CONSTRUCTION CONTRACTS DOCUEMENTS - PowerPoint PPT Presentation

1 / 70
About This Presentation
Title:

CONSTRUCTION CONTRACTS DOCUEMENTS

Description:

CONSTRUCTION CONTRACTS DOCUEMENTS BY LECTURER Maha Muhaisen APPLIED CIVIL ENGINEERING DEPT Advanced payment bond (cont d) The Contractor is to use the advance ... – PowerPoint PPT presentation

Number of Views:3066
Avg rating:3.0/5.0
Slides: 71
Provided by: Maha73
Category:

less

Transcript and Presenter's Notes

Title: CONSTRUCTION CONTRACTS DOCUEMENTS


1
CONSTRUCTION CONTRACTS DOCUEMENTS
BYLECTURERMaha Muhaisen
  • APPLIED CIVIL ENGINEERING DEPT

2
Resources
  • Construction Documents and Contracting, Joseph D.
    Coleman , 2004, Prentice Hall
  • Construction Contracts, Keith Collier, 1987,
    Prentice Hall
  • Construction Management, by Daniel W. Halpin
    and Ronald W. Woodhead, 2nd Edition , John Wiley
    Sons
  • Fidic Conditions of Contract for Construction,
    FOR BUILDING AND ENGINEERING WORKS DESIGNED BY
    THE EMPLOYER, 2005
  • Fidic Tendering Procedures, prequalification,
    tendering and award the contract, 1994.
  • Handouts and lecture notes

3
Grades
  • Research Projects homework 30
  • Midterm Exam. 30
  • Final Exam. 40

4
Course Outline
  • Introduction to construction project stages,
    overview of the construction contracting methods,
    and contracts types.
  • Bidding document
  • Invitation to bid
  • Instruction to bidders
  • Information to bidders bid data
  • Biding Forms
  • General conditions of contract
  • Specific condition of contract
  • Specification
  • BOQ
  • Drawings
  • Contract forms
  • Methods of Tendering, Bidding and Awarding
  • Contract Documents and Conditions
  • FIDIC Form of Contracts

5
  • Introduction to Construction Project Stages
  • Lecture (1)

6
Major Project Phases
  • The major phases in the project cycle that are
    common to most design and construction projects
    are
  • Project Planning
  • Design
  • Schematic Design
  • Design Development
  • Contract Documents
  • Construction Procurement (Bidding Phase)
  • Construction
  • Post Construction

7
Construction Project Characteristics
  • Construction projects are different than other
    types of projects due to the following
    characteristics
  • Construction projects are complex undertaking.
  • Every construction project is unique.
  • Construction projects involve a lot of
    uncertainties, lack of information and variables.

8
Project Life Cycle
  • Most of Construction projects life-cycle have
    common characteristics, Construction projects
    start with low cost and resources, high risk and
    uncertainty.
  • The life-cycle of a typical construction project
    could be summarized as following
  • Stage I represents the project formulation,
    feasibility studies, and the strategic decisions
    needed for project continue.
  • Stage II represents planning, basic design,
    budgeting, tendering and placing the project
    major contracts.
  • Stage III involves the construction phase of
    the project, equipment installation and testing.
  • Stage IV represents the final phase in the
    project which includes the project turnover,
    final testing and start-up.

9
Project Life Cycle
10
(No Transcript)
11
  • Lecture (2)

12
Construction Contracting Method (delivery
methods)
  • Traditional Approach (D-B-B)
  • The most common delivery system is called the
    traditional or standard approach or
    design-bid-build, in which the employer assigns
    the design and construction phases to two
    different firms (consultant/designer and
    contractor).

Appointing Main Contractor
Appointing Consultant
Constructing
Designing
13
Traditional Approach (D-B-B)
  • For many years, DBB has been the most common
    method of project delivery for public projects,
    and for many private projects as well.
  • Design Bid-Build is effective on projects
  • where the owner needs both professional design
    services and construction services
  • where the designer does not require detailed
    knowledge of the means and methods of
    construction.
  • DBB provides the owner with a high degree of
    control. Thats why it is the preferred project
    delivery system for owners who

14
Traditional Approach (D-B-B)
  • The owner defines project goals and objectives,
    secures the financing, and specifies the
    standards and contract terms.
  • The owner may perform planning, conceptual design
    and full design, or may engage an outside design
    professional (designer) for some or all of these
    tasks.
  • During this planning and preliminary stage, owner
    and designer work as a team to obtain required
    permits and conduct necessary site
    investigations.
  • The designer prepares the construction bid
    documents to reflect the owners project goals
    and objectives, the projects site conditions,
    and sound engineering practices.
  • Prospective contractors prepare their bids from
    these complete and specific bid documents.
  • The bidders submit their proposals to the owner,
    who determines the most responsive (typically the
    lowest) bid meeting project requirements.
  • In certain circumstances, owner may be justified
    in selecting a contractor outright and
    negotiating contract terms directly.

15
Advantages of D-B-B Approach
  • Applicable to a wide range of projects.
  • Well established and easily understood.
  • Clearly defined roles for all parties.
  • Provides the lowest initial price that
    competitive bidders can offer.
  • Extensive litigation has resulted in well
    established legal precedents.
  • Insurance and bonding are well defined.

16
Disadvantages of D-B-B Approach
  • Least-cost approach requires higher level of
    inspection.
  • Initial low bid might not result in ultimate
    lowest cost or final best value.
  • Designers may have limited knowledge of the true
    cost and scheduling implication of design
    decisions.

17
Design-Build Approach
  • Design-build approach is a project delivery
    system involving a single contract between the
    project employer and a design-build contractor
    covering both the design and construction of a
    project.
  • The design-builder performs design, construction
    engineering, and construction according to design
    parameters, performance criteria and other
    requirements established by the employer or his
    representative.

Appointing design construction contractor
Constructing
Designing
Tendering
18
Design-Build Approach
  • The owner contracts with a single entity to
    provide the design and to construct the project
    according to that design.
  • The contract might be negotiated with a single
    design-builder or result from competitive
    proposals.
  • The selection can be based on low price or on a
    set of value criteria (experience, staff, bonding
    capacity, etc.).
  • Design-build provides the owner with a single
    point of contact for project responsibilities,
    eliminating the need to assist in resolving
    designer-contractor disputes.
  • With the contractor playing a major role in
    design, costs are typically defined and
    maintained to a greater degree, and the
    coordination of fast-track management to achieve
    early completion is greatly simplified.
  • The design-builder makes many decisions that
    owner would make under DBB, due to delegation of
    greatly increased authority.

19
Design-Build Approach
  • For many owners, delegation of responsibilities
    leads to satisfactory projects. However, if the
    parties are inexperienced and do not cooperate,
    the transfer of control and risk can be
    disappointing.
  • The owner may need to restructure his/her
    internal procedures to accommodate design-build
    approach.
  • Compared to DBB, this involves a significantly
    different set of requirements and expectations
    for process, timelines and communications.
  • A clear understanding and documentation of
    design-build processes enhances the quality of
    design-build projects

20
Advantage of Design-Build Approach
  • Innovation and quality improvements through
  • - Alternative designs and construction
    methods
  • suited to the contractors capabilities
  • - Flexibility in the selection of design,
    materials, and
  • construction methods.
  • Earlier schedule and cost certainty

21
Disadvantage of Design-Build Approach
  • Reduced opportunities for smaller, local
    construction firms.
  • Fewer competitors and increased risk may result
    in higher initial costs.
  • Elimination of traditional checks and balances.
    Quality may be subordinated by cost or schedule
    considerations.
  • Less Engineer control over final design.
  • Higher procurement costs.
  • Traditional funding may not support fast-tracking
    construction or may require accelerated cash
    flow.
  • Accelerated construction can potentially
    overextend the workforce.

22
Others
  • Turnkey
  • Turnkey Variations
  • Direct Labor Approach.
  • Construction management

23
Turnkey
  • Turnkey adds to the design-builders
    responsibilities the operation and/or maintenance
    of the completed project.
  • Turnkey delivery has the potential for bringing a
    new project on line more quickly.
  • Three forms of turnkey project delivery
  • Design-build-operate-transfer
  • Design-build-operate-maintain
  • Design-build-own-operate-transfer

24
Turnkey Variation
  • Variations on turnkey add financing as a key
    component. While financing arrangements are
    unique for each project, developer financed
    projects generally resemble one of the turnkey
    delivery methods
  • FDBT (Finance, design, build, transfer)
  • FDBOT (Finance, design, build, operate, transfer)
  • FDBOOT (Finance, design, build ,own, operate,
    transfer)
  • In each case, the transfer of the project occurs
    only after the developers interests and
    financial obligations have been satisfied.

25
Assignment (1)
  • Describe the turnkey methods, turnkey variation
    methods, direct labor approach, and construction
    management method, highlighting on advantage and
    disadvantage of each one.

26
Lecture (3)
  • The contract, and contract types, overview of
    the construction documents.

27
Contract Definition
  • Agreement of at least two parties with purpose of
    creating legal obligation between the parties and
    capable of being enforced by the court of law.
  • Contract offer acceptance consideration

28
Introduction to contracts
  • Why Use contract in construction
  • Describe scope of work
  • Establish time frame
  • Establish cost and payment provision
  • Set fourth obligations and relationship
  • Minimize disputes
  • Improve economic return of investment

29
Content of the contract
  • Identify the parties
  • Promises and responsibilities
  • Scope of work
  • Price and payment terms
  • Commercial terms and conditions
  • Project execution plan.

30
Major Contract Types (traditional)
31
Lump Sum Contract
  • One price for the whole contract
  • Lump sum includes costs plus overheads and
    profits
  • Higher risk to contractor
  • Price quoted is a guaranteed price as per
    contract documents.
  • Payment based on a scheduled percentage scheme
    (monthly progress claims)
  • The contractor is free to use means and methods
    to complete the work and responsible for proper
    performance
  • Work must be well defined at bid time.
  • Fully developed plans and specifications

32
Lump Sum Contract/ advantage
  • Low risk on the owner, Higher risk to the
    contractor
  • Cost known at outset
  • Contractor will assign best personnel
  • Contractor selection is easy.

33
Lump Sum Contract/disadvantage
  • Changes is difficult and costly.
  • Contractor is free to use the lowest cost of
    material equipment, methods.

34
Unit Price
  • Quote Rates / Prices by units
  • No total final price
  • Re-negotiate for rates if the quantity or work
    considerably exceeds the initial target
  • Payment to contractor is based on the measure.
  • Unbalanced bids
  • Higher risk to owner
  • Ideal for work where quantities can not be
    accurately established before construction starts.

35
Unit Price contract
  • Require sufficient design definition to estimate
    quantities of units
  • Contractors bid based on units of works
  • Time cost risk (shared)
  • Owner at risk for total quantities
  • Contractor at risk for fixed unit price.
  • Large quantities changes (gt15-25) can lead to
    increase or decrease of unit price.

36
Unit Price / Requirement
  • Adequate breakdown and definition of work units
  • Good quantity surveying and reporting system.
  • Adequate drawings.
  • Experience in developing BOQ
  • Payment based on the measurement of the finished
    works.
  • Quantity sensitive analysis of unit prices to
    evaluate total bid price for potential quantity
    variation.

37
Unit Price / advantages
  • Suitable for competitive bid
  • Easy for contract selection
  • Early start is possible
  • Flexibility quantities and scope can be easily
    adjusted

38
Unit Price / disadvantages
  • Final cost not known from the beginning (BOQ only
    is estimated)
  • Staff needed to measure the finished quantities
    and report on the units not completed.
  • Unit price sometime tend to draw unbalanced bid.
    (For Unit-Price Contracts, a balanced bid is one
    in which each bid is priced to carry its share of
    the cost of the work and also its share of the
    contractors profit.
  • Contractors raise prices on certain items and
    make corresponding reductions of the prices on
    other items ,without changing the total amount of
    the bid)

39
Cost Plus
  • Actual cost plus a negotiated reimbursement to
    cover overheads and profit.
  • different methods of reimbursement
  • Cost percentage
  • Cost fixed fee
  • Cost fixed fee profit-sharing clause.
  • Higher risk to owner
  • Compromise guaranteed maximum price (GMP)
    reduces risk to owner while maintain advantage of
    cost plus contract.
  • By using this type of contract the contractor can
    start work without a clearly defined project
    scope, since all costs will be reimbursed and a
    profit guaranteed.

40
Cost Percent of Cost
  • Fee percentage of the total project cost
  • (Cost 500.000,Fee 2)

Advantages Disadvantages
profitable for the contractor No incentive to finish job quickly
Owner does not know total price
Larger the cost of the job, the higher the fee the owner pays
41
Cost Fixed Fee
  • Fee percentage of the original estimated total
    figure
  • Utilized on large multi-year jobs
  • Ex WW treatment plant Facility (Cost 20
    million, Fee 1)
  • 20 Million 1 fee 200,000 Million

Advantages Disadvantages
Fee amount is fixed regardless of price fluctuation Expensive materials and construction techniques may be used to expedite construction
Provides incentive to complete the project quickly
42
Cost Plus Fixed Fee
  • Most common form of negotiated contracts
  • COST expenses incurred by the contractor for
    the construction of the facility
  • Includes Labor, equipment, materials, and
    administrative costs
  • FEE compensation for expertise
  • Includes profit

43
Cost Fixed Fee Profit-Sharing Clause
  • Rewards contractors who minimize cost
  • Percentage of cost under GMP is considered profit
  • and shared with the contractor
  • Guaranteed Maximum Price (GMP)
  • of profit sharing is specified in contract

Advantages Disadvantages
Provides incentive to the contractor to save money Contractor must absorb any amount over the GMP
Plans specs. need to detailed
44
Cost Fixed Fee Profit-Sharing Clause
  • variation of this type of contract is called a
    guaranteed maximum price (GMP).
  • In this type of contract the contractor is
    reimbursed at cost with an agreed-upon fee up to
    the GMP, which is essentially a cap beyond this
    point the contractor is responsible for covering
    any additional costs within the original project
    scope
  • An incentive clause, which specifies that the
    contractor will receive additional profit for
    bringing the project in under the GMP.

45
Construction Documents
  • Bidding requirements
  • Notice to Bidders
  • Instruction to Bidders
  • Proposal Form
  • Contract Documents
  • Contract Forms
  • Conditions of the Contract
  • Specifications
  • Drawings
  • Addenda
  • Change Orders
  • Agreement.

46
Construction Documents
  • Construction Documents are defined as the written
    and graphic documents prepared or assembled by
    the A/E for communicating the design of the
    project and administering the contract for its
    construction.
  • 2 major groups
  • 1.Bidding Requirements
  • Used to attract bidders explains bidding
    process
  • 2.Contract Documents
  • Legally enforceable requirements that become
    part of the contract
  • Include all construction documents except
    bidding forms

47
CONSTRUCTION DOCUMENTS
48
CONSTRUCTION DOCUMENTSBIDDING REQUIREMENTS
  • BIDDING REQUIREMENTS
  • Bidding Requirements are used to attract bidders
    and explain the procedures to be followed in
    preparing and submitting bids .
  • Bidding requirements help bidders follow
    established procedures and submit bids that will
    not be disqualified because of technicalities.
    They do not become part of the contract documents
  • Bidding documents
  • All of the construction documents issued to
    bidders before the signing of an owner-contractor
    agreement.

49
Bid Package
  • Documents available to the contractor and on
    which he must make a decision to bid or not
  • A set of plans and technical specifications,
    Proposal form, general conditions, special
    conditions,
  • Description of the project to be constructed
  • Bid Package is prepared by

50
2-1 Instruction to bidders
  • It describe the scope of the bid, source of fund
    (if it is financed from other agency), fraudulent
    and fraud practices, eligible bidders, Eligible
    Materials, Equipment and Services, Clarification
    of Bidding Document, Site Visit, Pre-Bid Meeting,
    Amendment of Bidding Document

51
2-1 Instruction to bidders (contd)
  • See attached example for ITB.

52
2-2 Bid Data Sheet (BDS)
  • Definitions, Engineers Authority to Issue
    Variations, Performance Security, Inspection of
    Site, Program to Be Submitted, Cash Flow Estimate
  • Bid Security, Minimum Amount of Third Party
    Insurance
  • Time for Issue of the Notice to Commence, Time
    for Completion
  • Amount of Liquidated Damages, Limit of Liquidated
    Damages
  • Amount of Bonus for Early Completion, Limit of
    Bonus
  • Defects Liability Period, Amount of Interim
    Payment Certificates
  • Percentage of Retention, Limit of Retention
    Money, Amount of Advance Payment
  • Start Repayment of Advance Payment, Monthly
    Recovery of Advance Payment
  • Number of Copies of Statement of Completion and
    Final Statement
  • Procedure for Settlement of Disputes
  • Notice to Employer and Engineer
  • Origin of Materials and Plant

53
2-3Evaluation and qualification
  • This section contains all the criteria that the
    Employer shall use to evaluate bids and qualify
    Bidders if the bidding was not preceded by a
    prequalification exercise and post qualification
    is applied.
  • In accordance with items specified in ITB, no
    other methods, criteria and factors shall be
    used. The Bidder shall provide all the
    information requested in the forms included in
    (Bidding Forms) section..

54
2-3Evaluation and qualification (cond)
  • 1- evaluation describe the Adequacy of
    Technical Proposal, in case of Multiple
    Contracts, the conditions governs, Completion
    Time,
  • 2- Qualification describe the Eligibility,
    financial situation, staff, experience ,
    equipments.

55
2-4 Bidding forms
  • letter of bid (bid form)
  • Form of bid security
  • Technical proposal forms (personnel, equipment)
  • Bidders qualification forms as bidders data, JV
    information, Historical Contract Non-Performance,
    Current Contract Commitments , Historical
    Financial Performance, Average Annual Turnover,
    General and specific Experience,

56
  • See attached file

57
CONSTRUCTION DOCUMENTS
58
CONSTRUCTION DOCUMENTS
  • Contract documents (graphic and written) describe
    the proposed construction (the Work) that
    results from performing services, furnishing
    labor, and supplying and incorporating materials
    and equipment into the construction
  • Contract Forms
  • Conditions of the Contract
  • Specifications BOQ
  • Drawings
  • Addenda
  • Change Orders

59
A. CONTRACT FORMS
  • CONTRACT FORMS
  • Agreement
  • Performance Bond
  • Payment Bond
  • Certificates

60
B.CONDITIONS OF CONTRACT
  • CONDITIONS OF CONTRACT
  • Define basic rights, responsibilities, and
    relationships of the parties involved in the
    construction project.
  • 2 types General Conditions and Supplementary
    Conditions
  • GENERAL CONDITIONS
  • General clauses that establish how the project
    is to be administered.
  • Contain basic expressions of rights, duties, and
    limitations of the entities involved.
  • Usually in the form of published standard
    documents that include principles common to most
    construction Contracts.
  • SUPPLEMENTARY CONDITIONS
  • Modify or supplement general conditions as need
    to provide for requirements specific to a
    project. They are not standardized documents and
    are prepared for specific project needs.

61
A.1 Agreement
  • The written document signed by the owner and the
    contractor that is the legal instrument binding
    the parties to the contract.
  • Defines the relationship and obligations
    between owner and contractor.
  • The agreement is quite brief and appears to
    consist mostly of statements of fact, whereas the
    general conditions section deals primarily with
    matters that pertain generally to be construction
    work and the persons involved.
  • In other words, the agreement appears to consist
    of statements and the general conditions appear
    to be terms, or conditions.

62
Agreement (contd)
  • The agreement should contain
  • The names of contracting parties
  • A brief description of the work
  • A list of contract documents, including
    agreement, general conditions, drawings, and
    specifications.
  • The contract sum, or amount (lump-sum contract)
  • The procedures for payment
  • The contract time, or dates for start and
    completion
  • The signatures of contracting parties and
    witnesses
  • International construction documents are also
    often based on industry-prepared standard forms.

63
AGREEMENT FORM
  • A number of organizations prepare recommended
    standard general conditions and associated forms.
    Such as
  • ENAA (Engineering Advancement Association of
    Japan)
  • FIDIC (International Federation of Consulting
    Engineers)
  • ICE (Institute of Civil Engineers, United
    Kingdom)
  • JCT (Joint Contracts Tribunal)
  • SEE ATTACHED WORD FILE FOR EXAMPLES

64
A.2 .Bonds / Guarantees FORMS
  • 1- PERFORMANCE BOND / security
  • The Contractor, upon receiving the Letter of
    Acceptance, shall obtain and provide to the
    Employer before signing the Contract, the
    Performance Guarantee in the value of ten percent
    of the Contract Sum, as a guarantee of the proper
    execution of the Works in accordance with the
    Contract. This guarantee shall be issued by a
    licensed bank or financial institution acceptable
    to the Employer. The guarantee shall be prepared
    in the form included in part B of these
    conditions. The obtaining of such guarantee
    shall in all respects be at the expense of the
    Contractor.The Performance Security shall be
    provided to the Employer no later than the date
    specified in the Letter of Acceptance and shall
    be issued in an amount specified in the PCC
    (particular conditions of contract), by a bank or
    surety acceptable to the Employer, and
    denominated in the types and proportions of the
    currencies in which the Contract Price is
    payable.
  • The Performance Security shall be valid until a
    date 28 days from the date of issue of the
    Certificate of Completion in the case of a Bank
    Guarantee, and until one year from the date of
    issue of the Completion Certificate in the case
    of a Performance Bond.
  • In general , it is 10 of contract value
  • Defect liability
  • CERTIFICATES
  • Includes certificates of insurance, certificates
    of compliance with applicable laws and
    regulations.

65
Advanced payment bond
  • Provide a guarantee that subcontractor, material
    suppliers, and others providing labor, material
    goods, and services to the project will be paid.
  • The Employer shall make advance payment to the
    Contractor of the amounts stated in the PCC by
    the date stated in the PCC, against provision by
    the Contractor of an Unconditional Bank Guarantee
    in a form and by a bank acceptable to the
    Employer in amounts and currencies equal to the
    advance payment. The Guarantee shall remain
    effective until the advance payment has been
    repaid, but the amount of the Guarantee shall be
    progressively reduced by the amounts repaid by
    the Contractor. Interest shall not be charged on
    the advance payment.

66
Advanced payment bond (contd)
  • The Contractor is to use the advance payment only
    to pay for Equipment, Plant, Materials, and
    mobilization expenses required specifically for
    execution of the Contract. The Contractor shall
    demonstrate that advance payment has been used in
    this way by supplying copies of invoices or other
    documents to the Project Manager.
  • The advance payment shall be repaid by deducting
    proportionate amounts from payments otherwise due
    to the Contractor, following the schedule of
    completed percentages of the Works on a payment
    basis. No account shall be taken of the advance
    payment or its repayment in assessing valuations
    of work done, Variations, price adjustments,
    Compensation Events, Bonuses, or Liquidated
    Damages.

67
Defect liability Security
  • After primary taking over, 5 guarantee is
    submitted to employer for defect liability, valid
    for 365 days or as stipulated in PCC.

68
INSURANCE Certificates
  • Insurance for Works and Contractors Equipment,
  • Insurance against Injury to Persons and Damage to
    Property ,
  • Insurance for Contractors Personnel

69
General Conditions of contract
  • The conditions are intended to govern and
    regulate the obligation of formal contract.
  • Although the headings and topics included within
    different sets of GCC vary, there is a certain
    similarity of subject matter

70
Contents of GCC
  • Definitions
  • Contract documents
  • Rights and responsibilities of owner
  • Duties and authorities of engineer
  • Rights and responsibilities of contractor
  • Sub-contractor, Separate contractors
  • Time
  • Payments and completions
  • Changes in the work
  • Protection of persons and property
  • Insurance and bond
  • Disputes
  • Termination of contract
  • Miscellaneous provisions
Write a Comment
User Comments (0)
About PowerShow.com