Grid Connection Issues - PowerPoint PPT Presentation

1 / 9
About This Presentation
Title:

Grid Connection Issues

Description:

Grid Connection Issues Micro Hydro Projects Rachel Hodges Where, and how suitable is the Grid ? Tend to be in awkward locations Consider during initial ... – PowerPoint PPT presentation

Number of Views:57
Avg rating:3.0/5.0
Slides: 10
Provided by: engineeri75
Category:

less

Transcript and Presenter's Notes

Title: Grid Connection Issues


1
Grid Connection Issues
  • Micro Hydro Projects
  • Rachel Hodges

2
Where, and how suitable is the Grid?
  • Tend to be in awkward locations
  • Consider during initial feasibility
  • Can be a go/no-go decision maker
  • Look at
  • Distance
  • Single / 3 Phase
  • Voltage
  • Local Loads
  • Switchgear and Ratings
  • Accommodation

3
Synchronising
  • Synchronous Machine
  • Need inverters and controllers to match frequency
    of the grid
  • Need to consider harmonic content
  • Can operate in islanded system
  • Asynchronous or Induction Machines
  • Automatically match frequency of the grid
  • Need power factor control (switchable capacitors
    or DFIG)

4
G83 versus G59
  • G83
  • G59
  • For up to 16A per phase (6kW at Low Voltage)
  • Equipment G83 Certification
  • Notify the Distribution Network Operator (DNO)
  • For up to 5MW at 20kV
  • Connection application, connection offer and
    witness testing required.

5
Connection Application
  • DNO will look at
  • Transformer and connection capacity
  • Abnormal feed conditions
  • Fault Levels
  • Voltage Rise (P28)
  • Voltage Step Change, Flicker and Harmonics (G5/4)
  • Loss of Mains (Islanding) Protection and Earthing
    (G59)

6
Connection Offer
  • Can take up to 90 days
  • Connection offer will indicate
  • Non-contestable work and costs (to be undertaken
    by DNO)
  • Contestable work (undertaken by accredited 3rd
    party or DNO)
  • Constraints
  • Timeframes

7
G59 Protection
  • Under and Over Voltage
  • Under and Over Frequency
  • Loss of Mains (ROCOF, Vector Shift, Intertripping)

8
Metering
  • ROCs
  • Import / Export
  • Export MPAN from Supplier
  • Power Purchase Agreements
  • Benefits of Onsite Generation

9
Grid Connection Issues
  • Micro Hydro Projects
  • Rachel Hodges