Title: CONSTRUCTION CONTRACTS DOCUEMENTS
1CONSTRUCTION CONTRACTS DOCUEMENTS
BYLECTURERMaha Muhaisen
- APPLIED CIVIL ENGINEERING DEPT
2Resources
- Construction Documents and Contracting, Joseph D.
Coleman , 2004, Prentice Hall - Construction Contracts, Keith Collier, 1987,
Prentice Hall - Construction Management, by Daniel W. Halpin
and Ronald W. Woodhead, 2nd Edition , John Wiley
Sons - Fidic Conditions of Contract for Construction,
FOR BUILDING AND ENGINEERING WORKS DESIGNED BY
THE EMPLOYER, 2005 - Fidic Tendering Procedures, prequalification,
tendering and award the contract, 1994. - Handouts and lecture notes
3Grades
- Research Projects homework 30
- Midterm Exam. 30
- Final Exam. 40
4Course Outline
- Introduction to construction project stages,
overview of the construction contracting methods,
and contracts types. - Bidding document
- Invitation to bid
- Instruction to bidders
- Information to bidders bid data
- Biding Forms
- General conditions of contract
- Specific condition of contract
- Specification
- BOQ
- Drawings
- Contract forms
- Methods of Tendering, Bidding and Awarding
- Contract Documents and Conditions
- FIDIC Form of Contracts
5- Introduction to Construction Project Stages
- Lecture (1)
6Major Project Phases
- The major phases in the project cycle that are
common to most design and construction projects
are - Project Planning
- Design
- Schematic Design
- Design Development
- Contract Documents
- Construction Procurement (Bidding Phase)
- Construction
- Post Construction
7Construction Project Characteristics
- Construction projects are different than other
types of projects due to the following
characteristics - Construction projects are complex undertaking.
- Every construction project is unique.
- Construction projects involve a lot of
uncertainties, lack of information and variables.
8Project Life Cycle
- Most of Construction projects life-cycle have
common characteristics, Construction projects
start with low cost and resources, high risk and
uncertainty. - The life-cycle of a typical construction project
could be summarized as following - Stage I represents the project formulation,
feasibility studies, and the strategic decisions
needed for project continue. - Stage II represents planning, basic design,
budgeting, tendering and placing the project
major contracts. - Stage III involves the construction phase of
the project, equipment installation and testing. - Stage IV represents the final phase in the
project which includes the project turnover,
final testing and start-up.
9Project Life Cycle
10(No Transcript)
11 12Construction Contracting Method (delivery
methods)
- Traditional Approach (D-B-B)
- The most common delivery system is called the
traditional or standard approach or
design-bid-build, in which the employer assigns
the design and construction phases to two
different firms (consultant/designer and
contractor).
Appointing Main Contractor
Appointing Consultant
Constructing
Designing
13Traditional Approach (D-B-B)
- For many years, DBB has been the most common
method of project delivery for public projects,
and for many private projects as well. - Design Bid-Build is effective on projects
- where the owner needs both professional design
services and construction services - where the designer does not require detailed
knowledge of the means and methods of
construction. - DBB provides the owner with a high degree of
control. Thats why it is the preferred project
delivery system for owners who
14Traditional Approach (D-B-B)
- The owner defines project goals and objectives,
secures the financing, and specifies the
standards and contract terms. - The owner may perform planning, conceptual design
and full design, or may engage an outside design
professional (designer) for some or all of these
tasks. - During this planning and preliminary stage, owner
and designer work as a team to obtain required
permits and conduct necessary site
investigations. - The designer prepares the construction bid
documents to reflect the owners project goals
and objectives, the projects site conditions,
and sound engineering practices. - Prospective contractors prepare their bids from
these complete and specific bid documents. - The bidders submit their proposals to the owner,
who determines the most responsive (typically the
lowest) bid meeting project requirements. - In certain circumstances, owner may be justified
in selecting a contractor outright and
negotiating contract terms directly.
15Advantages of D-B-B Approach
- Applicable to a wide range of projects.
- Well established and easily understood.
- Clearly defined roles for all parties.
- Provides the lowest initial price that
competitive bidders can offer. - Extensive litigation has resulted in well
established legal precedents. - Insurance and bonding are well defined.
16Disadvantages of D-B-B Approach
- Least-cost approach requires higher level of
inspection. - Initial low bid might not result in ultimate
lowest cost or final best value. - Designers may have limited knowledge of the true
cost and scheduling implication of design
decisions.
17Design-Build Approach
- Design-build approach is a project delivery
system involving a single contract between the
project employer and a design-build contractor
covering both the design and construction of a
project. - The design-builder performs design, construction
engineering, and construction according to design
parameters, performance criteria and other
requirements established by the employer or his
representative.
Appointing design construction contractor
Constructing
Designing
Tendering
18Design-Build Approach
- The owner contracts with a single entity to
provide the design and to construct the project
according to that design. - The contract might be negotiated with a single
design-builder or result from competitive
proposals. - The selection can be based on low price or on a
set of value criteria (experience, staff, bonding
capacity, etc.). - Design-build provides the owner with a single
point of contact for project responsibilities,
eliminating the need to assist in resolving
designer-contractor disputes. - With the contractor playing a major role in
design, costs are typically defined and
maintained to a greater degree, and the
coordination of fast-track management to achieve
early completion is greatly simplified. - The design-builder makes many decisions that
owner would make under DBB, due to delegation of
greatly increased authority.
19Design-Build Approach
- For many owners, delegation of responsibilities
leads to satisfactory projects. However, if the
parties are inexperienced and do not cooperate,
the transfer of control and risk can be
disappointing. - The owner may need to restructure his/her
internal procedures to accommodate design-build
approach. - Compared to DBB, this involves a significantly
different set of requirements and expectations
for process, timelines and communications. - A clear understanding and documentation of
design-build processes enhances the quality of
design-build projects
20Advantage of Design-Build Approach
- Innovation and quality improvements through
- - Alternative designs and construction
methods - suited to the contractors capabilities
- - Flexibility in the selection of design,
materials, and - construction methods.
- Earlier schedule and cost certainty
-
21Disadvantage of Design-Build Approach
- Reduced opportunities for smaller, local
construction firms. - Fewer competitors and increased risk may result
in higher initial costs. - Elimination of traditional checks and balances.
Quality may be subordinated by cost or schedule
considerations. - Less Engineer control over final design.
- Higher procurement costs.
- Traditional funding may not support fast-tracking
construction or may require accelerated cash
flow. - Accelerated construction can potentially
overextend the workforce.
22Others
- Turnkey
- Turnkey Variations
- Direct Labor Approach.
- Construction management
23Turnkey
- Turnkey adds to the design-builders
responsibilities the operation and/or maintenance
of the completed project. - Turnkey delivery has the potential for bringing a
new project on line more quickly. - Three forms of turnkey project delivery
- Design-build-operate-transfer
- Design-build-operate-maintain
- Design-build-own-operate-transfer
24Turnkey Variation
- Variations on turnkey add financing as a key
component. While financing arrangements are
unique for each project, developer financed
projects generally resemble one of the turnkey
delivery methods - FDBT (Finance, design, build, transfer)
- FDBOT (Finance, design, build, operate, transfer)
- FDBOOT (Finance, design, build ,own, operate,
transfer) - In each case, the transfer of the project occurs
only after the developers interests and
financial obligations have been satisfied.
25Assignment (1)
- Describe the turnkey methods, turnkey variation
methods, direct labor approach, and construction
management method, highlighting on advantage and
disadvantage of each one.
26Lecture (3)
- The contract, and contract types, overview of
the construction documents.
27Contract Definition
- Agreement of at least two parties with purpose of
creating legal obligation between the parties and
capable of being enforced by the court of law. - Contract offer acceptance consideration
28Introduction to contracts
- Why Use contract in construction
- Describe scope of work
- Establish time frame
- Establish cost and payment provision
- Set fourth obligations and relationship
- Minimize disputes
- Improve economic return of investment
29Content of the contract
- Identify the parties
- Promises and responsibilities
- Scope of work
- Price and payment terms
- Commercial terms and conditions
- Project execution plan.
30Major Contract Types (traditional)
31Lump Sum Contract
- One price for the whole contract
- Lump sum includes costs plus overheads and
profits - Higher risk to contractor
- Price quoted is a guaranteed price as per
contract documents. - Payment based on a scheduled percentage scheme
(monthly progress claims) - The contractor is free to use means and methods
to complete the work and responsible for proper
performance - Work must be well defined at bid time.
- Fully developed plans and specifications
32Lump Sum Contract/ advantage
- Low risk on the owner, Higher risk to the
contractor - Cost known at outset
- Contractor will assign best personnel
- Contractor selection is easy.
33Lump Sum Contract/disadvantage
- Changes is difficult and costly.
- Contractor is free to use the lowest cost of
material equipment, methods.
34Unit Price
- Quote Rates / Prices by units
- No total final price
- Re-negotiate for rates if the quantity or work
considerably exceeds the initial target - Payment to contractor is based on the measure.
- Unbalanced bids
- Higher risk to owner
- Ideal for work where quantities can not be
accurately established before construction starts.
35Unit Price contract
- Require sufficient design definition to estimate
quantities of units - Contractors bid based on units of works
- Time cost risk (shared)
- Owner at risk for total quantities
- Contractor at risk for fixed unit price.
- Large quantities changes (gt15-25) can lead to
increase or decrease of unit price.
36Unit Price / Requirement
- Adequate breakdown and definition of work units
- Good quantity surveying and reporting system.
- Adequate drawings.
- Experience in developing BOQ
- Payment based on the measurement of the finished
works. - Quantity sensitive analysis of unit prices to
evaluate total bid price for potential quantity
variation.
37Unit Price / advantages
- Suitable for competitive bid
- Easy for contract selection
- Early start is possible
- Flexibility quantities and scope can be easily
adjusted
38Unit Price / disadvantages
- Final cost not known from the beginning (BOQ only
is estimated) - Staff needed to measure the finished quantities
and report on the units not completed. - Unit price sometime tend to draw unbalanced bid.
(For Unit-Price Contracts, a balanced bid is one
in which each bid is priced to carry its share of
the cost of the work and also its share of the
contractors profit. - Contractors raise prices on certain items and
make corresponding reductions of the prices on
other items ,without changing the total amount of
the bid)
39Cost Plus
- Actual cost plus a negotiated reimbursement to
cover overheads and profit. - different methods of reimbursement
- Cost percentage
- Cost fixed fee
- Cost fixed fee profit-sharing clause.
- Higher risk to owner
- Compromise guaranteed maximum price (GMP)
reduces risk to owner while maintain advantage of
cost plus contract. - By using this type of contract the contractor can
start work without a clearly defined project
scope, since all costs will be reimbursed and a
profit guaranteed.
40Cost Percent of Cost
- Fee percentage of the total project cost
- (Cost 500.000,Fee 2)
Advantages Disadvantages
profitable for the contractor No incentive to finish job quickly
Owner does not know total price
Larger the cost of the job, the higher the fee the owner pays
41Cost Fixed Fee
- Fee percentage of the original estimated total
figure - Utilized on large multi-year jobs
- Ex WW treatment plant Facility (Cost 20
million, Fee 1) - 20 Million 1 fee 200,000 Million
Advantages Disadvantages
Fee amount is fixed regardless of price fluctuation Expensive materials and construction techniques may be used to expedite construction
Provides incentive to complete the project quickly
42Cost Plus Fixed Fee
- Most common form of negotiated contracts
- COST expenses incurred by the contractor for
the construction of the facility - Includes Labor, equipment, materials, and
administrative costs - FEE compensation for expertise
- Includes profit
43Cost Fixed Fee Profit-Sharing Clause
- Rewards contractors who minimize cost
- Percentage of cost under GMP is considered profit
- and shared with the contractor
- Guaranteed Maximum Price (GMP)
- of profit sharing is specified in contract
Advantages Disadvantages
Provides incentive to the contractor to save money Contractor must absorb any amount over the GMP
Plans specs. need to detailed
44Cost Fixed Fee Profit-Sharing Clause
- variation of this type of contract is called a
guaranteed maximum price (GMP). - In this type of contract the contractor is
reimbursed at cost with an agreed-upon fee up to
the GMP, which is essentially a cap beyond this
point the contractor is responsible for covering
any additional costs within the original project
scope - An incentive clause, which specifies that the
contractor will receive additional profit for
bringing the project in under the GMP.
45 Construction Documents
- Bidding requirements
- Notice to Bidders
- Instruction to Bidders
- Proposal Form
- Contract Documents
- Contract Forms
- Conditions of the Contract
- Specifications
- Drawings
- Addenda
- Change Orders
- Agreement.
46 Construction Documents
- Construction Documents are defined as the written
and graphic documents prepared or assembled by
the A/E for communicating the design of the
project and administering the contract for its
construction. - 2 major groups
- 1.Bidding Requirements
- Used to attract bidders explains bidding
process - 2.Contract Documents
- Legally enforceable requirements that become
part of the contract - Include all construction documents except
bidding forms
47CONSTRUCTION DOCUMENTS
48CONSTRUCTION DOCUMENTSBIDDING REQUIREMENTS
- BIDDING REQUIREMENTS
- Bidding Requirements are used to attract bidders
and explain the procedures to be followed in
preparing and submitting bids . - Bidding requirements help bidders follow
established procedures and submit bids that will
not be disqualified because of technicalities.
They do not become part of the contract documents - Bidding documents
- All of the construction documents issued to
bidders before the signing of an owner-contractor
agreement.
49Bid Package
- Documents available to the contractor and on
which he must make a decision to bid or not - A set of plans and technical specifications,
Proposal form, general conditions, special
conditions, - Description of the project to be constructed
- Bid Package is prepared by
502-1 Instruction to bidders
- It describe the scope of the bid, source of fund
(if it is financed from other agency), fraudulent
and fraud practices, eligible bidders, Eligible
Materials, Equipment and Services, Clarification
of Bidding Document, Site Visit, Pre-Bid Meeting,
Amendment of Bidding Document
512-1 Instruction to bidders (contd)
- See attached example for ITB.
522-2 Bid Data Sheet (BDS)
- Definitions, Engineers Authority to Issue
Variations, Performance Security, Inspection of
Site, Program to Be Submitted, Cash Flow Estimate - Bid Security, Minimum Amount of Third Party
Insurance - Time for Issue of the Notice to Commence, Time
for Completion - Amount of Liquidated Damages, Limit of Liquidated
Damages - Amount of Bonus for Early Completion, Limit of
Bonus - Defects Liability Period, Amount of Interim
Payment Certificates - Percentage of Retention, Limit of Retention
Money, Amount of Advance Payment - Start Repayment of Advance Payment, Monthly
Recovery of Advance Payment - Number of Copies of Statement of Completion and
Final Statement - Procedure for Settlement of Disputes
- Notice to Employer and Engineer
- Origin of Materials and Plant
532-3Evaluation and qualification
- This section contains all the criteria that the
Employer shall use to evaluate bids and qualify
Bidders if the bidding was not preceded by a
prequalification exercise and post qualification
is applied. - In accordance with items specified in ITB, no
other methods, criteria and factors shall be
used. The Bidder shall provide all the
information requested in the forms included in
(Bidding Forms) section..
542-3Evaluation and qualification (cond)
- 1- evaluation describe the Adequacy of
Technical Proposal, in case of Multiple
Contracts, the conditions governs, Completion
Time, - 2- Qualification describe the Eligibility,
financial situation, staff, experience ,
equipments.
552-4 Bidding forms
- letter of bid (bid form)
- Form of bid security
- Technical proposal forms (personnel, equipment)
- Bidders qualification forms as bidders data, JV
information, Historical Contract Non-Performance,
Current Contract Commitments , Historical
Financial Performance, Average Annual Turnover,
General and specific Experience,
56 57CONSTRUCTION DOCUMENTS
58CONSTRUCTION DOCUMENTS
- Contract documents (graphic and written) describe
the proposed construction (the Work) that
results from performing services, furnishing
labor, and supplying and incorporating materials
and equipment into the construction - Contract Forms
- Conditions of the Contract
- Specifications BOQ
- Drawings
- Addenda
- Change Orders
59A. CONTRACT FORMS
- CONTRACT FORMS
- Agreement
- Performance Bond
- Payment Bond
- Certificates
60B.CONDITIONS OF CONTRACT
- CONDITIONS OF CONTRACT
- Define basic rights, responsibilities, and
relationships of the parties involved in the
construction project. - 2 types General Conditions and Supplementary
Conditions - GENERAL CONDITIONS
- General clauses that establish how the project
is to be administered. - Contain basic expressions of rights, duties, and
limitations of the entities involved. - Usually in the form of published standard
documents that include principles common to most
construction Contracts. - SUPPLEMENTARY CONDITIONS
- Modify or supplement general conditions as need
to provide for requirements specific to a
project. They are not standardized documents and
are prepared for specific project needs.
61A.1 Agreement
- The written document signed by the owner and the
contractor that is the legal instrument binding
the parties to the contract. - Defines the relationship and obligations
between owner and contractor. - The agreement is quite brief and appears to
consist mostly of statements of fact, whereas the
general conditions section deals primarily with
matters that pertain generally to be construction
work and the persons involved. - In other words, the agreement appears to consist
of statements and the general conditions appear
to be terms, or conditions.
62Agreement (contd)
- The agreement should contain
- The names of contracting parties
- A brief description of the work
- A list of contract documents, including
agreement, general conditions, drawings, and
specifications. - The contract sum, or amount (lump-sum contract)
- The procedures for payment
- The contract time, or dates for start and
completion - The signatures of contracting parties and
witnesses - International construction documents are also
often based on industry-prepared standard forms.
63AGREEMENT FORM
- A number of organizations prepare recommended
standard general conditions and associated forms.
Such as - ENAA (Engineering Advancement Association of
Japan) - FIDIC (International Federation of Consulting
Engineers) - ICE (Institute of Civil Engineers, United
Kingdom) - JCT (Joint Contracts Tribunal)
- SEE ATTACHED WORD FILE FOR EXAMPLES
64A.2 .Bonds / Guarantees FORMS
- 1- PERFORMANCE BOND / security
- The Contractor, upon receiving the Letter of
Acceptance, shall obtain and provide to the
Employer before signing the Contract, the
Performance Guarantee in the value of ten percent
of the Contract Sum, as a guarantee of the proper
execution of the Works in accordance with the
Contract. This guarantee shall be issued by a
licensed bank or financial institution acceptable
to the Employer. The guarantee shall be prepared
in the form included in part B of these
conditions. The obtaining of such guarantee
shall in all respects be at the expense of the
Contractor.The Performance Security shall be
provided to the Employer no later than the date
specified in the Letter of Acceptance and shall
be issued in an amount specified in the PCC
(particular conditions of contract), by a bank or
surety acceptable to the Employer, and
denominated in the types and proportions of the
currencies in which the Contract Price is
payable. - The Performance Security shall be valid until a
date 28 days from the date of issue of the
Certificate of Completion in the case of a Bank
Guarantee, and until one year from the date of
issue of the Completion Certificate in the case
of a Performance Bond. - In general , it is 10 of contract value
- Defect liability
- CERTIFICATES
- Includes certificates of insurance, certificates
of compliance with applicable laws and
regulations.
65Advanced payment bond
- Provide a guarantee that subcontractor, material
suppliers, and others providing labor, material
goods, and services to the project will be paid. - The Employer shall make advance payment to the
Contractor of the amounts stated in the PCC by
the date stated in the PCC, against provision by
the Contractor of an Unconditional Bank Guarantee
in a form and by a bank acceptable to the
Employer in amounts and currencies equal to the
advance payment. The Guarantee shall remain
effective until the advance payment has been
repaid, but the amount of the Guarantee shall be
progressively reduced by the amounts repaid by
the Contractor. Interest shall not be charged on
the advance payment.
66Advanced payment bond (contd)
- The Contractor is to use the advance payment only
to pay for Equipment, Plant, Materials, and
mobilization expenses required specifically for
execution of the Contract. The Contractor shall
demonstrate that advance payment has been used in
this way by supplying copies of invoices or other
documents to the Project Manager. - The advance payment shall be repaid by deducting
proportionate amounts from payments otherwise due
to the Contractor, following the schedule of
completed percentages of the Works on a payment
basis. No account shall be taken of the advance
payment or its repayment in assessing valuations
of work done, Variations, price adjustments,
Compensation Events, Bonuses, or Liquidated
Damages.
67Defect liability Security
- After primary taking over, 5 guarantee is
submitted to employer for defect liability, valid
for 365 days or as stipulated in PCC.
68INSURANCE Certificates
- Insurance for Works and Contractors Equipment,
- Insurance against Injury to Persons and Damage to
Property , - Insurance for Contractors Personnel
69General Conditions of contract
- The conditions are intended to govern and
regulate the obligation of formal contract. - Although the headings and topics included within
different sets of GCC vary, there is a certain
similarity of subject matter
70Contents of GCC
- Definitions
- Contract documents
- Rights and responsibilities of owner
- Duties and authorities of engineer
- Rights and responsibilities of contractor
- Sub-contractor, Separate contractors
- Time
- Payments and completions
- Changes in the work
- Protection of persons and property
- Insurance and bond
- Disputes
- Termination of contract
- Miscellaneous provisions