AC network, damping of
    power swings in the AC networks etc.
  • In many cases such additional control functions
    can make it possible to increase the safe power
    transmission capability of AC transmission lines
    where stability is a limitation.
  • Today's advanced semi-conductor technology,
    utilized in both power thyristors and
    microprocessors for the control system, has
    created almost unlimited possibilities for the
    control of the HVDC transmission system.
  • Different software programs are used for
    different kind of studies.

22
  • Normally a positive sequence program for example
    ABBs SIMPOW (now transferred to STRI AB) or
    PTIs PSS/E program is used for load-flow and
    stability studies.
  • For more detailed investigations of the
    performance of the inner control loops of the
    converter and its interaction with nearby network
    is simulated in a full three-phase representation
    program such as PSCAD/EMTDC.

PSCAD/EMTDC is used for detailed investigations
of the performance of a HVDC link.
23
Control room with VDU displays and          
 mimic board at Talcher,India.
FennoSkan HVDC Station, Control room, Rauma,
Finland.
24
  • 6)An HVDC transmission limits short circuit
    currents.
  • An HVDC transmission does not contribute to the
    short circuit current of the interconnected AC
    system.
  • When a high power AC transmission is constructed
    from a power plant to a major load center, the
    short circuit current level will increase in the
    receiving system.
  • High short circuit currents is becoming an
    increasingly difficult problem of many large
    cities.
  • They may result in a need to replace existing
    circuit breakers and other equipment if their
    rating is too low.
  • If, however, new generating plants are connected
    to the load center via a DC link , the situation
    will be quite different.
  • The reason is that an HVDC transmission does not
    contribute to the short circuit current of the
    interconnected AC system.

25
  • 7) Environmental benefits
  • Positive effects on the power systems Many HVDC
    transmissions have been built to interconnect
    different power systems by overhead lines or
    cables. By means of these links the existing
    generating plants in the networks more
    effectively so that the building of new power
    stations can be deferred. This makes economic
    sense, but it is also good for the environment.
  • There is an obvious environmental benefit by not
    having to build a new power station, but there
    are even greater environmental gains in the
    operation of the interconnected power system by
    using the available generating plants more
    efficiently.
  • The greatest environmental benefit is obtained by
    linking a system, which has much hydro generation
    to a system with predominantly thermal
    generation. This has the benefit of saving
    thermal generation ( predominately at peak demand
    ) by hydro generation.
  • Also the thermal generation can be run more
    efficiently at constant output and does not have
    to follow the load variations. This can be done
    easily with the hydro generation.

26
  • A DC line can carry more power than an AC line of
    the same size.

The figure above compares two 3,000 MW HVDC lines
(for the Three Gorges - Shanghai transmission,
China) to five 500 kV AC lines that would have
been used if AC transmission had been selected
27
HVDC technology. The conceptual design of the
classic HVDC converter stations of today dates
back from the mid 1970's, when thyristor valves
were taking over in place of the mercury arc
valves. But there has been a dramatic development
in the performance of HVDC equipment and systems.
28
  • A HVDC converter station uses thyristor valves to
    perform the conversion from AC to DC and vice
    versa.
  • The valves are normally arranged as a 12-pulse
    converter.
  • The valves are connected to the AC system by
    means of converter transformers.
  • The valves are normally placed in a building and
    the converter transformers are located just
    outside.
  • The 12-pulse HVDC converter produces current
    harmonics (11th, 13th, 23rd, 25th, 35th, 37th
    etc.) on the AC side.
  • These harmonics are prevented from entering into
    the connected AC network by AC filters, i.e.
    resonant circuits comprising capacitors,
    inductances (reactors) and resistors.
  • The filters also produce a part of the reactive
    power consumed by the converter.
  • The HVDC converter also gives rise to voltage
    harmonics on the DC side (12th, 24th, 36th etc.).
  • A large inductance (smoothing reactor) is always
    installed on the DC side to reduce the ripple in
    the direct current.
  • In addition, a DC filter is also normally needed
    to reduce the level of harmonic currents in the
    DC overhead line.
  • The harmonics may otherwise cause interference to
    telephone circuits in the vicinity of the DC
    line.

29
  • The power transmitted over the HVDC transmission
    is controlled by means of a control system.
  • It adjusts the triggering instants of the
    thyristor valves to obtain the desired
    combination of voltage and current in the DC
    system.
  • Several other apparatus are needed in a converter
    station, such as circuit breakers, current and
    voltage transducers, surge arresters, etc.
  • The conceptual design of the classic HVDC
    converter stations remained unchanged until 1995,
    when ABB introduced HVDC with Capacitor
    Commutated Converters (CCC).

30
Aspects on HVDC Classic performance
1.Reliability and availability 2.Losses
3.Disturbances 4.Fault performance
  • 1.HVDC Classic reliability and availability
  • Transmission configuration
  • The Reliability and availability requirements on
    a particular HVDC transmission are particularly
    high for links supplying major parts of a load
    (e.g. a city or an island) or evacuating a major
    power plant. Where it is essential to have at
    least 50 power if an outage occurs and for large
    size transmissions, a bipolar HVDC transmission
    is the natural choice. For network
    interconnections of moderate size often a
    monopolar configuration is chosen.
  • Bipolar HVDC converter stations are designed such
    that there shall be no risk of having a forced
    outage of both poles at the same time.
  • The most probable type of line fault a ground
    fault due to lightning, affects only one pole.
  • Bipolar HVDC line faults only happens in case of
    a fallen line tower.
  • Since bipolar faults are very rare, one can
    regard a HVDC bipole as being equivalent to a
    double circuit AC line from the reliability point
    of view.

31
  • B. Maintenance Spares.
  • Modern HVDC converter stations require little
    maintenance. Most HVDC stations schedule an
    annual maintenance period at a time when the
    utilization of the transmission is low.
  • For a bipolar link, one pole can be serviced
    while the other pole is live.
  • Maintenance can also be performed on redundant
    equipment, such as ABBs MACH 2TM , when the link
    is in full operation.
  • The majority of equipment in a converter station
    is normal high-voltage and low-voltage equipment
    ( breakers, disconnectors, transformers,
    capacitors, reactors, low-voltage power
    distribution and motor control systems, etc) that
    require normal service.
  • To further reduce the scheduled, and forced,
    outage time a facility for Remote Fault Tracing
    and Maintenance is included where the station can
    be monitored from virtually any remote location.
  • Spares are normally provided based on experience.
  • For some items which are essential for the
    operation and which may cause extensive downtime
    if failure happens, a complete unit is normally
    provided for each station. This is normally the
    case for converter transformers, smoothing
    reactors, wall bushings, instrument transformers,
    filter reactors and resistors, etc

32
  • 2.HVDC Classic transmission losses
  • DC Line
  • An optimized HVDC transmission line has lower
    losses than AC lines for same power capacity.
  • DC cables
  • HVDC cables also have lower losses than AC
    cables.
  • One reason for this is that there is no
    dielectric losses in an DC cable as there are in
    AC cables.
  • Also the full current capacity can be used for
    the power transmission as there is no 50 or 60 Hz
    charging current that causes conductor losses
    without any contribution to the active power.
  • Converter station
  • The losses, in the HVDC Classic converter
    stations amount to about 0.6 - 0.7 of the rated
    HVDC transmission capacity (per station) at rated
    load.
  • The no-load (standby) losses are about 0.1 . The
    main contributors to these losses are the
    converter transformers ( 50 ) and the thyristor
    valves ( 30 ). The rest comes from the AC
    filters, the smoothing reactor, the station
    service power and the DC filter.
  • Loss minimization in AC network
  • If the HVDC link is operated in parallel with AC
    lines, there is a possibility to adjust the power
    on the HVDC link to minimize the total grid
    losses.

33
  • 3.Disturbances in HVDC Classic transmissions
  • The AC/DC conversion process gives rise to
    electromagnetic harmonics of various frequencies.
    These harmonics must be dealt with in order not
    to cause disturbances with communication
    equipment. A converter station also has equipment
    that generates acoustic noise that can be
    disturbing to people in the neighborhood.
  • Telephone interference
  • Frequencies between 100 Hz and up to say 3 kHz,
    i.e. harmonics within the audible range, can
    cause telephone interference to people close to
    the DC and AC lines coming from the converter
    station.
  • The disturbance is then magnetically induced in
    the telephone cable (or wires) running at some
    distance from the high voltage line.
  • In order to prevent this AC filters and DC
    filters that suppresses these frequencies are
    included in the station.
  • Telephone interference from HVDC stations are
    relatively rare.
  • PLC interference
  • If power line carrier communications (in the
    range from 20 - 40 kHz up to about 200 kHz) are
    used in the AC grid (or on the DC line) high
    frequency noise from the HVDC converter might
    cause interference. To prevent this, a PLC filter
    can be installed.

34
  • Radio interference (RI)
  • High frequency noise from the HVDC converter
    might also cause radio interference in the AM
    bands (150 kHz - 30 MHz) in the vicinity of the
    converter station.
  • FM radio, TV and mobile phones occupy higher
    frequencies and are not disturbed.
  • The way to avoid radio interference is proper
    screening of the valve buildings (or outdoor
    valves).
  • In addition small RI-filters are normally
    provided that take care of the RI noise that
    escape from the building via the AC and DC
    bushings.
  • Audible noise
  • The audible noise that a HVDC converter station
    emits to the surroundings comes mainly from the
    converter transformers, the valve cooling fans,
    the smoothing reactors and the AC and DC filters.
  • There are a number of methods to mitigate the
    noise 1) orient disturbing equipment away from
    the most sensitive sound direction, 2) use of low
    noise level equipment, 3) screening or enclosing
    equipment .

35
4.HVDC Classic fault performance
  • DC overhead line faults
  • When a fault (flash-over) occurs on a AC line,
    there are circuit breakers that disconnects the
    line. It is then normally automatically
    re-connected again.
  • There are no DC breakers in the HVDC converter
    stations, so when a fault occurs on a DC line
    another method must be applied.
  • The fault is detected by the DC line fault
    protection. This protection orders the rectifier
    into inverter mode and this discharges the line
    effectively. After some 80 - 100 ms the line is
    charged again by the rectifier. If the fault was
    intermittent, due to e.g. a lightning strike,
    then normally the line can support the voltage
    and the power transmission continues. Full power
    is then resorted in about 200 ms after the fault.
  • But if the fault was due to contaminated line
    insulators there is a risk that re-charging of
    the line results in a second fault.
  • Many HVDC transmissions are designed such that
    after a number of failed restart attempts the
    following attempts are made with reduced voltage
    (80 ).
  • It should be pointed out that the DC line fault
    clearing does not involve any mechanical action
    and therefore is faster than for an AC line.
  • The DC fault current is also lower than the AC
    fault current and therefore the dead time before
    the restart is shorter than for an AC line!
  • The reduced voltage restart is also unique for
    HVDC.

36
  • DC cable faults
  • Cable faults are very rare. They are as a rule
    caused by mechanical damage. Therefore submarine
    DC cables are often buried (except in deep
    waters) to prevent damage from anchors and
    trawls. The same protection action occurs as for
    a DC line but without the restart attempt.
  • AC network faults
  • When a temporary fault occurs in the AC system
    connected to the rectifier, the HVDC transmission
    may suffer a power loss. Even in the case of
    close single-phase faults, the link may transmit
    up to 30 of the pre-fault power. As soon as the
    fault is cleared, power is restored to the
    pre-fault value.
  • When a fault occurs in the AC system connected to
    the inverter, a commutation failure can occur
    interrupting power flow.
  • If the AC-fault is temporary the power is
    restored as soon as the fault is cleared.
  • A distant fault with little effect on the
    converter station voltage (lt 10 percent) does not
    normally lead to a commutation failure.
  • A CCC (Capacitor Commutated Converter) HVDC
    converter can tolerate about twice this voltage
    drop before there is a risk of commutation
    failure.
  • Converter station faults
  • HVDC converter stations are provided with an
    elaborate protection system that is designed to
    detect fault conditions or other abnormal
    conditions that might expose equipment to hazard
    and/or cause unacceptable disturbances. The
    faulty equipment is taken out of service by the
    protection system.

37
Special Applications of HVDC
  • HVDC is particularly suited to undersea
    transmission, where the losses from AC are large.
  • First commercial HVDC link (Gotland 1 Sweden, in
    1954) was an undersea one.
  • Back-to-back converters are used to connect two
    AC systems with different frequencies as in
    Japan or two regions where AC is not
    synchronized as in the US.

38
Special Applications (continued)
  • HVDC links can stabilize AC system frequencies
    and voltages, and help with unplanned outages.
  • A DC link is asynchronous, and the conversion
    stations include frequency control functions.
  • Changing DC power flow rapidly and independently
    of AC flows can help control reactive power.
  • HVDC links designed to carry a maximum load
    cannot be overloaded by outage of parallel AC
    lines.

39
Renewable Energy HVDC
  • HVDC seems particularly suited to many renewable
    energy sources
  • Sources of supply (hydro, geothermal, wind,
    tidal) are often distant from demand centers.
  • Wind turbines operating at variable speed
    generate power at different frequencies,
    requiring conversions to and from DC.
  • Large hydro projects, for example, also often
    supply multiple transmission systems.

40
HVDC Solar Power
  • HVDC would appear to be particularly relevant for
    developing large scale solar electrical power.
  • Major sources are low latitude, and high altitude
    deserts, and these tend to be remote from major
    demand centers.
  • Photovoltaic cells also produce electricity as
    DC, eliminating the need to convert at source.

41
Transcontinental Energy Bridges
  • Siberia has large coal and gas reserves and could
    produce 450-600 billion kWh of hydroelectricity
    annually, 45 of Japanese output in 1995.
  • A 1,800 km 11,000MW HVDC link would enable
    electricity to be exported from Siberia to Japan.
  • Siberia could also be linked to Alaska via HVDC.
  • Zaire could produce 250500 billion kWh of
    hydroelectricity annually to send to Europe
    (5-6,000 km) on a 30-60,000 MW link.
  • Hydroelectric projects on a similar scale have
    been proposed for Canada, China and Brazil.

42
HVDC Installations in the world today
43
New Technologies Needed?
  • For transfers of 5,000 MW over 4,000 km, the
    optimum voltage rises to 1,0001,100 kV.
  • Technological developments in converter stations
    would be required to handle these voltages.
  • Lower line losses would reduce the optimum
    voltage.
  • However, environmentalist opposition and unstable
    international relations may be the biggest
    obstacle to such grandiose schemes.

44
HVDC links in India
45
AC harmonic filter area  at Talcher
Converter transformers of one pole at  Talcher,
in front of the valve hall.
46
(No Transcript)
47
Rihand HVDC station, India
Rihand HVDC station, Valve Hall interior, India
48
Vindhyachal HVDC 2250MW Back to back station,
India
Rihand HVDC station, Control room, India
Write a Comment
User Comments (0)
About PowerShow.com